1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2121101 MGR.NO. 055 PAGE 001 CONT 6238 SEC 33 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 623833001 HWY US0096 1805 N TIMBERLAND DR LUFK CNTY SAN AUGUSTINE DIST 11 CONTRACT PRICE $ 160,590.00 REPORT DATE 12/18/2013 11.21.34 CONTRACTOR 4C CONSTRUCTION 15478 EST PERIOD APR 23,2012 TO APR 30,2013 EST NO 014 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 01, 2012 TIME COMPUTED FROM APR 23, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 175 343 174 169 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 TIME SUSPENDED TOTAL DAYS ALLOWED = 175 2 1 TIME SUSPENDED DATE WORK COMPLETED 04/30/13 3 1 TIME SUSPENDED DAYS CHARGED TO DATE = 174 4 1 TIME SUSPENDED ASSESSED LIQ DAMAGES = 0 5 1 TIME SUSPENDED LIQ DAMAGE RATE $ 590 6 1 TIME SUSPENDED 7 1 TIME SUSPENDED LIQUIDATED DAMAGES 8 1 TIME SUSPENDED 0 DAYS AT $ 590 PER DAY 9 1 TIME SUSPENDED TOTAL = $ .00 10 1 TIME SUSPENDED 11 1 TIME SUSPENDED CERTIFIED AS CORRECT AND 12 1 TIME SUSPENDED ONE COPY HAS BEEN GIVEN 13 1 TIME SUSPENDED TO THE CONTRACTOR 14 1 TIME SUSPENDED 15 1 TIME SUSPENDED 16 1 TIME SUSPENDED ---------------------------- 17 1 TIME SUSPENDED AREA/PROJECT ENGINEER 18 1 TIME SUSPENDED 19 1 TIME SUSPENDED 20 1 TIME SUSPENDED 21 1 TIME SUSPENDED 22 1 TIME SUSPENDED 23 1 TIME SUSPENDED 24 1 TIME SUSPENDED 25 1 TIME SUSPENDED 26 1 TIME SUSPENDED 27 1 TIME SUSPENDED 28 1 TIME SUSPENDED 29 1 TIME SUSPENDED 30 1 WORK COMPLETED AND ACCEPTED 0 ----- ----- ----- 373 174 199 0 SATURDAY 0 SUNDAY 0 HOLIDAY 29 TIME SUSPENDED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2121101 MGR.NO. 055 PAGE 001 CONT 6238 SEC 33 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 623833001 HWY US0096 1805 N TIMBERLAND DR LUFK CNTY SAN AUGUSTINE DIST 11 CONTRACT PRICE $ 160,590.00 REPORT DATE 12/18/2013 11.21.35 CONTRACTOR 4C CONSTRUCTION 15478 EST PERIOD APR 23,2012 TO APR 30,2013 EST NO 014 & FINAL DIST. 11 COUNTY SAN AUGUSTINE CONTROL 6238-33-001 PROJECT RMC - 623833001 HIGHWAY US0096 0LIMITS- US 96 & VARIOUS LOCATIONS WITHIN SAN AUGUSTINE MAINT SECTION 0TYPE OF WORK- REMOVAL/DISPOSAL OF TREES AND LIMBS 0 0005 PREPARED BY C. MICHAEL LEE, P.E., 12/07/11 0 0055 ROADWAY NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0752 TREE REMOVAL (4"-12" DIA) EA 2,040.000 3,240.000 29.000 93,960.00 0065 0752 TREE REMOVAL (12"-18" DIA) EA 720.000 1,413.000 32.000 45,216.00 0070 0752 TREE REMOVAL (18"-24" DIA) EA 540.000 441.000 38.000 16,758.00 0075 0752 TREE REMOVAL (24"-30" DIA) EA 360.000 128.000 33.000 4,224.00 0080 0752 TREE REMOVAL (30"-36" DIA) EA 240.000 19.000 28.000 532.00 0085 0752 TREE REMOVAL (36"-42" DIA) EA 120.000 5.000 105.000 525.00 0090 0752 TREE REMOVAL (42"-48" DIA) EA 60.000 1.000 125.000 125.00 0095 0752 TREE REMOVAL (48"-60" DIA) EA 45.000 3.000 175.000 525.00 0100 0752 TREE REMOVAL (60"-72" DIA) EA 45.000 0.000 251.000 .00 0 SUBTOTAL BID ITEMS $ 161,865.00 0 TOTAL AMOUNT WORK DONE ROADWAY $ 161,865.00 0 TOTAL AMOUNT WORK DONE CONTROL 6238-33-001 $ 161,865.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2121101 MGR.NO. 055 PAGE 001 CONT 6238 SEC 33 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 623833001 HWY US0096 1805 N TIMBERLAND DR LUFK CNTY SAN AUGUSTINE DIST 11 CONTRACT PRICE $ 160,590.00 REPORT DATE 12/18/2013 11.21.35 CONTRACTOR 4C CONSTRUCTION 15478 EST PERIOD APR 23,2012 TO APR 30,2013 EST NO 014 & FINAL 0*********************************************************************************************************************************** -LIMITS - US 96 & VARIOUS LOCATIONS WITHIN 0 SAN AUGUSTINE MAINT SECTION DATE WORK BEGAN MAY 1 , 2012 WORKING DAYS USED 174 PERCENT COMPLETE 100.00 PERCENT TIME USED 99.40 DATE COMPLETED APR 30 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6238-33-001 RMC - 623833001 11 US0096 SAN AUGUSTINE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0752 TREE REMOVAL (4"-12" DIA) EA 2,040.000 3,240.000 29.000 93,960.00 0752 TREE REMOVAL (12"-18" DIA) EA 720.000 1,413.000 32.000 45,216.00 0752 TREE REMOVAL (18"-24" DIA) EA 540.000 441.000 38.000 16,758.00 0752 TREE REMOVAL (24"-30" DIA) EA 360.000 128.000 33.000 4,224.00 0752 TREE REMOVAL (30"-36" DIA) EA 240.000 19.000 28.000 532.00 0752 TREE REMOVAL (36"-42" DIA) EA 120.000 5.000 105.000 525.00 0752 TREE REMOVAL (42"-48" DIA) EA 60.000 1.000 125.000 125.00 0752 TREE REMOVAL (48"-60" DIA) EA 45.000 3.000 175.000 525.00 0 SUBTOTAL BID ITEMS $ 161,865.00 0 CONTRACT TOTAL ALL ITEMS $ 161,865.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2121101 MGR.NO. 055 PAGE 001 CONT 6238 SEC 33 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 623833001 HWY US0096 1805 N TIMBERLAND DR LUFK CNTY SAN AUGUSTINE DIST 11 CONTRACT PRICE $ 160,590.00 REPORT DATE 12/18/2013 11.21.35 CONTRACTOR 4C CONSTRUCTION 15478 EST PERIOD APR 23,2012 TO APR 30,2013 EST NO 014 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 203 RMC - 623833001 6238-33-001 161,865.00 .00 161,865.00 .00 .00 161,865.00 161,865.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 161,865.00 .00 161,865.00 .00 .00 161,865.00 161,865.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2121101 MGR.NO. 055 PAGE 001 CONT 6238 SEC 33 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 623833001 HWY US0096 1805 N TIMBERLAND DR LUFK CNTY SAN AUGUSTINE DIST 11 CONTRACT PRICE $ 160,590.00 REPORT DATE 12/18/2013 11.21.35 CONTRACTOR 4C CONSTRUCTION 15478 EST PERIOD APR 23,2012 TO APR 30,2013 EST NO 014 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6238-33-001 RMC - 623833001 11 US0096 SAN AUGUSTINE -LIMITS - US 96 & VARIOUS LOCATIONS WITHIN SAN AUGUSTINE MAINT SECTION - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 161,865.00