1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4134033 MGR.NO. 770 PAGE 001 CONT 6255 SEC 90 JOB 001 RES ENGR CEDILLO, MARGIE PROJ RMC - 625590001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 346,500.00 REPORT DATE 06/11/2014 09.25.19 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 16,2013 TO OCT 15,2013 EST NO 012 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 16, 2013 TIME COMPUTED FROM JUL 16, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 40 289 44 245 BROUGHT FORWARD ADDL DAYS GRANTED = 20 OCT 13 1 1 TOTAL DAYS ALLOWED = 60 2 1 DATE WORK COMPLETED 10/15/13 3 1 DAYS CHARGED TO DATE = 59 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 590 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 590 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 304 59 245 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4134033 MGR.NO. 770 PAGE 001 CONT 6255 SEC 90 JOB 001 RES ENGR CEDILLO, MARGIE PROJ RMC - 625590001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 346,500.00 REPORT DATE 06/11/2014 09.25.20 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 16,2013 TO OCT 15,2013 EST NO 012 & FINAL DIST. 24 COUNTY EL PASO CONTROL 6255-90-001 PROJECT RMC - 625590001 HIGHWAY IH0010 0LIMITS- VARIOUS LOCATIONS VARIOUS LOCATIONS 0TYPE OF WORK- STRUCTURES 0 0050 BOB BIELIK, P.E. DISTRICT ENGINEER NET LENGTH100.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 EAST AREA OFFICE 0075 CTB/BARRIER REPAIR 0 0080 0423 RETAINING WALL (STONE) SF 300.000 185.000 40.000 7,400.00 0085 0427 EPOXY PAINT FINISH SF 1,500.000 1,192.850 7.000 8,349.95 0090 0429 CNC STR REP (HORIZONTAL) SF 3,000.000 955.690 73.000 69,765.37 0095 0452 REMOV RAIL (CTB) LF 100.000 0.000 250.000 .00 0100 0500 MOBILIZATION LS 1.000 1.000 34,000.000 34,000.00 0105 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 3.000 12,000.000 36,000.00 0110 0720 SPALLING REPAIR (POLYMERIC)(FLEXIBLE) GAL 100.000 0.000 100.000 .00 0115 6834 PORTABLE CHANGEABLE MESSAGE SIGN EA 6.000 7.000 2,000.000 14,000.00 0120 0512*PORT CTB (MOVE)(SAFETY SH)(TY 1) LF 60.000 60.000 61.166 3,669.96 0125 9001*PAYMENT FOR SPECIAL PROVISION 004-2007 EA 1.000 1.000 10,464.810 10,464.81 0 SUBTOTAL BID ITEMS $ 183,650.09 0 TOTAL AMOUNT WORK DONE BOB BIELIK, P.E. DISTRICT ENGINEER $ 183,650.09 0 TOTAL AMOUNT WORK DONE CONTROL 6255-90-001 $ 183,650.09 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4134033 MGR.NO. 770 PAGE 001 CONT 6255 SEC 90 JOB 001 RES ENGR CEDILLO, MARGIE PROJ RMC - 625590001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 346,500.00 REPORT DATE 06/11/2014 09.25.20 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 16,2013 TO OCT 15,2013 EST NO 012 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS 0 VARIOUS LOCATIONS DATE WORK BEGAN JUL 16, 2013 WORKING DAYS USED 59 PERCENT COMPLETE 100.00 PERCENT TIME USED 98.30 DATE COMPLETED OCT 15 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6255-90-001 RMC - 625590001 24 IH0010 EL PASO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0423 RETAINING WALL (STONE) SF 300.000 185.000 40.000 7,400.00 0427 EPOXY PAINT FINISH SF 1,500.000 1,192.850 7.000 8,349.95 0429 CNC STR REP (HORIZONTAL) SF 3,000.000 955.690 73.000 69,765.37 0500 MOBILIZATION LS 1.000 1.000 34,000.000 34,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 3.000 12,000.000 36,000.00 6834 PORTABLE CHANGEABLE MESSAGE SIGN EA 6.000 7.000 2,000.000 14,000.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00512* PORT CTB (MOVE)(SAFETY SH)(TY 1) LF 60.000 60.000 61.166 3,669.96 9001* PAYMENT FOR SPECIAL PROVISION 004-2007 EA 1.000 1.000 10,464.810 10,464.81 0 SUBTOTAL BID ITEMS $ 183,650.09 0 CONTRACT TOTAL ALL ITEMS $ 183,650.09 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4134033 MGR.NO. 770 PAGE 001 CONT 6255 SEC 90 JOB 001 RES ENGR CEDILLO, MARGIE PROJ RMC - 625590001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 346,500.00 REPORT DATE 06/11/2014 09.25.20 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 16,2013 TO OCT 15,2013 EST NO 012 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 72 RMC - 625590001 6255-90-001 183,650.09 .00 183,650.09 .00 .00 183,650.09 173,185.28 10,464.81 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 183,650.09 .00 183,650.09 .00 .00 183,650.09 173,185.28 10,464.81 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4134033 MGR.NO. 770 PAGE 001 CONT 6255 SEC 90 JOB 001 RES ENGR CEDILLO, MARGIE PROJ RMC - 625590001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 346,500.00 REPORT DATE 06/11/2014 09.25.20 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 16,2013 TO OCT 15,2013 EST NO 012 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6255-90-001 RMC - 625590001 24 IH0010 EL PASO -LIMITS - VARIOUS LOCATIONS VARIOUS LOCATIONS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) - * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 125 9001* PAYMENT FOR SPECIAL EA 0.000 1.000 10,464.810 10,464.81 PROVISION 004-2007 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 10,464.81 0 TOTAL AMOUNT WORK DONE TO DATE - $ 183,650.09