1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3114005 MGR.NO. 064 PAGE 001 CONT 6220 SEC 67 JOB 001 RES ENGR VOLK, JEFFREY PROJ RMC - 622067001 HWY IH0010 702 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 339,173.88 REPORT DATE 08/14/2014 09.28.27 CONTRACTOR BIO LANDSCAPE & MAINTENANCE, EST PERIOD JUL 01,2011 TO DEC 31,2013 EST NO 032 & FINAL INC. 10109 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 01, 2011 TIME COMPUTED FROM JUL 01, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 198 884 131 753 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 13 1 1 SUNDAY TOTAL DAYS ALLOWED = 198 2 1 DATE WORK COMPLETED 12/31/13 3 1 DAYS CHARGED TO DATE = 141 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 TOO WET 7 1 SATURDAY LIQUIDATED DAMAGES 8 1 SUNDAY 0 DAYS AT $ 500 PER DAY 9 1 TOO WET TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 RAIN TO THE CONTRACTOR 14 1 SATURDAY 15 1 SUNDAY 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 WORK COMPLETED 20 1 WORK COMPLETED 21 1 WORK COMPLETED 22 1 WORK COMPLETED 23 1 WORK COMPLETED 24 1 WORK COMPLETED 25 1 WORK COMPLETED 26 1 WORK COMPLETED 27 1 WORK COMPLETED 28 1 WORK COMPLETED 29 1 WORK COMPLETED 30 1 WORK COMPLETED 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 915 141 774 2 SATURDAY 3 SUNDAY 0 HOLIDAY 2 TOO WET 1 RAIN 12 WORK COMPLETED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3114005 MGR.NO. 064 PAGE 001 CONT 6220 SEC 67 JOB 001 RES ENGR VOLK, JEFFREY PROJ RMC - 622067001 HWY IH0010 702 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 339,173.88 REPORT DATE 08/14/2014 09.28.27 CONTRACTOR BIO LANDSCAPE & MAINTENANCE, EST PERIOD JUL 01,2011 TO DEC 31,2013 EST NO 032 & FINAL INC. 10109 DIST. 12 COUNTY HARRIS CONTROL 6220-67-001 PROJECT RMC - 622067001 HIGHWAY IH0010 0LIMITS- VARIOUS HWYS IN EAST HARRIS COUNTY VARIOUS HWYS IN EAST HARRIS COUNTY 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0050 MOWING HWY RIGHT OF WAY NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY RHONDA K. LANGE 0 0075 0730 FULL-WIDTH MOWING AC 14,846.000 14,271.000 21.780 310,822.38 0075 0730 ADJ EST QUANTITY TO DATE 14,271.000 0080 0730 SPOT MOWING AC 100.000 0.000 21.780 .00 0085 0752 TREE TRIMMING/BRUSH REMOVAL(CHANNELS) AC 78.000 104.000 175.000 18,200.00 0 SUBTOTAL BID ITEMS $ 329,022.38 0 TOTAL AMOUNT WORK DONE MOWING HWY RIGHT OF WAY $ 329,022.38 0 TOTAL AMOUNT WORK DONE CONTROL 6220-67-001 $ 329,022.38 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3114005 MGR.NO. 064 PAGE 001 CONT 6220 SEC 67 JOB 001 RES ENGR VOLK, JEFFREY PROJ RMC - 622067001 HWY IH0010 702 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 339,173.88 REPORT DATE 08/14/2014 09.28.27 CONTRACTOR BIO LANDSCAPE & MAINTENANCE, EST PERIOD JUL 01,2011 TO DEC 31,2013 EST NO 032 & FINAL INC. 10109 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN EAST HARRIS COUNTY 0 VARIOUS HWYS IN EAST HARRIS COUNTY DATE WORK BEGAN JUL 1 , 2011 WORKING DAYS USED 141 PERCENT COMPLETE 100.00 PERCENT TIME USED 71.20 DATE COMPLETED DEC 31 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6220-67-001 RMC - 622067001 12 IH0010 HARRIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 14,846.000 14,271.000 21.780 310,822.38 0730 ADJ EST QUANTITY TO DATE 14,271.000 0752 TREE TRIMMING/BRUSH REMOVAL(CHANNELS) AC 78.000 104.000 175.000 18,200.00 0 SUBTOTAL BID ITEMS $ 329,022.38 0 CONTRACT TOTAL ALL ITEMS $ 329,022.38 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3114005 MGR.NO. 064 PAGE 001 CONT 6220 SEC 67 JOB 001 RES ENGR VOLK, JEFFREY PROJ RMC - 622067001 HWY IH0010 702 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 339,173.88 REPORT DATE 08/14/2014 09.28.27 CONTRACTOR BIO LANDSCAPE & MAINTENANCE, EST PERIOD JUL 01,2011 TO DEC 31,2013 EST NO 032 & FINAL INC. 10109 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102 RMC - 622067001 6220-67-001 329,022.38 .00 329,022.38 .00 .00 329,022.38 329,022.38 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 329,022.38 .00 329,022.38 .00 .00 329,022.38 329,022.38 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3114005 MGR.NO. 064 PAGE 001 CONT 6220 SEC 67 JOB 001 RES ENGR VOLK, JEFFREY PROJ RMC - 622067001 HWY IH0010 702 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 339,173.88 REPORT DATE 08/14/2014 09.28.27 CONTRACTOR BIO LANDSCAPE & MAINTENANCE, EST PERIOD JUL 01,2011 TO DEC 31,2013 EST NO 032 & FINAL INC. 10109 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6220-67-001 RMC - 622067001 12 IH0010 HARRIS -LIMITS - VARIOUS HWYS IN EAST HARRIS COUNTY VARIOUS HWYS IN EAST HARRIS COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 329,022.38