1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2111901 MGR.NO. 058 PAGE 001 CONT 6219 SEC 93 JOB 001 RES ENGR JUNEAU, STEVE PROJ RMC - 621993001 HWY IH0030 300 E. LOOP 390 N MARSHAL CNTY BOWIE DIST 19 CONTRACT PRICE $ 115,020.00 REPORT DATE 05/04/2012 10.17.38 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD MAR 01,2011 TO MAR 31,2012 EST NO 014 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 01, 2011 TIME COMPUTED FROM MAR 08, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 306 366 309 57 BROUGHT FORWARD ADDL DAYS GRANTED = 33 MAR 12 1 1 TOTAL DAYS ALLOWED = 339 2 1 DATE WORK COMPLETED 03/31/12 3 1 DAYS CHARGED TO DATE = 336 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 500 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 SUNDAY CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 SUNDAY 19 1 20 1 21 1 22 1 23 1 24 1 25 1 SUNDAY 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 397 336 61 0 SATURDAY 4 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2111901 MGR.NO. 058 PAGE 001 CONT 6219 SEC 93 JOB 001 RES ENGR JUNEAU, STEVE PROJ RMC - 621993001 HWY IH0030 300 E. LOOP 390 N MARSHAL CNTY BOWIE DIST 19 CONTRACT PRICE $ 115,020.00 REPORT DATE 05/04/2012 10.17.38 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD MAR 01,2011 TO MAR 31,2012 EST NO 014 & FINAL DIST. 19 COUNTY BOWIE CONTROL 6219-93-001 PROJECT RMC - 621993001 HIGHWAY IH0030 0LIMITS- VARIOUS . 0TYPE OF WORK- CALLOUT CABLE BARRIER REPAIR 0 0005 PREPARED BY ROBERT H. RATCLIFF, P.E. 0 0055 CALLOUT CABLE BARRIER REPAIR NET LENGTH 99.360 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0432 RIPRAP (MOW STRIP)(4 IN) CY 30.000 6.850 200.000 1,370.00 0065 7224 REPLACE POSTS (TL-3) EA 1,600.000 1,397.000 65.000 90,805.00 0070 7224 CABLE SPLICE / TURNBUCKLE (TL-3) EA 24.000 5.000 10.000 50.00 0075 7224 REPAIR CONCRETE FOUNDATION (TL-3) EA 21.000 0.000 20.000 .00 0080 7224 REPR OR REPLC CABLE BARR TERM SEC(TL-3) EA 36.000 21.000 10.000 210.00 0085 7224 REPLACE CABLE (TL-3) LF 4,000.000 0.000 1.000 .00 0090 5367*CABLE BARRIER SYSTEM (TL-3) LF 250.000 105.000 10.000 1,050.00 0095 5367*CABLE BARRIER TERMINAL SECTION (TL-3) EA 8.000 8.000 1,000.000 8,000.00 0100 9000*REMOVE CABLE,POST,CONC FOOTING, MOW EA 4.000 4.000 2,000.000 8,000.00 0105 9000*REMOVE TERMINAL ANCHOR SECT & MOW STRIP EA 2.000 2.000 1,000.000 2,000.00 0 SUBTOTAL BID ITEMS $ 111,485.00 0 TOTAL AMOUNT WORK DONE CALLOUT CABLE BARRIER REPAIR $ 111,485.00 0 TOTAL AMOUNT WORK DONE CONTROL 6219-93-001 $ 111,485.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2111901 MGR.NO. 058 PAGE 001 CONT 6219 SEC 93 JOB 001 RES ENGR JUNEAU, STEVE PROJ RMC - 621993001 HWY IH0030 300 E. LOOP 390 N MARSHAL CNTY BOWIE DIST 19 CONTRACT PRICE $ 115,020.00 REPORT DATE 05/04/2012 10.17.38 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD MAR 01,2011 TO MAR 31,2012 EST NO 014 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN MAR 1 , 2011 WORKING DAYS USED 336 PERCENT COMPLETE 100.00 PERCENT TIME USED 99.10 DATE COMPLETED MAR 31 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6219-93-001 RMC - 621993001 19 IH0030 BOWIE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0432 RIPRAP (MOW STRIP)(4 IN) CY 30.000 6.850 200.000 1,370.00 7224 REPLACE POSTS (TL-3) EA 1,600.000 1,397.000 65.000 90,805.00 7224 CABLE SPLICE / TURNBUCKLE (TL-3) EA 24.000 5.000 10.000 50.00 7224 REPR OR REPLC CABLE BARR TERM SEC(TL-3) EA 36.000 21.000 10.000 210.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 05367* CABLE BARRIER SYSTEM (TL-3) LF 250.000 105.000 10.000 1,050.00 5367* CABLE BARRIER TERMINAL SECTION (TL-3) EA 8.000 8.000 1,000.000 8,000.00 9000* REMOVE CABLE,POST,CONC FOOTING, MOW EA 4.000 4.000 2,000.000 8,000.00 9000* REMOVE TERMINAL ANCHOR SECT & MOW STRIP EA 2.000 2.000 1,000.000 2,000.00 0 SUBTOTAL BID ITEMS $ 111,485.00 0 CONTRACT TOTAL ALL ITEMS $ 111,485.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2111901 MGR.NO. 058 PAGE 001 CONT 6219 SEC 93 JOB 001 RES ENGR JUNEAU, STEVE PROJ RMC - 621993001 HWY IH0030 300 E. LOOP 390 N MARSHAL CNTY BOWIE DIST 19 CONTRACT PRICE $ 115,020.00 REPORT DATE 05/04/2012 10.17.38 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD MAR 01,2011 TO MAR 31,2012 EST NO 014 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 19 RMC - 621993001 6219-93-001 111,485.00 .00 111,485.00 .00 .00 111,485.00 111,485.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 111,485.00 .00 111,485.00 .00 .00 111,485.00 111,485.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2111901 MGR.NO. 058 PAGE 001 CONT 6219 SEC 93 JOB 001 RES ENGR JUNEAU, STEVE PROJ RMC - 621993001 HWY IH0030 300 E. LOOP 390 N MARSHAL CNTY BOWIE DIST 19 CONTRACT PRICE $ 115,020.00 REPORT DATE 05/04/2012 10.17.38 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD MAR 01,2011 TO MAR 31,2012 EST NO 014 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6219-93-001 RMC - 621993001 19 IH0030 BOWIE -LIMITS - VARIOUS . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 111,485.00