1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5091241 MGR.NO. 060 PAGE 001 CONT 6192 SEC 34 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ EMC - 619234001 HWY SH0087 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 513,867.50 REPORT DATE 11/08/2013 16.16.41 CONTRACTOR J.D. ABRAMS, L.P. 9821 EST PERIOD JUN 08,2009 TO NOV 19,2009 EST NO 008 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 08, 2009 TIME COMPUTED FROM JUN 08, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 45 146 54 92 BROUGHT FORWARD ADDL DAYS GRANTED = 20 NOV 09 1 1 AWAITING FINAL INSPECTION TOTAL DAYS ALLOWED = 65 2 1 AWAITING FINAL INSPECTION DATE WORK COMPLETED 11/19/09 3 1 AWAITING FINAL INSPECTION DAYS CHARGED TO DATE = 54 4 1 AWAITING FINAL INSPECTION ASSESSED LIQ DAMAGES = 0 5 1 AWAITING FINAL INSPECTION LIQ DAMAGE RATE $ 525 6 1 AWAITING FINAL INSPECTION 7 1 AWAITING FINAL INSPECTION LIQUIDATED DAMAGES 8 1 AWAITING FINAL INSPECTION 0 DAYS AT $ 525 PER DAY 9 1 AWAITING FINAL INSPECTION TOTAL = $ .00 10 1 AWAITING FINAL INSPECTION 11 1 AWAITING FINAL INSPECTION CERTIFIED AS CORRECT AND 12 1 AWAITING FINAL INSPECTION ONE COPY HAS BEEN GIVEN 13 1 AWAITING FINAL INSPECTION TO THE CONTRACTOR 14 1 AWAITING FINAL INSPECTION 15 1 AWAITING FINAL INSPECTION 16 1 AWAITING FINAL INSPECTION ---------------------------- 17 1 AWAITING FINAL INSPECTION AREA/PROJECT ENGINEER 18 1 AWAITING FINAL INSPECTION 19 1 WORK ACCEPTED - - - - ----- ----- ----- 165 54 111 0 SATURDAY 0 SUNDAY 0 HOLIDAY 18 AWAITING FINAL INSPECTION 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5091241 MGR.NO. 060 PAGE 001 CONT 6192 SEC 34 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ EMC - 619234001 HWY SH0087 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 513,867.50 REPORT DATE 11/08/2013 16.16.42 CONTRACTOR J.D. ABRAMS, L.P. 9821 EST PERIOD JUN 08,2009 TO NOV 19,2009 EST NO 008 & FINAL DIST. 12 COUNTY GALVESTON CONTROL 6192-34-001 PROJECT EMC - 619234001 HIGHWAY SH0087 0LIMITS- SH 124 TO APPROXIMATELY 4.7 MILES SOUTHWEST ALONG SH87 0TYPE OF WORK- TEMPORARY REVETMENT IN BOLIVER 0 0005 PREPARED BY: JEFFERY D. THOMSON 0 0055 TEMPORARY REVETMENT IN BOLIVER NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0512 PORT CTB (DES SOURCE)(SAFETY SH)(TY 2) LF 48,025.000 63,720.000 10.700 681,804.00 0060 0512 ADJ EST QUANTITY TO DATE 63,775.000 0065 9000*DEMOBILIZATION AND REMOBILIZATION LS 1.000 1.000 11,431.490 11,431.49 0070 9000*BACKFILL WASHED OUT CTB LS 1.000 1.000 5,715.850 5,715.85 0 SUBTOTAL BID ITEMS $ 698,951.34 0 TOTAL AMOUNT WORK DONE TEMPORARY REVETMENT IN BOLIVER $ 698,951.34 0 TOTAL AMOUNT WORK DONE CONTROL 6192-34-001 $ 698,951.34 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5091241 MGR.NO. 060 PAGE 001 CONT 6192 SEC 34 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ EMC - 619234001 HWY SH0087 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 513,867.50 REPORT DATE 11/08/2013 16.16.42 CONTRACTOR J.D. ABRAMS, L.P. 9821 EST PERIOD JUN 08,2009 TO NOV 19,2009 EST NO 008 & FINAL 0*********************************************************************************************************************************** -LIMITS - SH 124 TO APPROXIMATELY 0 4.7 MILES SOUTHWEST ALONG SH87 DATE WORK BEGAN JUN 8 , 2009 WORKING DAYS USED 54 PERCENT COMPLETE 100.00 PERCENT TIME USED 83.00 DATE COMPLETED NOV 19 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6192-34-001 EMC - 619234001 12 SH0087 GALVESTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0512 PORT CTB (DES SOURCE)(SAFETY SH)(TY 2) LF 48,025.000 63,720.000 10.700 681,804.00 0512* ADJ EST QUANTITY TO DATE 63,775.000 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09000* DEMOBILIZATION AND REMOBILIZATION LS 1.000 1.000 11,431.490 11,431.49 9000* BACKFILL WASHED OUT CTB LS 1.000 1.000 5,715.850 5,715.85 0 SUBTOTAL BID ITEMS $ 698,951.34 0 CONTRACT TOTAL ALL ITEMS $ 698,951.34 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5091241 MGR.NO. 060 PAGE 001 CONT 6192 SEC 34 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ EMC - 619234001 HWY SH0087 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 513,867.50 REPORT DATE 11/08/2013 16.16.42 CONTRACTOR J.D. ABRAMS, L.P. 9821 EST PERIOD JUN 08,2009 TO NOV 19,2009 EST NO 008 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85 EMC - 619234001 6192-34-001 698,951.34 .00 698,951.34 .00 .00 698,951.34 698,951.34 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 698,951.34 .00 698,951.34 .00 .00 698,951.34 698,951.34 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5091241 MGR.NO. 060 PAGE 001 CONT 6192 SEC 34 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ EMC - 619234001 HWY SH0087 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 513,867.50 REPORT DATE 11/08/2013 16.16.42 CONTRACTOR J.D. ABRAMS, L.P. 9821 EST PERIOD JUN 08,2009 TO NOV 19,2009 EST NO 008 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6192-34-001 EMC - 619234001 12 SH0087 GALVESTON -LIMITS - SH 124 TO APPROXIMATELY 4.7 MILES SOUTHWEST ALONG SH87 - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 698,951.34