1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2081205 MGR.NO. 053 PAGE 001 CONT 6173 SEC 84 JOB 001 RES ENGR BAKER, KAREN PROJ RMC - 617384001 HWY IH0045 901 N.FM 3083 EAST CONROE CNTY MONTGOMERY DIST 12 CONTRACT PRICE $ 354,700.00 REPORT DATE 11/04/2013 16.00.16 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 01, 2008 TIME COMPUTED FROM SEP 01, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 366 334 334 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 1 1 TOTAL DAYS ALLOWED = 366 2 1 DATE WORK COMPLETED 08/31/09 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 365 365 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2081205 MGR.NO. 053 PAGE 001 CONT 6173 SEC 84 JOB 001 RES ENGR BAKER, KAREN PROJ RMC - 617384001 HWY IH0045 901 N.FM 3083 EAST CONROE CNTY MONTGOMERY DIST 12 CONTRACT PRICE $ 354,700.00 REPORT DATE 11/04/2013 16.00.17 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL INC. 00644 DIST. 12 COUNTY MONTGOMERY CONTROL 6173-84-001 PROJECT RMC - 617384001 HIGHWAY IH0045 0LIMITS- VARIOUS HWYS IN MONTGOMERY COUNTY VARIOUS HWYS IN MONTGOMERY COUNTY 0TYPE OF WORK- ASPHALT PAVEMENT REPAIR 0 0050 POTHOLE REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY ANDY D. VARILLA 0 0075 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") SY 1,000.000 0.000 42.000 .00 0080 0700 POTHOLE REPAIR (SAW-CUT) SY 6,000.000 5,019.054 45.200 226,861.24 0085 0700 EMERGENCY MOBILIZATION EA 3.000 0.000 1,000.000 .00 0090 0712 JT/CRCK ROUT/SEAL (POLY MOD ASPH EMUL) LF 1,000.000 0.000 1.000 .00 0095 7288 FIBER REINFORCED POLYMER PATCH MATERIAL LB 15,000.000 0.000 2.500 .00 0 SUBTOTAL BID ITEMS $ 226,861.24 0 TOTAL AMOUNT WORK DONE POTHOLE REPAIR $ 226,861.24 0 0145 CONTRACTOR FORCE ACT OR AGR UNIT NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0146 PRICE 0147 POLICE OFFICE FOR TRAFFIC CONTROL 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACT OR AGR UNIT $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6173-84-001 $ 226,861.24 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2081205 MGR.NO. 053 PAGE 001 CONT 6173 SEC 84 JOB 001 RES ENGR BAKER, KAREN PROJ RMC - 617384001 HWY IH0045 901 N.FM 3083 EAST CONROE CNTY MONTGOMERY DIST 12 CONTRACT PRICE $ 354,700.00 REPORT DATE 11/04/2013 16.00.17 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN MONTGOMERY COUNTY 0 VARIOUS HWYS IN MONTGOMERY COUNTY DATE WORK BEGAN SEP 1 , 2008 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 99.70 DATE COMPLETED AUG 31 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6173-84-001 RMC - 617384001 12 IH0045 MONTGOMERY - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0700 POTHOLE REPAIR (SAW-CUT) SY 6,000.000 5,019.054 45.200 226,861.24 0 SUBTOTAL BID ITEMS $ 226,861.24 0 CONTRACT TOTAL ALL ITEMS $ 226,861.24 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2081205 MGR.NO. 053 PAGE 001 CONT 6173 SEC 84 JOB 001 RES ENGR BAKER, KAREN PROJ RMC - 617384001 HWY IH0045 901 N.FM 3083 EAST CONROE CNTY MONTGOMERY DIST 12 CONTRACT PRICE $ 354,700.00 REPORT DATE 11/04/2013 16.00.17 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 170 RMC - 617384001 6173-84-001 226,861.24 .00 226,861.24 .00 .00 226,861.24 226,861.24 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 226,861.24 .00 226,861.24 .00 .00 226,861.24 226,861.24 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2081205 MGR.NO. 053 PAGE 001 CONT 6173 SEC 84 JOB 001 RES ENGR BAKER, KAREN PROJ RMC - 617384001 HWY IH0045 901 N.FM 3083 EAST CONROE CNTY MONTGOMERY DIST 12 CONTRACT PRICE $ 354,700.00 REPORT DATE 11/04/2013 16.00.17 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6173-84-001 RMC - 617384001 12 IH0045 MONTGOMERY -LIMITS - VARIOUS HWYS IN MONTGOMERY COUNTY VARIOUS HWYS IN MONTGOMERY COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 226,861.24