1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5111430 MGR.NO. 806 PAGE 001 CONT 6213 SEC 04 JOB 001 RES ENGR SMITH, BECKY PROJ SUP - 621304001 HWY IH0035 7901 N. IH 35 AUSTIN CNTY HAYS DIST 14 CONTRACT PRICE $ 129,799.83 REPORT DATE 07/24/2012 12.52.15 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2011 TO JUL 01,2012 EST NO 014 & FINAL BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED 15227 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 16, 2011 TIME COMPUTED FROM JUN 01, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 731 396 396 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 12 1 1 WORK COMPLETED AND ACCEPTED TOTAL DAYS ALLOWED = 731 DATE WORK COMPLETED 07/01/12 DAYS CHARGED TO DATE = 396 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 0 0 LIQUIDATED DAMAGES 0 DAYS AT $ 0 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 397 396 1 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5111430 MGR.NO. 806 PAGE 001 CONT 6213 SEC 04 JOB 001 RES ENGR SMITH, BECKY PROJ SUP - 621304001 HWY IH0035 7901 N. IH 35 AUSTIN CNTY HAYS DIST 14 CONTRACT PRICE $ 129,799.83 REPORT DATE 07/24/2012 12.52.15 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2011 TO JUL 01,2012 EST NO 014 & FINAL BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED 15227 DIST. 14 COUNTY HAYS CONTROL 6213-04-001 PROJECT SUP - 621304001 HIGHWAY IH0035 0LIMITS- VARIOUS LOCATIONS IN HAYS COUNTY . 0TYPE OF WORK- LITTER PICKUP AND DISPOSAL 0 0005 CREATED BY BECKY SMITH 0 0055 LITTER PICK-UP NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL AC 12,553.000 5,014.000 9.500 47,633.00 0065 0734 LITTER REMOVAL - TRACT (1) AC 893.000 893.000 11.810 10,546.33 0 SUBTOTAL BID ITEMS $ 58,179.33 0 TOTAL AMOUNT WORK DONE LITTER PICK-UP $ 58,179.33 0 TOTAL AMOUNT WORK DONE CONTROL 6213-04-001 $ 58,179.33 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5111430 MGR.NO. 806 PAGE 001 CONT 6213 SEC 04 JOB 001 RES ENGR SMITH, BECKY PROJ SUP - 621304001 HWY IH0035 7901 N. IH 35 AUSTIN CNTY HAYS DIST 14 CONTRACT PRICE $ 129,799.83 REPORT DATE 07/24/2012 12.52.16 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2011 TO JUL 01,2012 EST NO 014 & FINAL BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED 15227 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN HAYS COUNTY 0 . DATE WORK BEGAN JUN 16, 2011 WORKING DAYS USED 396 PERCENT COMPLETE 100.00 PERCENT TIME USED 54.10 DATE COMPLETED JUL 1 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6213-04-001 SUP - 621304001 14 IH0035 HAYS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL AC 12,553.000 5,014.000 9.500 47,633.00 0734 LITTER REMOVAL - TRACT (1) AC 893.000 893.000 11.810 10,546.33 0 SUBTOTAL BID ITEMS $ 58,179.33 0 CONTRACT TOTAL ALL ITEMS $ 58,179.33 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5111430 MGR.NO. 806 PAGE 001 CONT 6213 SEC 04 JOB 001 RES ENGR SMITH, BECKY PROJ SUP - 621304001 HWY IH0035 7901 N. IH 35 AUSTIN CNTY HAYS DIST 14 CONTRACT PRICE $ 129,799.83 REPORT DATE 07/24/2012 12.52.16 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2011 TO JUL 01,2012 EST NO 014 & FINAL BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED 15227 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 106 SUP - 621304001 6213-04-001 58,179.33 .00 58,179.33 .00 .00 58,179.33 58,179.33 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 58,179.33 .00 58,179.33 .00 .00 58,179.33 58,179.33 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5111430 MGR.NO. 806 PAGE 001 CONT 6213 SEC 04 JOB 001 RES ENGR SMITH, BECKY PROJ SUP - 621304001 HWY IH0035 7901 N. IH 35 AUSTIN CNTY HAYS DIST 14 CONTRACT PRICE $ 129,799.83 REPORT DATE 07/24/2012 12.52.16 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2011 TO JUL 01,2012 EST NO 014 & FINAL BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED 15227 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6213-04-001 SUP - 621304001 14 IH0035 HAYS -LIMITS - VARIOUS LOCATIONS IN HAYS COUNTY . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 58,179.33