1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5132401 MGR.NO. PAGE 001 CONT 6253 SEC 71 JOB 001 RES ENGR CEDILLO,MARGIE PROJ RMC - 625371001 HWY LP0375 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 57,303.24 REPORT DATE 09/11/2013 09.23.38 CONTRACTOR AZTEC CONTRACTORS, INC. 15808 EST PERIOD JUL 01,2013 TO AUG 12,2013 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 01, 2013 TIME COMPUTED FROM JUL 01, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 31 22 9 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 13 1 1 TOTAL DAYS ALLOWED = 30 2 1 DATE WORK COMPLETED 08/12/13 3 1 SATURDAY DAYS CHARGED TO DATE = 29 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 570 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 570 PER DAY 9 1 TOTAL = $ .00 10 1 SATURDAY 11 1 SUNDAY CERTIFIED AS CORRECT AND 12 1 WORK COMPLETED AND ACCEPTED ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 43 29 14 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5132401 MGR.NO. PAGE 001 CONT 6253 SEC 71 JOB 001 RES ENGR CEDILLO,MARGIE PROJ RMC - 625371001 HWY LP0375 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 57,303.24 REPORT DATE 09/11/2013 09.23.38 CONTRACTOR AZTEC CONTRACTORS, INC. 15808 EST PERIOD JUL 01,2013 TO AUG 12,2013 EST NO 002 & FINAL DIST. 24 COUNTY EL PASO CONTROL 6253-71-001 PROJECT RMC - 625371001 HIGHWAY LP0375 0LIMITS- SEE PLAN SHEETS SEE PLAN SHEETS 0TYPE OF WORK- BIRD DETERRENT SYSTEM 0 0050 BOB BIELEK, P.E. DISTRICT ENGINEER NET LENGTH 10.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 EAST AREA OFFICE/WEST AREA OFFICE 0075 BIRD DETERRENT SYSTEM 0 0080 0427 EPOXY PAINT FINISH SF 1,000.000 8,500.500 2.240 19,041.12 0080 0427 ADJ EST QUANTITY TO DATE 2,548.000 0085 0446 SPOT CLEAN & PAINT EXIST STR LS 1.000 1.250 17,391.000 21,738.75 0085 0446 ADJ EST QUANTITY TO DATE 1.250 0090 0500 MOBILIZATION LS 1.000 1.250 5,610.000 7,012.50 0090 0500 ADJ EST QUANTITY TO DATE 1.250 0095 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.500 2.000 4,488.000 8,976.00 0095 0502 ADJ EST QUANTITY TO DATE 2.000 0100 2092 SPIDERS EA 30.000 30.000 72.930 2,187.90 0105 2092 SPIKES LF 460.000 949.000 6.730 6,386.77 0105 2092 ADJ EST QUANTITY TO DATE 1,028.000 0110 2092 NETTING SYSTEMS SF 7,134.000 5,277.500 2.810 14,829.78 0 SUBTOTAL BID ITEMS $ 80,172.82 0 TOTAL AMOUNT WORK DONE BOB BIELEK, P.E. DISTRICT ENGINEER $ 80,172.82 0 TOTAL AMOUNT WORK DONE CONTROL 6253-71-001 $ 80,172.82 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5132401 MGR.NO. PAGE 001 CONT 6253 SEC 71 JOB 001 RES ENGR CEDILLO,MARGIE PROJ RMC - 625371001 HWY LP0375 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 57,303.24 REPORT DATE 09/11/2013 09.23.38 CONTRACTOR AZTEC CONTRACTORS, INC. 15808 EST PERIOD JUL 01,2013 TO AUG 12,2013 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - SEE PLAN SHEETS 0 SEE PLAN SHEETS DATE WORK BEGAN JUL 1 , 2013 WORKING DAYS USED 29 PERCENT COMPLETE 100.00 PERCENT TIME USED 96.60 DATE COMPLETED AUG 12 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6253-71-001 RMC - 625371001 24 LP0375 EL PASO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0427 EPOXY PAINT FINISH SF 1,000.000 8,500.500 2.240 19,041.12 0427 ADJ EST QUANTITY TO DATE 2,548.000 0446 SPOT CLEAN & PAINT EXIST STR LS 1.000 1.250 17,391.000 21,738.75 0446 ADJ EST QUANTITY TO DATE 1.250 0500 MOBILIZATION LS 1.000 1.250 5,610.000 7,012.50 0500 ADJ EST QUANTITY TO DATE 1.250 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.500 2.000 4,488.000 8,976.00 0502 ADJ EST QUANTITY TO DATE 2.000 2092 SPIDERS EA 30.000 30.000 72.930 2,187.90 2092 SPIKES LF 460.000 949.000 6.730 6,386.77 2092 ADJ EST QUANTITY TO DATE 1,028.000 2092 NETTING SYSTEMS SF 7,134.000 5,277.500 2.810 14,829.78 0 SUBTOTAL BID ITEMS $ 80,172.82 0 CONTRACT TOTAL ALL ITEMS $ 80,172.82 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5132401 MGR.NO. PAGE 001 CONT 6253 SEC 71 JOB 001 RES ENGR CEDILLO,MARGIE PROJ RMC - 625371001 HWY LP0375 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 57,303.24 REPORT DATE 09/11/2013 09.23.38 CONTRACTOR AZTEC CONTRACTORS, INC. 15808 EST PERIOD JUL 01,2013 TO AUG 12,2013 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 72 RMC - 625371001 6253-71-001 80,172.82 .00 80,172.82 .00 .00 80,172.82 61,503.46 18,669.36 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 80,172.82 .00 80,172.82 .00 .00 80,172.82 61,503.46 18,669.36 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5132401 MGR.NO. PAGE 001 CONT 6253 SEC 71 JOB 001 RES ENGR CEDILLO,MARGIE PROJ RMC - 625371001 HWY LP0375 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 57,303.24 REPORT DATE 09/11/2013 09.23.38 CONTRACTOR AZTEC CONTRACTORS, INC. 15808 EST PERIOD JUL 01,2013 TO AUG 12,2013 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6253-71-001 RMC - 625371001 24 LP0375 EL PASO -LIMITS - SEE PLAN SHEETS SEE PLAN SHEETS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 80 0427 EPOXY PAINT FINISH SF 1,000.000 1,352.000 2.240 3,028.48 85 0446 SPOT CLEAN & PAINT EXIST STR LS 1.000 0.350 17,391.000 6,086.85 90 0500 MOBILIZATION LS 1.000 0.350 5,610.000 1,963.50 95 0502 BARRICADES, SIGNS AND MO 1.500 1.000 4,488.000 4,488.00 TRAFFIC HANDLING 105 2092 SPIKES LF 460.000 461.000 6.730 3,102.53 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 18,669.36 0 TOTAL AMOUNT WORK DONE TO DATE - $ 80,172.82