1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6124027 MGR.NO. 050 PAGE 001 CONT 6241 SEC 59 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 624159001 HWY FM0625 1071 N US 281 R.R. ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 499,994.40 REPORT DATE 12/02/2013 15.41.56 CONTRACTOR FOREMOST PAVING, INC. 620 EST PERIOD APR 04,2013 TO APR 15,2013 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 04, 2013 TIME COMPUTED FROM APR 15, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 20 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 TOTAL DAYS ALLOWED = 20 DATE WORK COMPLETED 04/15/13 DAYS CHARGED TO DATE = 0 4 1 WORK BEGAN- TIME CHARGES NOT STARTED ASSESSED LIQ DAMAGES = 0 5 1 WORK BEGAN- TIME CHARGES NOT STARTED LIQ DAMAGE RATE $ 590 6 1 SATURDAY 7 1 SUNDAY LIQUIDATED DAMAGES 8 1 WORK BEGAN- TIME CHARGES NOT STARTED 0 DAYS AT $ 590 PER DAY 9 1 WORK BEGAN- TIME CHARGES NOT STARTED TOTAL = $ .00 10 1 WORK BEGAN- TIME CHARGES NOT STARTED 11 1 WORK BEGAN- TIME CHARGES NOT STARTED CERTIFIED AS CORRECT AND 12 1 WORK BEGAN- TIME CHARGES NOT STARTED ONE COPY HAS BEEN GIVEN 13 1 SATURDAY TO THE CONTRACTOR 14 1 SUNDAY 15 1 WORK COMPLETED AND ACCEPTED ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 12 0 12 2 SATURDAY 2 SUNDAY 0 HOLIDAY 7 WORK BEGAN- TIME CHARGES NOT STARTED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6124027 MGR.NO. 050 PAGE 001 CONT 6241 SEC 59 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 624159001 HWY FM0625 1071 N US 281 R.R. ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 499,994.40 REPORT DATE 12/02/2013 15.41.56 CONTRACTOR FOREMOST PAVING, INC. 620 EST PERIOD APR 04,2013 TO APR 15,2013 EST NO 002 & FINAL DIST. 16 COUNTY JIM WELLS CONTROL 6241-59-001 PROJECT RMC - 624159001 HIGHWAY FM0625 0LIMITS- 3087 APPROXIMATELY 4.2 MILES SOUTH 0TYPE OF WORK- HMACP 0 0005 PREPARED BY ORLANDO J. CARRILLO 0 0055 HMACP NET LENGTH 4.196 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0500 MOBILIZATION LS 1.000 1.000 40,000.000 40,000.00 0065 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 6,000.000 6,000.00 0070 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 2,100.000 2,100.000 1.000 2,100.00 0075 0672 REFL PAV MRKR TY II-A-A EA 370.000 344.000 3.400 1,169.60 0080 3224 D-GR HMA(QCQA) TY-D SAC-B PG70-22 TON 4,760.000 4,609.450 90.750 418,307.59 0085 8251 RE PM W/RET REQ TY I(W)4"(SLD)(100MIL) LF 44,320.000 44,300.000 .320 14,176.00 0090 8251 RE PM W/RET REQ TY I(Y)4"(BRK)(100MIL) LF 5,600.000 5,400.000 .380 2,052.00 0095 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(100MIL) LF 6,200.000 6,401.000 .380 2,432.38 0 SUBTOTAL BID ITEMS $ 486,237.57 0 TOTAL AMOUNT WORK DONE HMACP $ 486,237.57 0 TOTAL AMOUNT WORK DONE CONTROL 6241-59-001 $ 486,237.57 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6124027 MGR.NO. 050 PAGE 001 CONT 6241 SEC 59 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 624159001 HWY FM0625 1071 N US 281 R.R. ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 499,994.40 REPORT DATE 12/02/2013 15.41.56 CONTRACTOR FOREMOST PAVING, INC. 620 EST PERIOD APR 04,2013 TO APR 15,2013 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - 3087 0 APPROXIMATELY 4.2 MILES SOUTH DATE WORK BEGAN APR 4 , 2013 WORKING DAYS USED 0 PERCENT COMPLETE 100.00 PERCENT TIME USED 0.00 DATE COMPLETED APR 15 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6241-59-001 RMC - 624159001 16 FM0625 JIM WELLS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0500 MOBILIZATION LS 1.000 1.000 40,000.000 40,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 6,000.000 6,000.00 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 2,100.000 2,100.000 1.000 2,100.00 0672 REFL PAV MRKR TY II-A-A EA 370.000 344.000 3.400 1,169.60 3224 D-GR HMA(QCQA) TY-D SAC-B PG70-22 TON 4,760.000 4,609.450 90.750 418,307.59 8251 RE PM W/RET REQ TY I(W)4"(SLD)(100MIL) LF 44,320.000 44,300.000 .320 14,176.00 8251 RE PM W/RET REQ TY I(Y)4"(BRK)(100MIL) LF 5,600.000 5,400.000 .380 2,052.00 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(100MIL) LF 6,200.000 6,401.000 .380 2,432.38 0 SUBTOTAL BID ITEMS $ 486,237.57 0 CONTRACT TOTAL ALL ITEMS $ 486,237.57 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6124027 MGR.NO. 050 PAGE 001 CONT 6241 SEC 59 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 624159001 HWY FM0625 1071 N US 281 R.R. ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 499,994.40 REPORT DATE 12/02/2013 15.41.56 CONTRACTOR FOREMOST PAVING, INC. 620 EST PERIOD APR 04,2013 TO APR 15,2013 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 126 RMC - 624159001 6241-59-001 486,237.57 .00 486,237.57 .00 .00 486,237.57 486,237.57 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 486,237.57 .00 486,237.57 .00 .00 486,237.57 486,237.57 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6124027 MGR.NO. 050 PAGE 001 CONT 6241 SEC 59 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 624159001 HWY FM0625 1071 N US 281 R.R. ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 499,994.40 REPORT DATE 12/02/2013 15.41.57 CONTRACTOR FOREMOST PAVING, INC. 620 EST PERIOD APR 04,2013 TO APR 15,2013 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6241-59-001 RMC - 624159001 16 FM0625 JIM WELLS -LIMITS - 3087 APPROXIMATELY 4.2 MILES SOUTH - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 486,237.57