1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5071201 MGR.NO. 050 PAGE 001 CONT 6160 SEC 04 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 616004001 HWY SH0288 1033 E. ORANGE ST ANGLETO CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 139,500.00 REPORT DATE 10/14/2013 16.28.40 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD AUG 16,2007 TO SEP 30,2008 EST NO 015 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 16, 2007 TIME COMPUTED FROM AUG 16, 2007 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 366 382 382 0 BROUGHT FORWARD ADDL DAYS GRANTED = 45 SEP 08 1 1 TOTAL DAYS ALLOWED = 411 2 1 DATE WORK COMPLETED 09/29/08 3 1 DAYS CHARGED TO DATE = 411 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 - ----- ----- ----- 411 411 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5071201 MGR.NO. 050 PAGE 001 CONT 6160 SEC 04 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 616004001 HWY SH0288 1033 E. ORANGE ST ANGLETO CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 139,500.00 REPORT DATE 10/14/2013 16.28.40 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD AUG 16,2007 TO SEP 30,2008 EST NO 015 & FINAL DIST. 12 COUNTY BRAZORIA CONTROL 6160-04-001 PROJECT RMC - 616004001 HIGHWAY SH0288 0LIMITS- VARIOUS HWYS IN BRAZORIA COUNTY VARIOUS HWYS IN BRAZORIA COUNTY 0TYPE OF WORK- FULL DEPTH REPAIR OF CONCRETE PAV 0 0005 PREPARED BY MICHELLE E. MILLIARD, P.E. 0 0055 FULL DEPTH REPAIR OF CONCRETE PVMNT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0361 FULL-DEPTH REPAIR CRCP (10") SY 200.000 200.005 204.000 40,801.02 0065 0361 FULL-DEPTH REPAIR CPJR (8") SY 90.000 23.666 190.000 4,496.54 0070 0361 FULL-DEPTH REPAIR CPJR (10") SY 400.000 396.914 204.000 80,970.46 0 SUBTOTAL BID ITEMS $ 126,268.02 0 TOTAL AMOUNT WORK DONE FULL DEPTH REPAIR OF CONCRETE PVMNT $ 126,268.02 0 0120 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0121 POLICE OFFICER FOR TRAFFIC CONTROL 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6160-04-001 $ 126,268.02 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5071201 MGR.NO. 050 PAGE 001 CONT 6160 SEC 04 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 616004001 HWY SH0288 1033 E. ORANGE ST ANGLETO CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 139,500.00 REPORT DATE 10/14/2013 16.28.40 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD AUG 16,2007 TO SEP 30,2008 EST NO 015 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN BRAZORIA COUNTY 0 VARIOUS HWYS IN BRAZORIA COUNTY DATE WORK BEGAN AUG 16, 2007 WORKING DAYS USED 411 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED SEP 29 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6160-04-001 RMC - 616004001 12 SH0288 BRAZORIA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0361 FULL-DEPTH REPAIR CRCP (10") SY 200.000 200.005 204.000 40,801.02 0361 FULL-DEPTH REPAIR CPJR (8") SY 90.000 23.666 190.000 4,496.54 0361 FULL-DEPTH REPAIR CPJR (10") SY 400.000 396.914 204.000 80,970.46 0 SUBTOTAL BID ITEMS $ 126,268.02 0 CONTRACT TOTAL ALL ITEMS $ 126,268.02 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5071201 MGR.NO. 050 PAGE 001 CONT 6160 SEC 04 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 616004001 HWY SH0288 1033 E. ORANGE ST ANGLETO CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 139,500.00 REPORT DATE 10/14/2013 16.28.40 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD AUG 16,2007 TO SEP 30,2008 EST NO 015 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 20 RMC - 616004001 6160-04-001 126,268.02 .00 126,268.02 .00 .00 126,268.02 126,268.02 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 126,268.02 .00 126,268.02 .00 .00 126,268.02 126,268.02 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5071201 MGR.NO. 050 PAGE 001 CONT 6160 SEC 04 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 616004001 HWY SH0288 1033 E. ORANGE ST ANGLETO CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 139,500.00 REPORT DATE 10/14/2013 16.28.40 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD AUG 16,2007 TO SEP 30,2008 EST NO 015 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6160-04-001 RMC - 616004001 12 SH0288 BRAZORIA -LIMITS - VARIOUS HWYS IN BRAZORIA COUNTY VARIOUS HWYS IN BRAZORIA COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 126,268.02