1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2132063 MGR.NO. 053 PAGE 001 CONT 6254 SEC 82 JOB 001 RES ENGR WARDEN, ALLEN PROJ SUP - 625482001 HWY US0069 807 PINE ST WOODVILLE CNTY TYLER DIST 20 CONTRACT PRICE $ 11,349.00 REPORT DATE 04/17/2014 15.57.38 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAR 01,2013 TO FEB 28,2014 EST NO 013 & FINAL BURKE CENTER 08985 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 01, 2013 TIME COMPUTED FROM MAR 01, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 337 331 6 BROUGHT FORWARD ADDL DAYS GRANTED = 0 FEB 14 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 02/28/14 3 1 DAYS CHARGED TO DATE = 359 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 - ----- ----- ----- 365 359 6 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2132063 MGR.NO. 053 PAGE 001 CONT 6254 SEC 82 JOB 001 RES ENGR WARDEN, ALLEN PROJ SUP - 625482001 HWY US0069 807 PINE ST WOODVILLE CNTY TYLER DIST 20 CONTRACT PRICE $ 11,349.00 REPORT DATE 04/17/2014 15.57.39 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAR 01,2013 TO FEB 28,2014 EST NO 013 & FINAL BURKE CENTER 08985 DIST. 20 COUNTY TYLER CONTROL 6254-82-001 PROJECT SUP - 625482001 HIGHWAY US0069 0LIMITS- US 69 US 69 0TYPE OF WORK- WOODVILLE ~ PICNIC 0 0005 WOODVILLE ~ PICNIC 0 0055 WOODVILLE ~ PICNIC MAINTENANCE NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0745 JANITORIAL MAINT-PICNIC AREA-SITE (1) CYC 26.000 21.000 105.000 2,205.00 0065 0745 GROUNDS MAINT-PICNIC MOW/TRIM-SITE (1) CYC 16.000 14.000 150.000 2,100.00 0070 0745 GROUNDS MAINT (MOWING/TRIMMING) CYC 1.000 0.000 150.000 .00 0075 0751 LEAF REMOVAL (SITE A) CYC 1.000 0.000 2,304.000 .00 0080 7070 GROUNDS MAINTENANCE (SITE A) CYC 4.000 0.000 52.500 .00 0085 0745 JANITORIAL MAINT-PICNIC AREA-SITE (2) CYC 26.000 21.000 60.000 1,260.00 0090 0745 GROUNDS MAINT-PICNIC MOW/TRIM-SITE (2) CYC 16.000 14.000 75.000 1,050.00 0095 7013 GROUNDS MAINTENANCE CYC 1.000 0.000 75.000 .00 0100 0751 LEAF REMOVAL (SITE B) CYC 1.000 0.000 500.000 .00 0105 7070 GROUNDS MAINTENANCE (SITE B) CYC 4.000 0.000 55.000 .00 0 SUBTOTAL BID ITEMS $ 6,615.00 0 TOTAL AMOUNT WORK DONE WOODVILLE ~ PICNIC MAINTENANCE $ 6,615.00 0 TOTAL AMOUNT WORK DONE CONTROL 6254-82-001 $ 6,615.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2132063 MGR.NO. 053 PAGE 001 CONT 6254 SEC 82 JOB 001 RES ENGR WARDEN, ALLEN PROJ SUP - 625482001 HWY US0069 807 PINE ST WOODVILLE CNTY TYLER DIST 20 CONTRACT PRICE $ 11,349.00 REPORT DATE 04/17/2014 15.57.39 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAR 01,2013 TO FEB 28,2014 EST NO 013 & FINAL BURKE CENTER 08985 0*********************************************************************************************************************************** -LIMITS - US 69 0 US 69 DATE WORK BEGAN MAR 1 , 2013 WORKING DAYS USED 359 PERCENT COMPLETE 100.00 PERCENT TIME USED 98.30 DATE COMPLETED FEB 28 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6254-82-001 SUP - 625482001 20 US0069 TYLER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0745 GROUNDS MAINT-PICNIC MOW/TRIM-SITE (1) CYC 16.000 14.000 150.000 2,100.00 0745 GROUNDS MAINT-PICNIC MOW/TRIM-SITE (2) CYC 16.000 14.000 75.000 1,050.00 0745 JANITORIAL MAINT-PICNIC AREA-SITE (1) CYC 26.000 21.000 105.000 2,205.00 0745 JANITORIAL MAINT-PICNIC AREA-SITE (2) CYC 26.000 21.000 60.000 1,260.00 0 SUBTOTAL BID ITEMS $ 6,615.00 0 CONTRACT TOTAL ALL ITEMS $ 6,615.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2132063 MGR.NO. 053 PAGE 001 CONT 6254 SEC 82 JOB 001 RES ENGR WARDEN, ALLEN PROJ SUP - 625482001 HWY US0069 807 PINE ST WOODVILLE CNTY TYLER DIST 20 CONTRACT PRICE $ 11,349.00 REPORT DATE 04/17/2014 15.57.39 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAR 01,2013 TO FEB 28,2014 EST NO 013 & FINAL BURKE CENTER 08985 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 229 SUP - 625482001 6254-82-001 6,615.00 .00 6,615.00 .00 .00 6,615.00 6,615.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 6,615.00 .00 6,615.00 .00 .00 6,615.00 6,615.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2132063 MGR.NO. 053 PAGE 001 CONT 6254 SEC 82 JOB 001 RES ENGR WARDEN, ALLEN PROJ SUP - 625482001 HWY US0069 807 PINE ST WOODVILLE CNTY TYLER DIST 20 CONTRACT PRICE $ 11,349.00 REPORT DATE 04/17/2014 15.57.39 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAR 01,2013 TO FEB 28,2014 EST NO 013 & FINAL BURKE CENTER 08985 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6254-82-001 SUP - 625482001 20 US0069 TYLER -LIMITS - US 69 US 69 - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 6,615.00