1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7081208 MGR.NO. 060 PAGE 001 CONT 6179 SEC 16 JOB 001 RES ENGR WILLIAM, BABBINGTON PROJ RMC - 617916001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 269,270.00 REPORT DATE 12/03/2013 17.25.13 CONTRACTOR SWEEPING SERVICES OF TEXAS - EST PERIOD SEP 07,2008 TO SEP 06,2009 EST NO 014 & FINAL OPERATING, L.P. 11910 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 09, 2008 TIME COMPUTED FROM SEP 07, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 359 359 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 09 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 09/06/09 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 WORK COMPLETED AND ACCEPTED LIQUIDATED DAMAGES 0 DAYS AT $ 0 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 365 365 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7081208 MGR.NO. 060 PAGE 001 CONT 6179 SEC 16 JOB 001 RES ENGR WILLIAM, BABBINGTON PROJ RMC - 617916001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 269,270.00 REPORT DATE 12/03/2013 17.25.14 CONTRACTOR SWEEPING SERVICES OF TEXAS - EST PERIOD SEP 07,2008 TO SEP 06,2009 EST NO 014 & FINAL OPERATING, L.P. 11910 DIST. 12 COUNTY GALVESTON CONTROL 6179-16-001 PROJECT RMC - 617916001 HIGHWAY IH0045 0LIMITS- VARIOUS HWYS IN GALVESTON COUNTY VARIOUS HYWS IN GALVESTON COUNTY 0TYPE OF WORK- CLEANING AND SWEEPING HIGHWAYS 0 0005 PREPARED BY: JAMIE MEDINA 0 0055 SWEEPING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0738 CLEANING/SWEEPING (SPOT) MI 50.000 55.000 25.000 1,375.00 0065 0738 CLEANING/SWEEPING (HANDWORK) SY 20,000.000 15,689.776 .150 2,353.47 0070 0738 CLEAN/SWEEP-CENTER MEDIAN-AREA (1) CYC 18.000 17.640 3,840.000 67,737.60 0075 0738 CLEAN/SWEEP-CENTER MEDIAN-AREA (2) CYC 18.000 17.000 950.000 16,150.00 0080 0738 CLEAN/SWEEP-CENTER MEDIAN-AREA (3) CYC 12.000 12.000 500.000 6,000.00 0085 0738 CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA (1) CYC 18.000 17.360 3,840.000 66,662.40 0090 0738 CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA (2) CYC 18.000 18.000 800.000 14,400.00 0095 0738 CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA (3) CYC 12.000 11.000 500.000 5,500.00 0100 0738 CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA (4) CYC 6.000 7.000 400.000 2,800.00 0105 0738 CLEAN/SWEEP-FRONTAGE ROAD-AREA (1) CYC 12.000 12.000 3,940.000 47,280.00 0110 0738 CLEAN/SWEEP-FRONTAGE ROAD-AREA (2) CYC 12.000 13.000 1,200.000 15,600.00 0115 0738 CLEAN/SWEEP-FRONTAGE ROAD-AREA (3) CYC 6.000 6.000 600.000 3,600.00 0120 0738 CLEAN/SWEEP (ENTR/EXT RMP)(AREA 3) CYC 6.000 6.000 500.000 3,000.00 0125 0738 CLEAN/SWEEP (ENTR/EXT RMP)(AREA 1) CYC 6.000 7.000 1,600.000 11,200.00 0130 0738 CLEAN/SWEEPING-(ENTR/EXT RMP)(AREA 2) CYC 6.000 6.000 500.000 3,000.00 1 SUBTOTAL BID ITEMS $ 266,658.47 0 TOTAL AMOUNT WORK DONE SWEEPING $ 266,658.47 0 TOTAL AMOUNT WORK DONE CONTROL 6179-16-001 $ 266,658.47 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7081208 MGR.NO. 060 PAGE 001 CONT 6179 SEC 16 JOB 001 RES ENGR WILLIAM, BABBINGTON PROJ RMC - 617916001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 269,270.00 REPORT DATE 12/03/2013 17.25.14 CONTRACTOR SWEEPING SERVICES OF TEXAS - EST PERIOD SEP 07,2008 TO SEP 06,2009 EST NO 014 & FINAL OPERATING, L.P. 11910 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN GALVESTON COUNTY 0 VARIOUS HYWS IN GALVESTON COUNTY DATE WORK BEGAN SEP 9 , 2008 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED SEP 6 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6179-16-001 RMC - 617916001 12 IH0045 GALVESTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0738 CLEANING/SWEEPING (SPOT) MI 50.000 55.000 25.000 1,375.00 0738 CLEANING/SWEEPING (HANDWORK) SY 20,000.000 15,689.776 .150 2,353.47 0738 CLEAN/SWEEP-CENTER MEDIAN-AREA (1) CYC 18.000 17.640 3,840.000 67,737.60 0738 CLEAN/SWEEP-CENTER MEDIAN-AREA (2) CYC 18.000 17.000 950.000 16,150.00 0738 CLEAN/SWEEP-CENTER MEDIAN-AREA (3) CYC 12.000 12.000 500.000 6,000.00 0738 CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA (1) CYC 18.000 17.360 3,840.000 66,662.40 0738 CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA (2) CYC 18.000 18.000 800.000 14,400.00 0738 CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA (3) CYC 12.000 11.000 500.000 5,500.00 0738 CLEAN/SWEEP-OUTSIDE MAIN LANE-AREA (4) CYC 6.000 7.000 400.000 2,800.00 0738 CLEAN/SWEEP-FRONTAGE ROAD-AREA (1) CYC 12.000 12.000 3,940.000 47,280.00 0738 CLEAN/SWEEP-FRONTAGE ROAD-AREA (2) CYC 12.000 13.000 1,200.000 15,600.00 0738 CLEAN/SWEEP-FRONTAGE ROAD-AREA (3) CYC 6.000 6.000 600.000 3,600.00 0738 CLEAN/SWEEP (ENTR/EXT RMP)(AREA 3) CYC 6.000 6.000 500.000 3,000.00 0738 CLEAN/SWEEP (ENTR/EXT 1 RMP)(AREA 1) CYC 6.000 7.000 1,600.000 11,200.00 0738 CLEAN/SWEEPING-(ENTR/EXT RMP)(AREA 2) CYC 6.000 6.000 500.000 3,000.00 0 SUBTOTAL BID ITEMS $ 266,658.47 0 CONTRACT TOTAL ALL ITEMS $ 266,658.47 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7081208 MGR.NO. 060 PAGE 001 CONT 6179 SEC 16 JOB 001 RES ENGR WILLIAM, BABBINGTON PROJ RMC - 617916001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 269,270.00 REPORT DATE 12/03/2013 17.25.14 CONTRACTOR SWEEPING SERVICES OF TEXAS - EST PERIOD SEP 07,2008 TO SEP 06,2009 EST NO 014 & FINAL OPERATING, L.P. 11910 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85 RMC - 617916001 6179-16-001 266,658.47 .00 266,658.47 .00 .00 266,658.47 266,658.47 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 266,658.47 .00 266,658.47 .00 .00 266,658.47 266,658.47 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7081208 MGR.NO. 060 PAGE 001 CONT 6179 SEC 16 JOB 001 RES ENGR WILLIAM, BABBINGTON PROJ RMC - 617916001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 269,270.00 REPORT DATE 12/03/2013 17.25.14 CONTRACTOR SWEEPING SERVICES OF TEXAS - EST PERIOD SEP 07,2008 TO SEP 06,2009 EST NO 014 & FINAL OPERATING, L.P. 11910 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6179-16-001 RMC - 617916001 12 IH0045 GALVESTON -LIMITS - VARIOUS HWYS IN GALVESTON COUNTY VARIOUS HYWS IN GALVESTON COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 266,658.47