1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2111204 MGR.NO. 053 PAGE 001 CONT 6219 SEC 94 JOB 001 RES ENGR BROWN, RICHARD PROJ RMC - 621994001 HWY US0059 901 N. FM 3083 EAST CONRO CNTY MONTGOMERY DIST 12 CONTRACT PRICE $ 289,200.00 REPORT DATE 08/14/2014 10.13.20 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD MAY 16,2011 TO APR 30,2012 EST NO 013 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 16, 2011 TIME COMPUTED FROM MAY 16, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 321 321 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 12 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 04/30/12 3 1 DAYS CHARGED TO DATE = 351 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 351 351 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2111204 MGR.NO. 053 PAGE 001 CONT 6219 SEC 94 JOB 001 RES ENGR BROWN, RICHARD PROJ RMC - 621994001 HWY US0059 901 N. FM 3083 EAST CONRO CNTY MONTGOMERY DIST 12 CONTRACT PRICE $ 289,200.00 REPORT DATE 08/14/2014 10.13.20 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD MAY 16,2011 TO APR 30,2012 EST NO 013 & FINAL DIST. 12 COUNTY MONTGOMERY CONTROL 6219-94-001 PROJECT RMC - 621994001 HIGHWAY US0059 0LIMITS- VARIOUS HWYS IN MONTGOMERY COUNTY VARIOUS HWYS IN MONTGOMERY COUNTY 0TYPE OF WORK- CONCRETE STRUCTURE & SPALL REPAIR 0 0050 CONCRETE STRUCTURE & SPALL REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY ANDY D. VARILLA 0 0075 0104 REMOVING CONC (MISC) SY 100.000 0.000 60.000 .00 0080 0361 FULL-DEPTH REPAIR CRCP (8"-14") SY 600.000 188.219 245.000 46,113.66 0080 0361 ADJ EST QUANTITY TO DATE 189.000 0085 0429 CNC STR REP (HORIZONTAL) SF 1,400.000 0.000 37.000 .00 0085 0429 ADJ EST QUANTITY TO DATE 60.000 0090 0429 CNC STR REP (REMOVE & REPLACE) CY 500.000 0.000 78.000 .00 0090 0429 ADJ EST QUANTITY TO DATE 0.000 0095 0438 CLEAN AND SEAL EXIST JOINTS LF 800.000 0.000 15.000 .00 0095 0438 ADJ EST QUANTITY TO DATE 0.000 0100 0454 SEALED EXPANSION JOINT (4 IN)(SEJ-A) LF 60.000 0.000 250.000 .00 0100 0454 ADJ EST QUANTITY TO DATE 0.000 0105 0465 INLET (STAGE II)(TY C) EA 1.000 5.000 3,000.000 15,000.00 0105 0465 ADJ EST QUANTITY TO DATE 3.000 0110 0529 CONC CURB & GUTTER (TY II) LF 1,400.000 115.000 11.000 1,265.00 0150 0361*FULL-DEPTH REPAIR CRCP (15") SY 928.000 922.830 252.180 232,719.27 0155 4491*TYPE CAC CONCRETE CY 2.000 2.000 2,053.070 4,106.14 0 SUBTOTAL BID ITEMS $ 299,204.07 0 TOTAL AMOUNT WORK DONE CONCRETE STRUCTURE & SPALL REPAIR $ 299,204.07 0 0160 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) 1 0161 POLICE OFFICER FOR TRAFFIC CONTROL 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6219-94-001 $ 299,204.07 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2111204 MGR.NO. 053 PAGE 001 CONT 6219 SEC 94 JOB 001 RES ENGR BROWN, RICHARD PROJ RMC - 621994001 HWY US0059 901 N. FM 3083 EAST CONRO CNTY MONTGOMERY DIST 12 CONTRACT PRICE $ 289,200.00 REPORT DATE 08/14/2014 10.13.20 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD MAY 16,2011 TO APR 30,2012 EST NO 013 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN MONTGOMERY COUNTY 0 VARIOUS HWYS IN MONTGOMERY COUNTY DATE WORK BEGAN MAY 16, 2011 WORKING DAYS USED 351 PERCENT COMPLETE 100.00 PERCENT TIME USED 96.10 DATE COMPLETED APR 30 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6219-94-001 RMC - 621994001 12 US0059 MONTGOMERY - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0361 FULL-DEPTH REPAIR CRCP (8"-14") SY 600.000 188.219 245.000 46,113.66 0361 ADJ EST QUANTITY TO DATE 189.000 0465 INLET (STAGE II)(TY C) EA 1.000 5.000 3,000.000 15,000.00 0465 ADJ EST QUANTITY TO DATE 3.000 0529 CONC CURB & GUTTER (TY II) LF 1,400.000 115.000 11.000 1,265.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00361* FULL-DEPTH REPAIR CRCP (15") SY 928.000 922.830 252.180 232,719.27 4491* TYPE CAC CONCRETE CY 2.000 2.000 2,053.070 4,106.14 0 SUBTOTAL BID ITEMS $ 299,204.07 0 CONTRACT TOTAL ALL ITEMS $ 299,204.07 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2111204 MGR.NO. 053 PAGE 001 CONT 6219 SEC 94 JOB 001 RES ENGR BROWN, RICHARD PROJ RMC - 621994001 HWY US0059 901 N. FM 3083 EAST CONRO CNTY MONTGOMERY DIST 12 CONTRACT PRICE $ 289,200.00 REPORT DATE 08/14/2014 10.13.20 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD MAY 16,2011 TO APR 30,2012 EST NO 013 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 170 RMC - 621994001 6219-94-001 299,204.07 .00 299,204.07 .00 .00 299,204.07 299,204.07 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 299,204.07 .00 299,204.07 .00 .00 299,204.07 299,204.07 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2111204 MGR.NO. 053 PAGE 001 CONT 6219 SEC 94 JOB 001 RES ENGR BROWN, RICHARD PROJ RMC - 621994001 HWY US0059 901 N. FM 3083 EAST CONRO CNTY MONTGOMERY DIST 12 CONTRACT PRICE $ 289,200.00 REPORT DATE 08/14/2014 10.13.20 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD MAY 16,2011 TO APR 30,2012 EST NO 013 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6219-94-001 RMC - 621994001 12 US0059 MONTGOMERY -LIMITS - VARIOUS HWYS IN MONTGOMERY COUNTY VARIOUS HWYS IN MONTGOMERY COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 299,204.07