1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11062301 MGR.NO. PAGE 001 CONT 6125 SEC 28 JOB 001 RES ENGR HOLLAND, HOWARD PROJ RMC - 612528001 HWY FM0586 2495 HWY 183 N BROWNWOOD CNTY BROWN DIST 23 CONTRACT PRICE $ 221,545.20 REPORT DATE 06/25/2012 14.27.01 CONTRACTOR D. I. J. CONSTRUCTION, INC. 440 EST PERIOD DEC 25,2006 TO MAR 21,2007 EST NO 005 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN DEC 25, 2006 TIME COMPUTED FROM DEC 25, 2006 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 45 66 18 48 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 07 1 1 TOTAL DAYS ALLOWED = 45 2 1 DATE WORK COMPLETED 03/21/07 3 1 SATURDAY DAYS CHARGED TO DATE = 29 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 450 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 450 PER DAY 9 1 TOTAL = $ .00 10 1 SATURDAY 11 1 SUNDAY CERTIFIED AS CORRECT AND 12 1 TOO WET ONE COPY HAS BEEN GIVEN 13 1 TOO WET TO THE CONTRACTOR 14 1 RAIN 15 1 RAIN 16 1 ---------------------------- 17 1 SATURDAY AREA/PROJECT ENGINEER 18 1 SUNDAY 19 1 20 1 21 1 WORK COMPLETED AND ACCEPTED - - - 0 ----- ----- ----- 87 29 58 3 SATURDAY 3 SUNDAY 0 HOLIDAY 2 TOO WET 2 RAIN 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11062301 MGR.NO. PAGE 001 CONT 6125 SEC 28 JOB 001 RES ENGR HOLLAND, HOWARD PROJ RMC - 612528001 HWY FM0586 2495 HWY 183 N BROWNWOOD CNTY BROWN DIST 23 CONTRACT PRICE $ 221,545.20 REPORT DATE 06/25/2012 14.27.01 CONTRACTOR D. I. J. CONSTRUCTION, INC. 440 EST PERIOD DEC 25,2006 TO MAR 21,2007 EST NO 005 & FINAL DIST. 23 COUNTY BROWN CONTROL 6125-28-001 PROJECT RMC - 612528001 HIGHWAY FM0586 0LIMITS- VARIOUS "." 0TYPE OF WORK- SEALING CRACKS 0 0050 SEALING CRACKS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0055 0712 JT/CRCK SEAL (RUBBER-ASPHALT) LMI 418.800 0.000 529.000 .00 0055 0712 ADJ EST QUANTITY TO DATE 0.000 0065 9001*JT/CRACK SEAL (RUBBER ASPHALT) CLASS A LMI 418.800 422.570 522.000 220,581.54 0070 9001*JT/CRCK SEAL (RUBBER ASPHALT) CLASS A LS 1.000 1.000 7,800.000 7,800.00 0 SUBTOTAL BID ITEMS $ 228,381.54 0 TOTAL AMOUNT WORK DONE SEALING CRACKS $ 228,381.54 0 TOTAL AMOUNT WORK DONE CONTROL 6125-28-001 $ 228,381.54 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11062301 MGR.NO. PAGE 001 CONT 6125 SEC 28 JOB 001 RES ENGR HOLLAND, HOWARD PROJ RMC - 612528001 HWY FM0586 2495 HWY 183 N BROWNWOOD CNTY BROWN DIST 23 CONTRACT PRICE $ 221,545.20 REPORT DATE 06/25/2012 14.27.01 CONTRACTOR D. I. J. CONSTRUCTION, INC. 440 EST PERIOD DEC 25,2006 TO MAR 21,2007 EST NO 005 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 "." DATE WORK BEGAN DEC 25, 2006 WORKING DAYS USED 29 PERCENT COMPLETE 100.00 PERCENT TIME USED 64.40 DATE COMPLETED MAR 21 2007 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6125-28-001 RMC - 612528001 23 FM0586 BROWN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) - * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09001* JT/CRACK SEAL (RUBBER ASPHALT) CLASS A LMI 418.800 422.570 522.000 220,581.54 9001* JT/CRCK SEAL (RUBBER ASPHALT) CLASS A LS 1.000 1.000 7,800.000 7,800.00 0 SUBTOTAL BID ITEMS $ 228,381.54 0 CONTRACT TOTAL ALL ITEMS $ 228,381.54 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11062301 MGR.NO. PAGE 001 CONT 6125 SEC 28 JOB 001 RES ENGR HOLLAND, HOWARD PROJ RMC - 612528001 HWY FM0586 2495 HWY 183 N BROWNWOOD CNTY BROWN DIST 23 CONTRACT PRICE $ 221,545.20 REPORT DATE 06/25/2012 14.27.01 CONTRACTOR D. I. J. CONSTRUCTION, INC. 440 EST PERIOD DEC 25,2006 TO MAR 21,2007 EST NO 005 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 25 RMC - 612528001 6125-28-001 228,381.54 .00 228,381.54 .00 .00 228,381.54 228,381.54 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 228,381.54 .00 228,381.54 .00 .00 228,381.54 228,381.54 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11062301 MGR.NO. PAGE 001 CONT 6125 SEC 28 JOB 001 RES ENGR HOLLAND, HOWARD PROJ RMC - 612528001 HWY FM0586 2495 HWY 183 N BROWNWOOD CNTY BROWN DIST 23 CONTRACT PRICE $ 221,545.20 REPORT DATE 06/25/2012 14.27.02 CONTRACTOR D. I. J. CONSTRUCTION, INC. 440 EST PERIOD DEC 25,2006 TO MAR 21,2007 EST NO 005 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6125-28-001 RMC - 612528001 23 FM0586 BROWN -LIMITS - VARIOUS "." - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 228,381.54