1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1124028 MGR.NO. 051 PAGE 001 CONT 6235 SEC 09 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 623509001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 432,010.00 REPORT DATE 08/31/2012 10.24.29 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD APR 09,2012 TO JUN 05,2012 EST NO 004 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 18, 2012 TIME COMPUTED FROM APR 09, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 24 53 30 23 BROUGHT FORWARD ADDL DAYS GRANTED = 9 JUN 12 1 1 TOTAL DAYS ALLOWED = 33 2 1 SATURDAY DATE WORK COMPLETED 06/05/12 3 1 SUNDAY DAYS CHARGED TO DATE = 32 4 1 ASSESSED LIQ DAMAGES = 0 5 1 WORK COMPLETED AND ACCEPTED LIQ DAMAGE RATE $ 590 0 LIQUIDATED DAMAGES 0 DAYS AT $ 590 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 58 32 26 1 SATURDAY 1 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1124028 MGR.NO. 051 PAGE 001 CONT 6235 SEC 09 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 623509001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 432,010.00 REPORT DATE 08/31/2012 10.24.29 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD APR 09,2012 TO JUN 05,2012 EST NO 004 & FINAL INC. 00644 DIST. 20 COUNTY HARDIN CONTROL 6235-09-001 PROJECT RMC - 623509001 HIGHWAY US0069 0LIMITS- HARDIN, JEFFERSON, AND CHAMBERS COUNTIES HARDIN, JEFFERSON, AND CHAMBERS COUNTIES 0TYPE OF WORK- FLEXIBLE BASE REPAIRS 0 0005 PREPARED 9-28-11 0 0055 ROADWAY NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0351 FLEX PAVEMT STRUCTURE REPAIR(VAR DEPTH) CY 1,881.000 1,881.700 210.000 395,157.00 0065 0500 MOBILIZATION LS 1.000 1.000 35,000.000 35,000.00 0070 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 3.000 500.000 1,500.00 0070 0502 ADJ EST QUANTITY TO DATE 3.000 0075 0662 WK ZN PAV MRK SHT TERM (TAB) TY W EA 100.000 49.000 2.000 98.00 0080 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 400.000 16.000 2.000 32.00 0095 9001*REPAIR CHIN RD APPROACH/DEPARTURE CO#2 LS 30,233.110 30,233.110 1.000 30,233.11 0 SUBTOTAL BID ITEMS $ 462,020.11 0 TOTAL AMOUNT WORK DONE ROADWAY $ 462,020.11 0 TOTAL AMOUNT WORK DONE CONTROL 6235-09-001 $ 462,020.11 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1124028 MGR.NO. 051 PAGE 001 CONT 6235 SEC 09 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 623509001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 432,010.00 REPORT DATE 08/31/2012 10.24.29 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD APR 09,2012 TO JUN 05,2012 EST NO 004 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - HARDIN, JEFFERSON, AND CHAMBERS COUNTIES 0 HARDIN, JEFFERSON, AND CHAMBERS COUNTIES DATE WORK BEGAN APR 18, 2012 WORKING DAYS USED 32 PERCENT COMPLETE 100.00 PERCENT TIME USED 96.90 DATE COMPLETED JUN 5 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6235-09-001 RMC - 623509001 20 US0069 HARDIN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEX PAVEMT STRUCTURE REPAIR(VAR DEPTH) CY 1,881.000 1,881.700 210.000 395,157.00 0500 MOBILIZATION LS 1.000 1.000 35,000.000 35,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 3.000 500.000 1,500.00 0502 ADJ EST QUANTITY TO DATE 3.000 0662 WK ZN PAV MRK SHT TERM (TAB) TY W EA 100.000 49.000 2.000 98.00 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 400.000 16.000 2.000 32.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09001* REPAIR CHIN RD APPROACH/DEPARTURE CO#2 LS 30,233.110 30,233.110 1.000 30,233.11 0 SUBTOTAL BID ITEMS $ 462,020.11 0 CONTRACT TOTAL ALL ITEMS $ 462,020.11 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1124028 MGR.NO. 051 PAGE 001 CONT 6235 SEC 09 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 623509001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 432,010.00 REPORT DATE 08/31/2012 10.24.29 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD APR 09,2012 TO JUN 05,2012 EST NO 004 & FINAL INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 101 RMC - 623509001 6235-09-001 462,020.11 .00 462,020.11 .00 .00 462,020.11 460,970.11 1,050.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 462,020.11 .00 462,020.11 .00 .00 462,020.11 460,970.11 1,050.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1124028 MGR.NO. 051 PAGE 001 CONT 6235 SEC 09 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 623509001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 432,010.00 REPORT DATE 08/31/2012 10.24.29 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD APR 09,2012 TO JUN 05,2012 EST NO 004 & FINAL INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6235-09-001 RMC - 623509001 20 US0069 HARDIN -LIMITS - HARDIN, JEFFERSON, AND CHAMBERS COUNTIES HARDIN, JEFFERSON, AND CHAMBERS COUNTIES LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0500 MOBILIZATION LS 1.000 0.030 35,000.000 1,050.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 1,050.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 462,020.11