1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6121605 MGR.NO. 058 PAGE 001 CONT 6235 SEC 58 JOB 001 RES ENGR REITMANN, BILL PROJ BPM - 623558001 HWY SH0035 P.O. BOX 1367 SINTON CNTY REFUGIO DIST 16 CONTRACT PRICE $ 32,100.00 REPORT DATE 03/04/2013 07.43.30 CONTRACTOR CERVANTES CONSTRUCTION 14396 EST PERIOD JUL 16,2012 TO JUL 18,2012 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 16, 2012 TIME COMPUTED FROM JUL 16, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 20 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 12 TOTAL DAYS ALLOWED = 20 DATE WORK COMPLETED 07/18/12 DAYS CHARGED TO DATE = 2 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 570 0 LIQUIDATED DAMAGES 0 DAYS AT $ 570 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - 16 1 TIME BEGAN - WORK BEGAN ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 WORK COMPLETED AND ACCEPTED - - - - 0 ----- ----- ----- 3 2 1 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6121605 MGR.NO. 058 PAGE 001 CONT 6235 SEC 58 JOB 001 RES ENGR REITMANN, BILL PROJ BPM - 623558001 HWY SH0035 P.O. BOX 1367 SINTON CNTY REFUGIO DIST 16 CONTRACT PRICE $ 32,100.00 REPORT DATE 03/04/2013 07.43.30 CONTRACTOR CERVANTES CONSTRUCTION 14396 EST PERIOD JUL 16,2012 TO JUL 18,2012 EST NO 002 & FINAL DIST. 16 COUNTY REFUGIO CONTROL 6235-58-001 PROJECT BPM - 623558001 HIGHWAY SH0035 0LIMITS- DRAW 1.7 MI. N. OF FM 774 . 0TYPE OF WORK- CONCRETE STRUCTURE REPAIR 0 0005 PREPARED BY ORLANDO J CARRILLO 0 0055 CONCRETE STRUCTURE REPAIR NET LENGTH 0.999 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0429 CNC STR REP (VERTICAL OR OVERHEAD) SF 180.000 110.000 120.000 13,200.00 0065 0500 MOBILIZATION LS 1.000 1.000 7,000.000 7,000.00 0070 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 3,500.000 3,500.00 0 SUBTOTAL BID ITEMS $ 23,700.00 0 TOTAL AMOUNT WORK DONE CONCRETE STRUCTURE REPAIR $ 23,700.00 0 TOTAL AMOUNT WORK DONE CONTROL 6235-58-001 $ 23,700.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6121605 MGR.NO. 058 PAGE 001 CONT 6235 SEC 58 JOB 001 RES ENGR REITMANN, BILL PROJ BPM - 623558001 HWY SH0035 P.O. BOX 1367 SINTON CNTY REFUGIO DIST 16 CONTRACT PRICE $ 32,100.00 REPORT DATE 03/04/2013 07.43.30 CONTRACTOR CERVANTES CONSTRUCTION 14396 EST PERIOD JUL 16,2012 TO JUL 18,2012 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - DRAW 1.7 MI. N. OF FM 774 0 . DATE WORK BEGAN JUL 16, 2012 WORKING DAYS USED 2 PERCENT COMPLETE 100.00 PERCENT TIME USED 10.00 DATE COMPLETED JUL 18 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6235-58-001 BPM - 623558001 16 SH0035 REFUGIO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0429 CNC STR REP (VERTICAL OR OVERHEAD) SF 180.000 110.000 120.000 13,200.00 0500 MOBILIZATION LS 1.000 1.000 7,000.000 7,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 3,500.000 3,500.00 0 SUBTOTAL BID ITEMS $ 23,700.00 0 CONTRACT TOTAL ALL ITEMS $ 23,700.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6121605 MGR.NO. 058 PAGE 001 CONT 6235 SEC 58 JOB 001 RES ENGR REITMANN, BILL PROJ BPM - 623558001 HWY SH0035 P.O. BOX 1367 SINTON CNTY REFUGIO DIST 16 CONTRACT PRICE $ 32,100.00 REPORT DATE 03/04/2013 07.43.30 CONTRACTOR CERVANTES CONSTRUCTION 14396 EST PERIOD JUL 16,2012 TO JUL 18,2012 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 196 BPM - 623558001 6235-58-001 23,700.00 .00 23,700.00 .00 .00 23,700.00 23,700.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 23,700.00 .00 23,700.00 .00 .00 23,700.00 23,700.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6121605 MGR.NO. 058 PAGE 001 CONT 6235 SEC 58 JOB 001 RES ENGR REITMANN, BILL PROJ BPM - 623558001 HWY SH0035 P.O. BOX 1367 SINTON CNTY REFUGIO DIST 16 CONTRACT PRICE $ 32,100.00 REPORT DATE 03/04/2013 07.43.30 CONTRACTOR CERVANTES CONSTRUCTION 14396 EST PERIOD JUL 16,2012 TO JUL 18,2012 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6235-58-001 BPM - 623558001 16 SH0035 REFUGIO -LIMITS - DRAW 1.7 MI. N. OF FM 774 . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 23,700.00