1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1134038 MGR.NO. 795 PAGE 001 CONT 6250 SEC 92 JOB 001 RES ENGR DARWIN LANKFORD PROJ RMC - 625092001 HWY SH0152 7599 US 287 CHILDRESS CNTY WHEELER DIST 25 CONTRACT PRICE $ 27,583.96 REPORT DATE 07/22/2013 09.01.25 CONTRACTOR SURFACE PREPARATION EST PERIOD MAR 18,2013 TO MAR 22,2013 EST NO 002 & FINAL TECHNOLOGIES, LLC 09024 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 19, 2013 TIME COMPUTED FROM MAR 18, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 20 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 13 TOTAL DAYS ALLOWED = 20 DATE WORK COMPLETED 03/22/13 DAYS CHARGED TO DATE = 3 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 570 0 LIQUIDATED DAMAGES 0 DAYS AT $ 570 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER 18 1 TIME SUSP - LETTER SUBMITTED 19 1 20 1 21 1 22 1 WORK COMPLETED - - - ----- ----- ----- 5 3 2 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 TIME SUSP - LETTER SUBMITTED 1 WORK COMPLETED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1134038 MGR.NO. 795 PAGE 001 CONT 6250 SEC 92 JOB 001 RES ENGR DARWIN LANKFORD PROJ RMC - 625092001 HWY SH0152 7599 US 287 CHILDRESS CNTY WHEELER DIST 25 CONTRACT PRICE $ 27,583.96 REPORT DATE 07/22/2013 09.01.26 CONTRACTOR SURFACE PREPARATION EST PERIOD MAR 18,2013 TO MAR 22,2013 EST NO 002 & FINAL TECHNOLOGIES, LLC 09024 DIST. 25 COUNTY WHEELER CONTROL 6250-92-001 PROJECT RMC - 625092001 HIGHWAY SH0152 0LIMITS- GRAY CO.LINE E, OKLA STATE LINE 0TYPE OF WORK- CENTERLINE RUMBLE STRIPS 0 0050 CENTERLINE TEXTURING NET LENGTH 30.690 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0055 0500 MOBILIZATION LS 1.000 1.000 13,000.000 13,000.00 0060 5369 CENTERLINE TEXTURING STA 1,620.440 1,559.060 9.000 14,031.54 0 SUBTOTAL BID ITEMS $ 27,031.54 0 TOTAL AMOUNT WORK DONE CENTERLINE TEXTURING $ 27,031.54 0 TOTAL AMOUNT WORK DONE CONTROL 6250-92-001 $ 27,031.54 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1134038 MGR.NO. 795 PAGE 001 CONT 6250 SEC 92 JOB 001 RES ENGR DARWIN LANKFORD PROJ RMC - 625092001 HWY SH0152 7599 US 287 CHILDRESS CNTY WHEELER DIST 25 CONTRACT PRICE $ 27,583.96 REPORT DATE 07/22/2013 09.01.26 CONTRACTOR SURFACE PREPARATION EST PERIOD MAR 18,2013 TO MAR 22,2013 EST NO 002 & FINAL TECHNOLOGIES, LLC 09024 0*********************************************************************************************************************************** -LIMITS - GRAY CO.LINE E, 0 OKLA STATE LINE DATE WORK BEGAN MAR 19, 2013 WORKING DAYS USED 3 PERCENT COMPLETE 100.00 PERCENT TIME USED 15.00 DATE COMPLETED MAR 22 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6250-92-001 RMC - 625092001 25 SH0152 WHEELER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0500 MOBILIZATION LS 1.000 1.000 13,000.000 13,000.00 5369 CENTERLINE TEXTURING STA 1,620.440 1,559.060 9.000 14,031.54 0 SUBTOTAL BID ITEMS $ 27,031.54 0 CONTRACT TOTAL ALL ITEMS $ 27,031.54 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1134038 MGR.NO. 795 PAGE 001 CONT 6250 SEC 92 JOB 001 RES ENGR DARWIN LANKFORD PROJ RMC - 625092001 HWY SH0152 7599 US 287 CHILDRESS CNTY WHEELER DIST 25 CONTRACT PRICE $ 27,583.96 REPORT DATE 07/22/2013 09.01.26 CONTRACTOR SURFACE PREPARATION EST PERIOD MAR 18,2013 TO MAR 22,2013 EST NO 002 & FINAL TECHNOLOGIES, LLC 09024 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 242 RMC - 625092001 6250-92-001 27,031.54 .00 27,031.54 .00 .00 27,031.54 26,641.54 390.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 27,031.54 .00 27,031.54 .00 .00 27,031.54 26,641.54 390.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1134038 MGR.NO. 795 PAGE 001 CONT 6250 SEC 92 JOB 001 RES ENGR DARWIN LANKFORD PROJ RMC - 625092001 HWY SH0152 7599 US 287 CHILDRESS CNTY WHEELER DIST 25 CONTRACT PRICE $ 27,583.96 REPORT DATE 07/22/2013 09.01.26 CONTRACTOR SURFACE PREPARATION EST PERIOD MAR 18,2013 TO MAR 22,2013 EST NO 002 & FINAL TECHNOLOGIES, LLC 09024 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6250-92-001 RMC - 625092001 25 SH0152 WHEELER -LIMITS - GRAY CO.LINE E, OKLA STATE LINE LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 55 0500 MOBILIZATION LS 1.000 0.030 13,000.000 390.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 390.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 27,031.54