1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7121706 MGR.NO. 054 PAGE 001 CONT 6244 SEC 40 JOB 001 RES ENGR JEFFERY, MARK PROJ RMC - 624440001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 148,290.00 REPORT DATE 05/10/2013 11.23.14 CONTRACTOR K & R CONTRACTORS 7458 EST PERIOD SEP 17,2012 TO FEB 21,2013 EST NO 008 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 17, 2012 TIME COMPUTED FROM SEP 25, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 174 137 27 110 BROUGHT FORWARD ADDL DAYS GRANTED = 0 FEB 13 1 1 TOTAL DAYS ALLOWED = 174 2 1 SATURDAY DATE WORK COMPLETED 02/21/13 3 1 SUNDAY DAYS CHARGED TO DATE = 38 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 590 6 1 RAIN 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 590 PER DAY 9 1 SATURDAY TOTAL = $ .00 10 1 SUNDAY 11 1 RAIN CERTIFIED AS CORRECT AND 12 1 RAIN ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 SATURDAY ---------------------------- 17 1 SUNDAY AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 WORK COMPLETED AND ACCEPTED - - - 0 ----- ----- ----- 158 38 120 3 SATURDAY 3 SUNDAY 0 HOLIDAY 3 RAIN 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7121706 MGR.NO. 054 PAGE 001 CONT 6244 SEC 40 JOB 001 RES ENGR JEFFERY, MARK PROJ RMC - 624440001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 148,290.00 REPORT DATE 05/10/2013 11.23.14 CONTRACTOR K & R CONTRACTORS 7458 EST PERIOD SEP 17,2012 TO FEB 21,2013 EST NO 008 & FINAL DIST. 17 COUNTY FREESTONE CONTROL 6244-40-001 PROJECT RMC - 624440001 HIGHWAY SH0075 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- TREE REMOVAL 0 0005 PREPARED BY DISTRICT MAINTENANCE 0 0055 TREE REMOVAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0752 TREE REMOVAL (4"-12" DIA) EA 2,100.000 2,725.000 30.000 81,750.00 0065 0752 TREE REMOVAL (12"-18" DIA) EA 500.000 394.000 50.000 19,700.00 0070 0752 TREE REMOVAL (18"-24" DIA) EA 180.000 151.000 100.000 15,100.00 0075 0752 TREE REMOVAL (24"-30" DIA) EA 80.000 82.000 150.000 12,300.00 0080 0752 TREE REMOVAL (30"-36" DIA) EA 55.000 41.000 200.000 8,200.00 0085 0752 TREE REMOVAL (36"-42" DIA) EA 30.000 11.000 225.000 2,475.00 0090 0752 TREE REMOVAL (42"-48" DIA) EA 14.000 12.000 250.000 3,000.00 0095 0752 TREE REMOVAL (48"-60" DIA) EA 5.000 3.000 300.000 900.00 0100 0752 TREE REMOVAL (60"-72" DIA) EA 5.000 2.000 300.000 600.00 0105 0752 TREE TRIMMING EA 200.000 169.000 25.000 4,225.00 0110 0752 STUMP REMOVAL (12" OR LESS) EA 25.000 0.000 20.000 .00 0115 0752 STUMP REMOVAL (GREATER THAN 12") EA 20.000 0.000 25.000 .00 0120 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 4.000 0.000 10.000 .00 0 SUBTOTAL BID ITEMS $ 148,250.00 0 TOTAL AMOUNT WORK DONE TREE REMOVAL $ 148,250.00 0 TOTAL AMOUNT WORK DONE CONTROL 6244-40-001 $ 148,250.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7121706 MGR.NO. 054 PAGE 001 CONT 6244 SEC 40 JOB 001 RES ENGR JEFFERY, MARK PROJ RMC - 624440001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 148,290.00 REPORT DATE 05/10/2013 11.23.14 CONTRACTOR K & R CONTRACTORS 7458 EST PERIOD SEP 17,2012 TO FEB 21,2013 EST NO 008 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN SEP 17, 2012 WORKING DAYS USED 38 PERCENT COMPLETE 100.00 PERCENT TIME USED 21.80 DATE COMPLETED FEB 21 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6244-40-001 RMC - 624440001 17 SH0075 FREESTONE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0752 TREE REMOVAL (4"-12" DIA) EA 2,100.000 2,725.000 30.000 81,750.00 0752 TREE REMOVAL (12"-18" DIA) EA 500.000 394.000 50.000 19,700.00 0752 TREE REMOVAL (18"-24" DIA) EA 180.000 151.000 100.000 15,100.00 0752 TREE REMOVAL (24"-30" DIA) EA 80.000 82.000 150.000 12,300.00 0752 TREE REMOVAL (30"-36" DIA) EA 55.000 41.000 200.000 8,200.00 0752 TREE REMOVAL (36"-42" DIA) EA 30.000 11.000 225.000 2,475.00 0752 TREE REMOVAL (42"-48" DIA) EA 14.000 12.000 250.000 3,000.00 0752 TREE REMOVAL (48"-60" DIA) EA 5.000 3.000 300.000 900.00 0752 TREE REMOVAL (60"-72" DIA) EA 5.000 2.000 300.000 600.00 0752 TREE TRIMMING EA 200.000 169.000 25.000 4,225.00 0 SUBTOTAL BID ITEMS $ 148,250.00 0 CONTRACT TOTAL ALL ITEMS $ 148,250.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7121706 MGR.NO. 054 PAGE 001 CONT 6244 SEC 40 JOB 001 RES ENGR JEFFERY, MARK PROJ RMC - 624440001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 148,290.00 REPORT DATE 05/10/2013 11.23.14 CONTRACTOR K & R CONTRACTORS 7458 EST PERIOD SEP 17,2012 TO FEB 21,2013 EST NO 008 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 82 RMC - 624440001 6244-40-001 148,250.00 .00 148,250.00 .00 .00 148,250.00 148,250.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 148,250.00 .00 148,250.00 .00 .00 148,250.00 148,250.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7121706 MGR.NO. 054 PAGE 001 CONT 6244 SEC 40 JOB 001 RES ENGR JEFFERY, MARK PROJ RMC - 624440001 HWY SH0075 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 148,290.00 REPORT DATE 05/10/2013 11.23.15 CONTRACTOR K & R CONTRACTORS 7458 EST PERIOD SEP 17,2012 TO FEB 21,2013 EST NO 008 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6244-40-001 RMC - 624440001 17 SH0075 FREESTONE -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 148,250.00