1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5131127 MGR.NO. 055 PAGE 001 CONT 6256 SEC 02 JOB 001 RES ENGR LEE, MICHAEL PROJ RMC - 625602001 HWY FM0001 918 INDUSTRIAL BLVD NACOG CNTY SABINE DIST 11 CONTRACT PRICE $ 224,406.75 REPORT DATE 06/02/2014 08.51.19 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD JUL 08,2013 TO MAY 31,2014 EST NO 012 & FINAL SERVICES, INC. 11075 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 08, 2013 TIME COMPUTED FROM JUL 08, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 85 297 42 255 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAY 14 1 1 TIME SUSPENDED TOTAL DAYS ALLOWED = 85 2 1 TIME SUSPENDED DATE WORK COMPLETED 05/31/14 3 1 TIME SUSPENDED DAYS CHARGED TO DATE = 42 4 1 TIME SUSPENDED ASSESSED LIQ DAMAGES = 0 5 1 TIME SUSPENDED LIQ DAMAGE RATE $ 0 6 1 TIME SUSPENDED 7 1 TIME SUSPENDED LIQUIDATED DAMAGES 8 1 TIME SUSPENDED 0 DAYS AT $ 0 PER DAY 9 1 TIME SUSPENDED TOTAL = $ .00 10 1 TIME SUSPENDED 11 1 TIME SUSPENDED CERTIFIED AS CORRECT AND 12 1 TIME SUSPENDED ONE COPY HAS BEEN GIVEN 13 1 TIME SUSPENDED TO THE CONTRACTOR 14 1 TIME SUSPENDED 15 1 TIME SUSPENDED 16 1 TIME SUSPENDED ---------------------------- 17 1 TIME SUSPENDED AREA/PROJECT ENGINEER 18 1 TIME SUSPENDED 19 1 TIME SUSPENDED 20 1 TIME SUSPENDED 21 1 TIME SUSPENDED 22 1 TIME SUSPENDED 23 1 TIME SUSPENDED 24 1 TIME SUSPENDED 25 1 TIME SUSPENDED 26 1 TIME SUSPENDED 27 1 TIME SUSPENDED 28 1 TIME SUSPENDED 29 1 TIME SUSPENDED 30 1 TIME SUSPENDED 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 328 42 286 0 SATURDAY 0 SUNDAY 0 HOLIDAY 30 TIME SUSPENDED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5131127 MGR.NO. 055 PAGE 001 CONT 6256 SEC 02 JOB 001 RES ENGR LEE, MICHAEL PROJ RMC - 625602001 HWY FM0001 918 INDUSTRIAL BLVD NACOG CNTY SABINE DIST 11 CONTRACT PRICE $ 224,406.75 REPORT DATE 06/02/2014 08.51.20 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD JUL 08,2013 TO MAY 31,2014 EST NO 012 & FINAL SERVICES, INC. 11075 DIST. 11 COUNTY SABINE CONTROL 6256-02-001 PROJECT RMC - 625602001 HIGHWAY FM0001 0LIMITS- VARIOUS LOCATIONS IN THE SHELBY AND SABINE MAINTENANCE SECTIONS 0TYPE OF WORK- CULVERT REPLACEMENT 0 0050 ROADWAY NET LENGTH 0.100 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY C. MICHAEL LEE, P.E. 2/12/13 0 0075 0132 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 928.000 822.000 17.000 13,974.00 0080 0158 SPEC EXCAV WORK (HYD EXCAVATOR) HR 18.000 26.000 50.000 1,300.00 0085 0164 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 2,480.000 2,765.000 .500 1,382.50 0090 0164 BROADCAST SEED (TEMP) (WARM) SY 1,240.000 1,240.000 .500 620.00 0095 0168 VEGETATIVE WATERING MG 15.000 3.750 10.000 37.50 0100 0169 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 300.000 75.000 3.000 225.00 0105 0400 CEM STABIL BKFL CY 27.000 46.000 125.000 5,750.00 0110 0400 CUT & RESTORING PAV SY 10.500 10.500 92.000 966.00 0115 0402 TRENCH EXCAVATION PROTECTION LF 38.000 38.000 8.000 304.00 0120 0403 TEMPORARY SPL SHORING SF 1,300.000 2,235.000 25.000 55,875.00 0125 0420 CL C CONC (COLLAR) EA 3.000 3.000 600.000 1,800.00 0130 0430 CL C CONC FOR EXT STRU (CULV)(6'X 5') LF 31.000 31.000 466.000 14,446.00 0135 0430 CL C CONC FOR EXT STRU (CULV)(7'X 7') LF 8.000 8.000 922.000 7,376.00 0140 0464 RC PIPE (CL III)(24 IN) LF 62.000 62.000 94.000 5,828.00 0145 0466 HEADWALL (CH-PW-0)(DIA= 60 IN) EA 1.000 1.000 9,275.000 9,275.00 0150 0466 WINGWALL (PW-2)(HW=7 FT) EA 2.000 2.000 13,050.000 26,100.00 0155 0466 WINGWALL (PW-2)(HW=11 FT) EA 2.000 2.000 33,000.000 66,000.00 0160 0467 SET (TY II)(24 IN)(RCP)(3:1)(C) EA 1.000 3.000 665.000 1,995.00 0165 0467 SET (TY II)(36 IN)(RCP)(4:1)(C) EA 2.000 0.000 1,950.000 .00 0170 0496 REMOV STR (PIPE) LF 48.500 48.500 9.500 460.75 1 0175 0500 MOBILIZATION LS 1.000 1.000 22,000.000 22,000.00 0180 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 4.000 1,500.000 6,000.00 0185 0658 INSTL OM ASSM (OM-2Z)(FLX)GND EA 2.000 2.000 50.000 100.00 0190 1122 BACKHOE WORK (EROSION & SEDM CONT) HR 25.000 16.250 50.000 812.50 0195 1122 TEMPORARY SEDIMENT CONTROL FENCE INSTLL LF 550.000 137.500 3.000 412.50 0200 1122 TEMPORARY SEDIMENT CONTROL FENCE REMOVE LF 550.000 137.500 1.500 206.25 0210 0401*FLOWABLE BACKFILL CY 15.000 19.000 133.560 2,537.64 0220 0430*CL C CONC FOR EXT STR (CULV)(2-7'X7') LF 12.000 12.000 1,358.050 16,296.60 0230 0432*RIPRAP (STONE COMMON)(DRY)(18 IN) CY 82.000 82.000 130.150 10,672.30 0240 0466*WINGWALL (PW-2)(HW=8 FT) EA 2.000 2.000 16,304.220 32,608.44 0 SUBTOTAL BID ITEMS $ 305,360.98 0 TOTAL AMOUNT WORK DONE ROADWAY $ 305,360.98 0 TOTAL AMOUNT WORK DONE CONTROL 6256-02-001 $ 305,360.98 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5131127 MGR.NO. 055 PAGE 001 CONT 6256 SEC 02 JOB 001 RES ENGR LEE, MICHAEL PROJ RMC - 625602001 HWY FM0001 918 INDUSTRIAL BLVD NACOG CNTY SABINE DIST 11 CONTRACT PRICE $ 224,406.75 REPORT DATE 06/02/2014 08.51.20 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD JUL 08,2013 TO MAY 31,2014 EST NO 012 & FINAL SERVICES, INC. 11075 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN THE SHELBY AND 0 SABINE MAINTENANCE SECTIONS DATE WORK BEGAN JUL 8 , 2013 WORKING DAYS USED 42 PERCENT COMPLETE 100.00 PERCENT TIME USED 49.40 DATE COMPLETED MAY 31 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6256-02-001 RMC - 625602001 11 FM0001 SABINE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0132 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 928.000 822.000 17.000 13,974.00 0158 SPEC EXCAV WORK (HYD EXCAVATOR) HR 18.000 26.000 50.000 1,300.00 0164 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 2,480.000 2,765.000 .500 1,382.50 0164 BROADCAST SEED (TEMP) (WARM) SY 1,240.000 1,240.000 .500 620.00 0168 VEGETATIVE WATERING MG 15.000 3.750 10.000 37.50 0169 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 300.000 75.000 3.000 225.00 0400 CEM STABIL BKFL CY 27.000 46.000 125.000 5,750.00 0400 CUT & RESTORING PAV SY 10.500 10.500 92.000 966.00 0402 TRENCH EXCAVATION PROTECTION LF 38.000 38.000 8.000 304.00 0403 TEMPORARY SPL SHORING SF 1,300.000 2,235.000 25.000 55,875.00 0420 CL C CONC (COLLAR) EA 3.000 3.000 600.000 1,800.00 0430 CL C CONC FOR EXT STRU (CULV)(6'X 5') LF 31.000 31.000 466.000 14,446.00 0430 CL C CONC FOR EXT STRU (CULV)(7'X 7') LF 8.000 8.000 922.000 7,376.00 0464 RC PIPE (CL III)(24 IN) LF 62.000 62.000 94.000 5,828.00 0466 HEADWALL (CH-PW-0)(DIA= 60 IN) EA 1.000 1.000 9,275.000 9,275.00 0466 WINGWALL (PW-2)(HW=7 FT) EA 2.000 2.000 13,050.000 26,100.00 0466 WINGWALL (PW-2)(HW=11 FT) EA 2.000 2.000 33,000.000 66,000.00 0467 SET (TY II)(24 1 IN)(RCP)(3:1)(C) EA 1.000 3.000 665.000 1,995.00 0496 REMOV STR (PIPE) LF 48.500 48.500 9.500 460.75 0500 MOBILIZATION LS 1.000 1.000 22,000.000 22,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 4.000 1,500.000 6,000.00 0658 INSTL OM ASSM (OM-2Z)(FLX)GND EA 2.000 2.000 50.000 100.00 1122 BACKHOE WORK (EROSION & SEDM CONT) HR 25.000 16.250 50.000 812.50 1122 TEMPORARY SEDIMENT CONTROL FENCE INSTLL LF 550.000 137.500 3.000 412.50 1122 TEMPORARY SEDIMENT CONTROL FENCE REMOVE LF 550.000 137.500 1.500 206.25 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00401* FLOWABLE BACKFILL CY 15.000 19.000 133.560 2,537.64 0430* CL C CONC FOR EXT STR (CULV)(2-7'X7') LF 12.000 12.000 1,358.050 16,296.60 0432* RIPRAP (STONE COMMON)(DRY)(18 IN) CY 82.000 82.000 130.150 10,672.30 0466* WINGWALL (PW-2)(HW=8 FT) EA 2.000 2.000 16,304.220 32,608.44 0 SUBTOTAL BID ITEMS $ 305,360.98 0 CONTRACT TOTAL ALL ITEMS $ 305,360.98 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5131127 MGR.NO. 055 PAGE 001 CONT 6256 SEC 02 JOB 001 RES ENGR LEE, MICHAEL PROJ RMC - 625602001 HWY FM0001 918 INDUSTRIAL BLVD NACOG CNTY SABINE DIST 11 CONTRACT PRICE $ 224,406.75 REPORT DATE 06/02/2014 08.51.20 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD JUL 08,2013 TO MAY 31,2014 EST NO 012 & FINAL SERVICES, INC. 11075 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 202 RMC - 625602001 6256-02-001 305,360.98 .00 305,360.98 .00 .00 305,360.98 305,360.98 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 305,360.98 .00 305,360.98 .00 .00 305,360.98 305,360.98 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5131127 MGR.NO. 055 PAGE 001 CONT 6256 SEC 02 JOB 001 RES ENGR LEE, MICHAEL PROJ RMC - 625602001 HWY FM0001 918 INDUSTRIAL BLVD NACOG CNTY SABINE DIST 11 CONTRACT PRICE $ 224,406.75 REPORT DATE 06/02/2014 08.51.21 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD JUL 08,2013 TO MAY 31,2014 EST NO 012 & FINAL SERVICES, INC. 11075 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6256-02-001 RMC - 625602001 11 FM0001 SABINE -LIMITS - VARIOUS LOCATIONS IN THE SHELBY AND SABINE MAINTENANCE SECTIONS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 305,360.98