1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8124017 MGR.NO. 054 PAGE 001 CONT 6241 SEC 55 JOB 001 RES ENGR JEFFERY, MARK PROJ RMC - 624155001 HWY FM1365 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 1,950,359.05 REPORT DATE 11/11/2013 14.51.36 CONTRACTOR KNIFE RIVER CORPORATION - EST PERIOD NOV 05,2012 TO OCT 07,2013 EST NO 012 & FINAL SOUTH 13245 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 05, 2012 TIME COMPUTED FROM NOV 13, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 99 330 103 227 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 13 1 1 AWAITING ACCEPTANCE FROM AE TOTAL DAYS ALLOWED = 99 2 1 AWAITING ACCEPTANCE FROM AE DATE WORK COMPLETED 10/07/13 3 1 AWAITING ACCEPTANCE FROM AE DAYS CHARGED TO DATE = 103 4 1 AWAITING ACCEPTANCE FROM AE ASSESSED LIQ DAMAGES = 4 5 1 AWAITING ACCEPTANCE FROM AE LIQ DAMAGE RATE $ 785 6 1 AWAITING ACCEPTANCE FROM AE 7 1 WORK COMPLETED AND ACCEPTED LIQUIDATED DAMAGES 4 DAYS AT $ 785 PER DAY TOTAL = $ 3,140.00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 337 103 234 0 SATURDAY 0 SUNDAY 0 HOLIDAY 6 AWAITING ACCEPTANCE FROM AE 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8124017 MGR.NO. 054 PAGE 001 CONT 6241 SEC 55 JOB 001 RES ENGR JEFFERY, MARK PROJ RMC - 624155001 HWY FM1365 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 1,950,359.05 REPORT DATE 11/11/2013 14.51.37 CONTRACTOR KNIFE RIVER CORPORATION - EST PERIOD NOV 05,2012 TO OCT 07,2013 EST NO 012 & FINAL SOUTH 13245 DIST. 17 COUNTY FREESTONE CONTROL 6241-55-001 PROJECT RMC - 624155001 HIGHWAY FM1365 0LIMITS- LIMESTONE COUNTY LINE BS 84 0TYPE OF WORK- ROADWAY RESTORATION 0 0005 PREPARED BY DISTRICT MAINTENANCE 0 0055 ROADWAY RESTORATION NET LENGTH 5.951 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0100 PREPARING ROW STA 2.000 2.000 1,000.000 2,000.00 0065 0105 REMOVING STAB BASE & ASPH PAV (8"-10") SY 65.000 65.000 10.260 666.90 0070 0105 REMOVING STAB BASE & ASPH PAV (12") SY 252.000 252.000 12.000 3,024.00 0075 0110 EXCAVATION (ROADWAY) CY 2,148.000 2,148.000 12.440 26,721.12 0080 0112 SUBGRADE WIDENING (DENS CONT) STA 254.930 251.680 220.000 55,369.60 0085 0132 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 189.000 232.000 20.000 4,640.00 0090 0134 BACKFILL (TY B) STA 307.040 307.040 55.000 16,887.20 0095 0150 BLADING STA 307.040 307.040 40.000 12,281.60 0100 0150 BLADING HR 19.000 19.000 125.000 2,375.00 0105 0164 DRILL SEEDING (PERM) (RURAL) (SANDY) SY 41,176.000 41,176.000 .080 3,294.08 0110 0164 DRILL SEEDING (TEMP) (WARM) SY 20,588.000 20,588.000 .080 1,647.04 0115 0164 DRILL SEEDING (TEMP) (COOL) SY 20,588.000 0.000 .080 .00 0120 0168 VEGETATIVE WATERING MG 411.800 0.000 10.000 .00 0125 0247 FL BS (CMP IN PLC)(TY A GR 2)(5") SY 34,428.000 34,428.000 5.230 180,058.44 0130 0247 FL BS (RDWY DEL) (TY A GR 2) TON 3,859.000 3,859.000 14.530 56,071.27 0135 0247 FL BS (CMP IN PLC) (TY A GR 2) (4") SY 53,877.000 54,839.740 4.210 230,875.31 0140 0251 REWORK BS MTL (TY D) (6") (ORD COMP) STA 4.200 4.200 175.000 735.00 0145 0251 REWORK BS MTL (TY D) (8") (ORD COMP) STA 110.660 115.000 145.000 16,675.00 0150 0251 REWORK BS MTL (TY D)(4")(ORD COMP) STA 27.860 27.860 130.000 3,621.80 1 0155 0251 REWORK BS MTL (TY D)(9")(ORD COMP) STA 144.270 144.000 145.000 20,880.00 0160 0275 CEMENT TON 1,985.000 1,952.600 107.200 209,318.72 0165 0275 CEMENT TREAT (EXIST MATL) (10") SY 97,653.000 97,652.890 1.250 122,066.11 0170 0275 CEMENT TREAT (NEW BASE)(12") SY 6,349.000 6,349.000 1.350 8,571.15 0175 0276 CEM TRT(PLNT MX)(CL N)(TY E)(GR 4)(8") SY 252.000 252.000 22.000 5,544.00 0180 0276 CEM TRT(PLNT MX)(CL N)(TY E)(GR 4)(12") SY 333.000 333.000 27.000 8,991.00 0185 0316 ASPH (RC-250) GAL 18,910.000 18,910.000 3.910 73,938.10 0190 0316 AGGR (TY-B GR-5 OR TY-L GR-5 SAC-B) CY 700.000 700.000 70.000 49,000.00 0195 0316 ASPH (TIER II) GAL 34,139.000 34,139.000 3.520 120,169.28 0200 0316 AGGR (TIER II) CY 759.000 759.000 90.000 68,310.00 0205 0340 D-GR HMA(METH) TY-C SAC-B PG70-22 TON 715.000 1,303.070 80.000 104,245.60 0210 0354 PLANE ASPH CONC PAV (2 1/2") SY 1,683.000 1,683.000 3.500 5,890.50 0215 0400 CUT & RESTORING PAV SY 97.000 112.000 98.910 11,077.92 0220 0402 TRENCH EXCAVATION PROTECTION LF 105.000 105.000 6.250 656.25 0225 0403 TEMPORARY SPL SHORING SF 1,341.000 1,341.000 26.050 34,933.05 0230 0420 CL B CONC (MISC) CY 4.800 4.800 469.000 2,251.20 0235 0432 RIPRAP (CONC)(4 IN) CY 26.800 35.700 339.000 12,102.30 0240 0432 RIPRAP (STONE PROTECTION)(15 IN) CY 16.000 16.000 450.000 7,200.00 0245 0460 CMP (GAL STL 24 IN) LF 77.000 77.000 49.090 3,779.93 0250 0460 CMP (GAL STL 36 IN) LF 50.000 50.000 63.250 3,162.50 0255 0460 CMP AR (GAL STL DES 2) LF 32.000 32.000 45.560 1,457.92 0260 0460 CMP AR (GAL STL DES 3) LF 107.000 107.000 51.790 5,541.53 0265 0460 CMP AR (GAL STL DES 4) LF 3.000 3.000 125.040 375.12 0270 0460 CMP AR (GAL STL DES 7) LF 83.000 127.000 107.830 13,694.41 0275 0466 WINGWALL (PW)(HW=5 FT) EA 4.000 4.000 7,510.000 30,040.00 0280 0467 SET (TY II)(24 IN)(CMP)(4:1)(C) EA 4.000 4.000 1,555.000 6,220.00 0285 0467 SET (TY II)(36 IN)(CMP)(4:1)(C) EA 2.000 2.000 1,760.000 3,520.00 0290 0467 SET (TY II)(DES 3)(CMP)(3:1)(C) EA 1.000 1.000 1,627.000 1,627.00 0295 0467 SET (TY II)(DES 2)(CMP)(4:1)(C) EA 2.000 2.000 1,490.000 2,980.00 0300 0467 SET (TY II)(DES 3)(CMP)(4:1)(C) EA 5.000 5.000 1,592.000 7,960.00 0305 0467 SET (TY II)(DES 4)(CMP)(4:1)(C) EA 2.000 2.000 1,981.000 3,962.00 0310 0496 REMOV STR (PIPE) LF 1.000 1.000 208.000 208.00 0315 0496 REMOV STR (PIPE) EA 9.000 9.000 365.000 3,285.00 0320 0500 MOBILIZATION LS 1.000 1.000 194,000.000 194,000.00 0325 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 8.000 5,000.000 40,000.00 0330 0506 ROCK FILTER DAMS (INSTALL) (TY 1) LF 1,705.000 1,705.000 23.250 39,641.25 1 0335 0506 ROCK FILTER DAMS (REMOVE) LF 1,705.000 1,705.000 6.410 10,929.05 0340 0506 BACKHOE WORK (EROSION & SEDM CONT) HR 19.000 0.000 100.000 .00 0345 0506 TEMPORARY SEDIMENT CONTROL FENCE LF 12,080.000 12,080.000 2.750 33,220.00 0350 0530 DRIVEWAYS (CONC) EA 4.000 4.000 3,000.000 12,000.00 0355 0530 DRIVEWAYS (ACP) EA 6.000 6.000 2,600.000 15,600.00 0360 0530 DRIVEWAYS (SURF TREAT) EA 14.000 14.000 925.000 12,950.00 0365 0530 TURNOUTS (SURF TREAT) EA 25.000 25.000 500.000 12,500.00 0370 0530 DRIVEWAYS (OTHER) EA 53.000 53.000 150.000 7,950.00 0375 0560 MAILBOX INSTALL-D (TWW-POST)TY 4 FND-TB EA 6.000 6.000 270.000 1,620.00 0380 0560 MAILBOX INSTALL-M (TWW-POST)TY 4 FND-TB EA 1.000 2.000 580.000 1,160.00 0385 0560 MAILBOX INSTALL-SP (TIM-POST) TY 5 FND EA 1.000 1.000 208.000 208.00 0390 0560 MAILBOX INSTALL-S(TWW-POST)TY 4 FND- EA 19.000 18.000 235.000 4,230.00 0395 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (BRK) LF 6,610.000 4,180.000 .180 752.40 0400 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (SLD) LF 19,800.000 16,583.000 .160 2,653.28 0405 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 1,610.000 1,880.000 1.000 1,880.00 0410 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 62,770.000 61,382.000 .440 27,008.08 0415 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 371.000 371.000 5.210 1,932.91 0420 0666 REFL PAV MRK TY I(W)(RR XING) (100MIL) EA 2.000 2.000 300.000 600.00 0425 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 6,610.000 6,590.000 .470 3,097.30 0430 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 19,800.000 19,800.000 .450 8,910.00 0435 0672 REFL PAV MRKR TY II-A-A EA 577.000 574.000 2.770 1,589.98 0 SUBTOTAL BID ITEMS $ 2,004,334.20 0 MATERIAL ON HAND 0 LINE MATRL. NO MATERIAL DESCRIPTION UNIT QUANTITY % INV UNIT PRICE AMOUNT NO. PRICE ALLOWED($) ($) 0 0445 913 STR PLATE PIPE LF 0.000 100 15.960 .00 0450 913 STR PLATE PIPE LF 0.000 100 17.560 .00 0455 913 STR PLATE PIPE LF 0.000 100 24.360 .00 0460 913 STR PLATE PIPE LF 0.000 100 50.820 .00 0465 4672324775 SET (TY II)(DES 4)(CMP)(4:1) (C) FT 0.000 100 135.000 .00 0485 4672316776 SET (TY II)(DES 3)(CMP)(3:1) (C) FT 0.000 100 156.000 .00 1 0490 4672262777 SET (TY II)(24 IN)(CMP)(4:1) (C) FT 0.000 100 156.000 .00 0495 4672266778 SET (TY II)(36 IN)(CMP)(4:1) (C) FT 0.000 100 267.000 .00 0 TOTAL AMOUNT WORK DONE ROADWAY RESTORATION $ 2,004,334.20 0 TOTAL AMOUNT WORK DONE CONTROL 6241-55-001 $ 2,004,334.20 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8124017 MGR.NO. 054 PAGE 001 CONT 6241 SEC 55 JOB 001 RES ENGR JEFFERY, MARK PROJ RMC - 624155001 HWY FM1365 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 1,950,359.05 REPORT DATE 11/11/2013 14.51.38 CONTRACTOR KNIFE RIVER CORPORATION - EST PERIOD NOV 05,2012 TO OCT 07,2013 EST NO 012 & FINAL SOUTH 13245 0*********************************************************************************************************************************** -LIMITS - LIMESTONE COUNTY LINE 0 BS 84 DATE WORK BEGAN NOV 5 , 2012 WORKING DAYS USED 103 PERCENT COMPLETE 100.00 PERCENT TIME USED 104.00 DATE COMPLETED OCT 7 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6241-55-001 RMC - 624155001 17 FM1365 FREESTONE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0100 PREPARING ROW STA 2.000 2.000 1,000.000 2,000.00 0105 REMOVING STAB BASE & ASPH PAV (8"-10") SY 65.000 65.000 10.260 666.90 0105 REMOVING STAB BASE & ASPH PAV (12") SY 252.000 252.000 12.000 3,024.00 0110 EXCAVATION (ROADWAY) CY 2,148.000 2,148.000 12.440 26,721.12 0112 SUBGRADE WIDENING (DENS CONT) STA 254.930 251.680 220.000 55,369.60 0132 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 189.000 232.000 20.000 4,640.00 0134 BACKFILL (TY B) STA 307.040 307.040 55.000 16,887.20 0150 BLADING STA 307.040 307.040 40.000 12,281.60 0150 BLADING HR 19.000 19.000 125.000 2,375.00 0164 DRILL SEEDING (PERM) (RURAL) (SANDY) SY 41,176.000 41,176.000 .080 3,294.08 0164 DRILL SEEDING (TEMP) (WARM) SY 20,588.000 20,588.000 .080 1,647.04 0247 FL BS (RDWY DEL) (TY A GR 2) TON 3,859.000 3,859.000 14.530 56,071.27 0247 FL BS (CMP IN PLC)(TY A GR 2)(5") SY 34,428.000 34,428.000 5.230 180,058.44 0247 FL BS (CMP IN PLC) (TY A GR 2) (4") SY 53,877.000 54,839.740 4.210 230,875.31 0251 REWORK BS MTL (TY D) (6") (ORD COMP) STA 4.200 4.200 175.000 735.00 0251 REWORK BS MTL (TY D) (8") (ORD COMP) STA 110.660 115.000 145.000 16,675.00 10251 REWORK BS MTL (TY D)(4")(ORD COMP) STA 27.860 27.860 130.000 3,621.80 0251 REWORK BS MTL (TY D)(9")(ORD COMP) STA 144.270 144.000 145.000 20,880.00 0275 CEMENT TON 1,985.000 1,952.600 107.200 209,318.72 0275 CEMENT TREAT (EXIST MATL) (10") SY 97,653.000 97,652.890 1.250 122,066.11 0275 CEMENT TREAT (NEW BASE)(12") SY 6,349.000 6,349.000 1.350 8,571.15 0276 CEM TRT(PLNT MX)(CL N)(TY E)(GR 4)(8") SY 252.000 252.000 22.000 5,544.00 0276 CEM TRT(PLNT MX)(CL N)(TY E)(GR 4)(12") SY 333.000 333.000 27.000 8,991.00 0316 ASPH (RC-250) GAL 18,910.000 18,910.000 3.910 73,938.10 0316 AGGR (TY-B GR-5 OR TY-L GR-5 SAC-B) CY 700.000 700.000 70.000 49,000.00 0316 ASPH (TIER II) GAL 34,139.000 34,139.000 3.520 120,169.28 0316 AGGR (TIER II) CY 759.000 759.000 90.000 68,310.00 0340 D-GR HMA(METH) TY-C SAC-B PG70-22 TON 715.000 1,303.070 80.000 104,245.60 0354 PLANE ASPH CONC PAV (2 1/2") SY 1,683.000 1,683.000 3.500 5,890.50 0400 CUT & RESTORING PAV SY 97.000 112.000 98.910 11,077.92 0402 TRENCH EXCAVATION PROTECTION LF 105.000 105.000 6.250 656.25 0403 TEMPORARY SPL SHORING SF 1,341.000 1,341.000 26.050 34,933.05 0420 CL B CONC (MISC) CY 4.800 4.800 469.000 2,251.20 0432 RIPRAP (CONC)(4 IN) CY 26.800 35.700 339.000 12,102.30 0432 RIPRAP (STONE PROTECTION)(15 IN) CY 16.000 16.000 450.000 7,200.00 0460 CMP (GAL STL 24 IN) LF 77.000 77.000 49.090 3,779.93 0460 CMP (GAL STL 36 IN) LF 50.000 50.000 63.250 3,162.50 0460 CMP AR (GAL STL DES 2) LF 32.000 32.000 45.560 1,457.92 0460 CMP AR (GAL STL DES 3) LF 107.000 107.000 51.790 5,541.53 0460 CMP AR (GAL STL DES 4) LF 3.000 3.000 125.040 375.12 0460 CMP AR (GAL STL DES 7) LF 83.000 127.000 107.830 13,694.41 0466 WINGWALL (PW)(HW=5 FT) EA 4.000 4.000 7,510.000 30,040.00 0467 SET (TY II)(24 IN)(CMP)(4:1)(C) EA 4.000 4.000 1,555.000 6,220.00 0467 SET (TY II)(36 IN)(CMP)(4:1)(C) EA 2.000 2.000 1,760.000 3,520.00 0467 SET (TY II)(DES 3)(CMP)(3:1)(C) EA 1.000 1.000 1,627.000 1,627.00 0467 SET (TY II)(DES 2)(CMP)(4:1)(C) EA 2.000 2.000 1,490.000 2,980.00 0467 SET (TY II)(DES 3)(CMP)(4:1)(C) EA 5.000 5.000 1,592.000 7,960.00 0467 SET (TY II)(DES 4)(CMP)(4:1)(C) EA 2.000 2.000 1,981.000 3,962.00 0496 REMOV STR (PIPE) LF 1.000 1.000 208.000 208.00 0496 REMOV STR (PIPE) EA 9.000 9.000 365.000 3,285.00 0500 MOBILIZATION LS 1.000 1.000 194,000.000 194,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 8.000 5,000.000 40,000.00 10506 ROCK FILTER DAMS (INSTALL) (TY 1) LF 1,705.000 1,705.000 23.250 39,641.25 0506 ROCK FILTER DAMS (REMOVE) LF 1,705.000 1,705.000 6.410 10,929.05 0506 TEMPORARY SEDIMENT CONTROL FENCE LF 12,080.000 12,080.000 2.750 33,220.00 0530 DRIVEWAYS (CONC) EA 4.000 4.000 3,000.000 12,000.00 0530 DRIVEWAYS (ACP) EA 6.000 6.000 2,600.000 15,600.00 0530 DRIVEWAYS (SURF TREAT) EA 14.000 14.000 925.000 12,950.00 0530 TURNOUTS (SURF TREAT) EA 25.000 25.000 500.000 12,500.00 0530 DRIVEWAYS (OTHER) EA 53.000 53.000 150.000 7,950.00 0560 MAILBOX INSTALL-D (TWW-POST)TY 4 FND-TB EA 6.000 6.000 270.000 1,620.00 0560 MAILBOX INSTALL-M (TWW-POST)TY 4 FND-TB EA 1.000 2.000 580.000 1,160.00 0560 MAILBOX INSTALL-SP (TIM-POST) TY 5 FND EA 1.000 1.000 208.000 208.00 0560 MAILBOX INSTALL-S(TWW-POST)TY 4 FND- EA 19.000 18.000 235.000 4,230.00 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (BRK) LF 6,610.000 4,180.000 .180 752.40 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (SLD) LF 19,800.000 16,583.000 .160 2,653.28 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 1,610.000 1,880.000 1.000 1,880.00 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 62,770.000 61,382.000 .440 27,008.08 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 371.000 371.000 5.210 1,932.91 0666 REFL PAV MRK TY I(W)(RR XING) (100MIL) EA 2.000 2.000 300.000 600.00 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 6,610.000 6,590.000 .470 3,097.30 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 19,800.000 19,800.000 .450 8,910.00 0672 REFL PAV MRKR TY II-A-A EA 577.000 574.000 2.770 1,589.98 0 SUBTOTAL BID ITEMS $ 2,004,334.20 0 CONTRACT TOTAL ALL ITEMS $ 2,004,334.20 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8124017 MGR.NO. 054 PAGE 001 CONT 6241 SEC 55 JOB 001 RES ENGR JEFFERY, MARK PROJ RMC - 624155001 HWY FM1365 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 1,950,359.05 REPORT DATE 11/11/2013 14.51.38 CONTRACTOR KNIFE RIVER CORPORATION - EST PERIOD NOV 05,2012 TO OCT 07,2013 EST NO 012 & FINAL SOUTH 13245 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 82 RMC - 624155001 6241-55-001 2,004,334.20 .00 2,004,334.20 .00 3,140.00 2,001,194.20 1,979,272.20 21,922.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 2,004,334.20 .00 2,004,334.20 .00 3,140.00 2,001,194.20 1,979,272.20 21,922.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8124017 MGR.NO. 054 PAGE 001 CONT 6241 SEC 55 JOB 001 RES ENGR JEFFERY, MARK PROJ RMC - 624155001 HWY FM1365 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 1,950,359.05 REPORT DATE 11/11/2013 14.51.39 CONTRACTOR KNIFE RIVER CORPORATION - EST PERIOD NOV 05,2012 TO OCT 07,2013 EST NO 012 & FINAL SOUTH 13245 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6241-55-001 RMC - 624155001 17 FM1365 FREESTONE -LIMITS - LIMESTONE COUNTY LINE BS 84 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 205 0340 D-GR HMA(METH) TY-C SAC-B TON 715.000 271.850 80.000 21,748.00 PG70-22 405 0662 WK ZN PAV MRK SHT TERM (TAB) EA 1,610.000 174.000 1.000 174.00 TY Y-2 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 21,922.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 2,004,334.20