1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7071210 MGR.NO. 050 PAGE 001 CONT 6160 SEC 89 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 616089001 HWY SH0288 1033 E. ORANGE ST ANGLETO CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 338,200.00 REPORT DATE 08/08/2013 16.23.29 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 31,2007 TO JUN 02,2008 EST NO 012 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 31, 2007 TIME COMPUTED FROM AUG 31, 2007 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 366 275 275 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 08 1 1 TOTAL DAYS ALLOWED = 366 2 1 DATE WORK COMPLETED 06/02/08 DAYS CHARGED TO DATE = 277 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 0 0 LIQUIDATED DAMAGES 0 DAYS AT $ 0 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 277 277 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7071210 MGR.NO. 050 PAGE 001 CONT 6160 SEC 89 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 616089001 HWY SH0288 1033 E. ORANGE ST ANGLETO CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 338,200.00 REPORT DATE 08/08/2013 16.23.29 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 31,2007 TO JUN 02,2008 EST NO 012 & FINAL INC. 00644 DIST. 12 COUNTY BRAZORIA CONTROL 6160-89-001 PROJECT RMC - 616089001 HIGHWAY SH0288 0LIMITS- VARIOUS HWYS IN BRAZORIA COUNTY VARIOUS HWYS IN BRAZORIA COUNTY 0TYPE OF WORK- FLEXIBLE PAVEMENT STRUCTURE REPAIR 0 0005 PREPARED BY MICHELLE E. MILLIARD, P.E. 0 0055 FLEXIBLE PAVEMENT STRUCTURE REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 5,600.000 5,593.161 42.000 234,912.76 0065 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") SY 4,000.000 4,000.883 25.750 103,022.74 0 SUBTOTAL BID ITEMS $ 337,935.50 0 TOTAL AMOUNT WORK DONE FLEXIBLE PAVEMENT STRUCTURE REPAIR $ 337,935.50 0 0115 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0116 UNIFORM POLICE OFFICER 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6160-89-001 $ 337,935.50 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7071210 MGR.NO. 050 PAGE 001 CONT 6160 SEC 89 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 616089001 HWY SH0288 1033 E. ORANGE ST ANGLETO CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 338,200.00 REPORT DATE 08/08/2013 16.23.29 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 31,2007 TO JUN 02,2008 EST NO 012 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN BRAZORIA COUNTY 0 VARIOUS HWYS IN BRAZORIA COUNTY DATE WORK BEGAN AUG 31, 2007 WORKING DAYS USED 277 PERCENT COMPLETE 100.00 PERCENT TIME USED 75.60 DATE COMPLETED JUN 2 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6160-89-001 RMC - 616089001 12 SH0288 BRAZORIA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 5,600.000 5,593.161 42.000 234,912.76 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") SY 4,000.000 4,000.883 25.750 103,022.74 0 SUBTOTAL BID ITEMS $ 337,935.50 0 CONTRACT TOTAL ALL ITEMS $ 337,935.50 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7071210 MGR.NO. 050 PAGE 001 CONT 6160 SEC 89 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 616089001 HWY SH0288 1033 E. ORANGE ST ANGLETO CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 338,200.00 REPORT DATE 08/08/2013 16.23.29 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 31,2007 TO JUN 02,2008 EST NO 012 & FINAL INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 20 RMC - 616089001 6160-89-001 337,935.50 .00 337,935.50 .00 .00 337,935.50 337,935.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 337,935.50 .00 337,935.50 .00 .00 337,935.50 337,935.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7071210 MGR.NO. 050 PAGE 001 CONT 6160 SEC 89 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 616089001 HWY SH0288 1033 E. ORANGE ST ANGLETO CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 338,200.00 REPORT DATE 08/08/2013 16.23.30 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD AUG 31,2007 TO JUN 02,2008 EST NO 012 & FINAL INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6160-89-001 RMC - 616089001 12 SH0288 BRAZORIA -LIMITS - VARIOUS HWYS IN BRAZORIA COUNTY VARIOUS HWYS IN BRAZORIA COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 337,935.50