1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6102207 MGR.NO. 005 PAGE 001 CONT 6210 SEC 65 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 621065001 HWY LP0020 1817 BOB BULLOCK LAREDO CNTY WEBB DIST 22 CONTRACT PRICE $ 317,751.67 REPORT DATE 09/13/2012 07.44.19 CONTRACTOR GILMAR CONSTRUCTION, LTD. 10900 EST PERIOD AUG 09,2010 TO APR 24,2012 EST NO 021 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 09, 2010 TIME COMPUTED FROM AUG 09, 2010 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 601 591 10 BROUGHT FORWARD ADDL DAYS GRANTED = 226 APR 12 1 1 WORK COMPLETED TOTAL DAYS ALLOWED = 591 2 1 WORK COMPLETED DATE WORK COMPLETED 04/24/12 3 1 WORK COMPLETED DAYS CHARGED TO DATE = 591 4 1 WORK COMPLETED ASSESSED LIQ DAMAGES = 0 5 1 WORK COMPLETED LIQ DAMAGE RATE $ 500 6 1 WORK COMPLETED 7 1 WORK COMPLETED LIQUIDATED DAMAGES 8 1 WORK COMPLETED 0 DAYS AT $ 500 PER DAY 9 1 WORK COMPLETED TOTAL = $ .00 10 1 WORK COMPLETED 11 1 WORK COMPLETED CERTIFIED AS CORRECT AND 12 1 WORK COMPLETED ONE COPY HAS BEEN GIVEN 13 1 WORK COMPLETED TO THE CONTRACTOR 14 1 WORK COMPLETED 15 1 WORK COMPLETED 16 1 WORK COMPLETED ---------------------------- 17 1 WORK COMPLETED AREA/PROJECT ENGINEER 18 1 WORK COMPLETED 19 1 WORK COMPLETED 20 1 WORK COMPLETED 21 1 WORK COMPLETED 22 1 WORK COMPLETED 23 1 WORK COMPLETED 24 1 WORK COMPLETED AND ACCEPTED - - 0 ----- ----- ----- 625 591 34 0 SATURDAY 0 SUNDAY 0 HOLIDAY 23 WORK COMPLETED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6102207 MGR.NO. 005 PAGE 001 CONT 6210 SEC 65 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 621065001 HWY LP0020 1817 BOB BULLOCK LAREDO CNTY WEBB DIST 22 CONTRACT PRICE $ 317,751.67 REPORT DATE 09/13/2012 07.44.21 CONTRACTOR GILMAR CONSTRUCTION, LTD. 10900 EST PERIOD AUG 09,2010 TO APR 24,2012 EST NO 021 & FINAL DIST. 22 COUNTY WEBB CONTROL 6210-65-001 PROJECT RMC - 621065001 HIGHWAY LP0020 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- INSTALL RAISED MEDIAN, SIGNING & STRIPIN 0 0050 RAISED MEDIAN, SIGNING & STRIPING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY NPM 4-29-10 0 0075 0104 REMOVING CONC (PAV) SY 60.000 14.660 73.750 1,081.18 0075 0104 ADJ EST QUANTITY TO DATE 14.660 0080 0104 REMOVING CONC (MEDIANS) SY 51.000 267.650 31.500 8,430.98 0080 0104 ADJ EST QUANTITY TO DATE 267.650 0085 0104 REMOVING CONC (CURB) LF 159.000 1,278.000 3.500 4,473.00 0085 0104 ADJ EST QUANTITY TO DATE 1,278.000 0090 0104 REMOVING CONC (CURB AND GUTTER) LF 1,893.000 639.000 9.150 5,846.85 0090 0104 ADJ EST QUANTITY TO DATE 639.000 0095 0104 REMOVING CONC (WHEELCHAIR RAMP) SY 27.000 61.440 15.750 967.68 0095 0104 ADJ EST QUANTITY TO DATE 61.440 0100 0104 REMOVING CONC (PAVERS) SY 400.000 668.770 8.950 5,985.49 0100 0104 ADJ EST QUANTITY TO DATE 668.770 0105 0105 REMOVING STAB BASE & ASPH PAV(14") SY 800.000 225.140 21.000 4,727.94 0105 0105 ADJ EST QUANTITY TO DATE 225.140 0110 0340 D-GR HMA(METH) TY-B PG70-22 TON 525.000 69.840 106.000 7,403.04 0110 0340 ADJ EST QUANTITY TO DATE 69.840 0115 0340 D-GR HMA(METH) TY-C PG70-22 TON 179.000 125.910 131.000 16,494.21 0115 0340 ADJ EST QUANTITY TO DATE 125.910 0120 0360 CONC PVMT (CONT REINF-CRCP)(12") SY 60.000 66.670 95.000 6,333.65 0120 0360 ADJ EST QUANTITY TO DATE 66.670 0140 0464 RC PIPE (CL III)(24 IN) LF 100.000 24.000 46.000 1,104.00 0140 0464 ADJ EST QUANTITY TO DATE 24.000 0145 0465 INLET (COMPL)(TY C) EA 1.000 1.000 3,500.000 3,500.00 0150 0465 MANH (COMPL)(JCT BOX)(TY C) EA 1.000 0.000 3,900.000 .00 1 0150 0465 ADJ EST QUANTITY TO DATE 0.000 0155 0479 ADJ MANHS EA 1.000 0.000 1,000.000 .00 0155 0479 ADJ EST QUANTITY TO DATE 0.000 0160 0496 REMOV STR (INLET) EA 1.000 0.000 500.000 .00 0160 0496 ADJ EST QUANTITY TO DATE 0.000 0165 0500 MOBILIZATION LS 1.000 1.000 23,855.000 23,855.00 0170 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 12.000 12.000 2,000.000 24,000.00 0175 0506 TEMPORARY SEDIMENT CONTROL FENCE LF 40.000 0.000 3.950 .00 0175 0506 ADJ EST QUANTITY TO DATE 0.000 0180 0528 LANDSCAPE PAVERS SY 158.000 252.840 32.000 8,090.88 0180 0528 ADJ EST QUANTITY TO DATE 252.840 0185 0529 CONC CURB (TY II) LF 3,034.000 2,571.000 8.000 20,568.00 0185 0529 ADJ EST QUANTITY TO DATE 2,571.000 0190 0529 CONC CURB AND GUTTER (TY II)(REINF) LF 558.000 91.000 12.000 1,092.00 0190 0529 ADJ EST QUANTITY TO DATE 91.000 0195 0530 DRIVEWAYS (CONC) SY 51.000 0.000 52.000 .00 0195 0530 ADJ EST QUANTITY TO DATE 0.000 0200 0531 CURB RAMPS (TY 1) EA 1.000 4.000 800.000 3,200.00 0200 0531 ADJ EST QUANTITY TO DATE 4.000 0205 0531 CURB RAMPS (TY 2) EA 7.000 2.000 800.000 1,600.00 0205 0531 ADJ EST QUANTITY TO DATE 2.000 0210 0644 INS SM RD SN SUP&AM TY 10BWG(1) SA(P) EA 3.000 5.000 400.000 2,000.00 0210 0644 ADJ EST QUANTITY TO DATE 5.000 0215 0644 REMOVE SM RD SN SUP & AM EA 2.000 6.000 95.000 570.00 0215 0644 ADJ EST QUANTITY TO DATE 6.000 0220 0658 INSTL OM ASSM (OM-3R)(FLX)SRF EA 2.000 0.000 250.000 .00 0220 0658 ADJ EST QUANTITY TO DATE 0.000 0225 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 2,310.000 20.000 .720 14.40 0225 0666 ADJ EST QUANTITY TO DATE 20.000 0230 0666 REFL PAV MRK TY I (W) 4" (DOT)(100MIL) LF 60.000 0.000 2.500 .00 0230 0666 ADJ EST QUANTITY TO DATE 0.000 0235 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 3,185.000 0.000 .720 .00 0235 0666 ADJ EST QUANTITY TO DATE 0.000 0240 0666 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 3,126.000 2,530.000 1.450 3,668.50 0240 0666 ADJ EST QUANTITY TO DATE 2,530.000 0245 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 687.000 720.000 10.100 7,272.00 0245 0666 ADJ EST QUANTITY TO DATE 720.000 0250 0666 REFL PAV MRK TY I (W) (ARROW) (100MIL) EA 9.000 15.000 120.000 1,800.00 0250 0666 ADJ EST QUANTITY TO DATE 15.000 0255 0666 REFL PAV MRK TY I(W)(DBL 1 ARROW)(100MIL) EA 1.000 5.000 260.000 1,300.00 0255 0666 ADJ EST QUANTITY TO DATE 5.000 0260 0666 REFL PAV MRK TY I (W) (WORD) (100MIL) EA 13.000 15.000 145.000 2,175.00 0260 0666 ADJ EST QUANTITY TO DATE 15.000 0265 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 1,320.000 0.000 .800 .00 0265 0666 ADJ EST QUANTITY TO DATE 0.000 0270 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 5,542.000 1,985.000 .750 1,488.75 0270 0666 ADJ EST QUANTITY TO DATE 1,985.000 0275 0666 REFL PAV MRK TY I (Y) 12"(SLD)(100MIL) LF 27.000 15.000 6.370 95.55 0275 0666 ADJ EST QUANTITY TO DATE 15.000 0280 0666 REFL PAV MRK TY I (Y) 24"(SLD)(100MIL) LF 344.000 16.000 10.100 161.60 0280 0666 ADJ EST QUANTITY TO DATE 16.000 0285 0672 REFL PAV MRKR TY I-C EA 12.000 0.000 6.750 .00 0285 0672 ADJ EST QUANTITY TO DATE 0.000 0290 0672 REFL PAV MRKR TY II-A-A EA 184.000 12.000 4.250 51.00 0290 0672 ADJ EST QUANTITY TO DATE 12.000 0295 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 10,324.000 1,637.000 .720 1,178.64 0295 0677 ADJ EST QUANTITY TO DATE 1,637.000 0300 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 251.000 251.000 1.500 376.50 0305 0677 ELIM EXT PAV MRK & MRKS (ARROW) EA 10.000 20.000 85.000 1,700.00 0305 0677 ADJ EST QUANTITY TO DATE 20.000 0310 0677 ELIM EXT PAV MRK & MRKS (DBL ARROW) EA 1.000 1.000 140.000 140.00 0315 0677 ELIM EXT PAV MRK & MRKS (WORD) EA 11.000 12.000 115.000 1,380.00 0315 0677 ADJ EST QUANTITY TO DATE 12.000 0320 5845 MEDIAN BARR SEPARATOR(W)(FURN & INSTL) LF 240.000 0.000 53.000 .00 0320 5845 ADJ EST QUANTITY TO DATE 0.000 0325 5845 MEDIAN BARR SEPARATOR(Y)(FURN & INSTL) LF 362.000 0.000 53.000 .00 0325 5845 ADJ EST QUANTITY TO DATE 0.000 0330 6834 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 1.000 4,632.000 4,632.00 0330 6834 ADJ EST QUANTITY TO DATE 1.000 0335 0104*REMOVING CONC (COPING) LF 41.000 41.000 100.000 4,100.00 0340 0402*TRENCH EXCAVATION PROTECTION LF 75.000 75.000 5.000 375.00 0345 0432*RIPRAP (MOW STRIP)(5 IN) CY 2.000 2.000 500.000 1,000.00 0350 0438*CLEAN AND SEAL CRACKS LF 41.000 41.000 20.000 820.00 0355 0512*MOVE SPECIAL PORTABLE TRAFFIC BARRIER LF 41.000 41.000 50.000 2,050.00 0360 0770*REPAIR RAIL ELEMENT (W-BEAM) LF 75.000 25.000 15.000 375.00 0360 0770 ADJ EST QUANTITY TO DATE 25.000 1 0365 0770*REM/REPL TIMBER/STL POST W/ CONC FND EA 2.000 3.000 100.000 300.00 0365 0770 ADJ EST QUANTITY TO DATE 3.000 0370 0770*REALIGN POSTS EA 4.000 4.000 30.000 120.00 0375 9000*MOBILIZATION LS 1.000 1.000 1,200.000 1,200.00 0380 9000*TCP MO 1.000 1.000 2,000.000 2,000.00 0385 0105*REMOVING STAB BASE & ASPH PAV(16") SY 407.000 639.700 32.410 20,732.68 0385 0105 ADJ EST QUANTITY TO DATE 639.700 0390 0132*EMBANKMENT (FINAL)(ORD COMP)(TY A) CY 320.400 336.400 19.500 6,559.80 0390 0132 ADJ EST QUANTITY TO DATE 336.400 0395 0216*PROOF ROLLING HR 3.000 6.000 90.000 540.00 0395 0216 ADJ EST QUANTITY TO DATE 6.000 0400 0247*FL BS (CMP IN PLC)(TY D GR 4)(FNAL POS) CY 21.000 0.000 42.000 .00 0400 0247 ADJ EST QUANTITY TO DATE 0.000 0405 0330*LRA PAV TY-I GR-C TON 279.000 313.670 130.000 40,777.10 0405 0330 ADJ EST QUANTITY TO DATE 313.670 0410 0432*RIPRAP(CONC)(FLUME)(OPT2) CY 10.000 10.000 465.000 4,650.00 0415 0479*ADJUST INLET (CAP) EA 2.000 2.000 1,800.000 3,600.00 0420 0644*RELOCATE SM RD SN SUP & AM TY 10BWG EA 1.000 2.000 550.000 1,100.00 0420 0644 ADJ EST QUANTITY TO DATE 2.000 0425 0666*REFL PAV MRK TY I (W) 8" (DOT)(100MIL) LF 126.000 33.000 4.550 150.15 0425 0666 ADJ EST QUANTITY TO DATE 33.000 0430 0666*REFL PAV MRK TY I (Y) 8" (SLD)(100MIL) LF 54.000 70.000 4.550 318.50 0430 0666 ADJ EST QUANTITY TO DATE 70.000 0435 0677*ELIM EXT PAV MRK & MRKS (24") LF 36.000 112.000 6.550 733.60 0435 0677 ADJ EST QUANTITY TO DATE 112.000 0440 3198*FAST TRACK (CPCD)(12") SY 1,211.000 1,470.700 104.000 152,952.80 0440 3198 ADJ EST QUANTITY TO DATE 1,470.700 0445 9000*REFL PAV MRK TY I (Y) 24" (SLD)(100MIL) LF 10.000 0.000 13.000 .00 0445 9000 ADJ EST QUANTITY TO DATE 0.000 0450 9000*TWO LIGHT TOWER & FUEL WK 6.000 5.000 586.000 2,930.00 0450 9000 ADJ EST QUANTITY TO DATE 5.000 0455 0666*REFL PAV MRK TY I (W) 12"(SLD)(100MIL) LF 58.000 0.000 5.500 .00 0455 0666 ADJ EST QUANTITY TO DATE 0.000 0460 0110*EXCAVATION (ROADWAY) CY 44.660 406.540 12.500 5,081.75 0460 0110 ADJ EST QUANTITY TO DATE 406.540 0465 0672*REFL PAV MRKR TY II-C-R EA 63.000 0.000 13.500 .00 0465 0672 ADJ EST QUANTITY TO DATE 0.000 0470 0677*ELIM EXT PAV MRK & MRKS (12") LF 89.000 0.000 6.200 .00 0470 0677 ADJ EST QUANTITY TO DATE 0.000 0475 9000*MEDIAN BARR SEPARATOR POST 1 (W) FUR&INST EA 19.000 0.000 138.000 .00 0475 9000 ADJ EST QUANTITY TO DATE 0.000 0480 9000*FL BS (CMP IN PLC) (TY D GR 4) (FIN POS CY 15.000 0.000 42.000 .00 0480 9000 ADJ EST QUANTITY TO DATE 0.000 0485 0531*CONC SIDEWALKS (6") SY 26.000 15.000 47.750 716.25 0485 0531 ADJ EST QUANTITY TO DATE 15.000 0490 9000*RELOCATE SM RD SN & AM TY 10 BWG EA 2.000 0.000 325.000 .00 0490 9000 ADJ EST QUANTITY TO DATE 0.000 0495 9000*SAW-CUT ASPHALT LF 630.000 603.000 3.750 2,261.25 0495 9000 ADJ EST QUANTITY TO DATE 603.000 0 SUBTOTAL BID ITEMS $ 434,201.72 0 TOTAL AMOUNT WORK DONE RAISED MEDIAN, SIGNING & STRIPING $ 434,201.72 0 TOTAL AMOUNT WORK DONE CONTROL 6210-65-001 $ 434,201.72 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6102207 MGR.NO. 005 PAGE 001 CONT 6210 SEC 65 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 621065001 HWY LP0020 1817 BOB BULLOCK LAREDO CNTY WEBB DIST 22 CONTRACT PRICE $ 317,751.67 REPORT DATE 09/13/2012 07.44.22 CONTRACTOR GILMAR CONSTRUCTION, LTD. 10900 EST PERIOD AUG 09,2010 TO APR 24,2012 EST NO 021 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN AUG 9 , 2010 WORKING DAYS USED 591 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED APR 24 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6210-65-001 RMC - 621065001 22 LP0020 WEBB - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0104 REMOVING CONC (PAV) SY 60.000 14.660 73.750 1,081.18 0104 ADJ EST QUANTITY TO DATE 14.660 0104 REMOVING CONC (MEDIANS) SY 51.000 267.650 31.500 8,430.98 0104 ADJ EST QUANTITY TO DATE 267.650 0104 REMOVING CONC (CURB) LF 159.000 1,278.000 3.500 4,473.00 0104 ADJ EST QUANTITY TO DATE 1,278.000 0104 REMOVING CONC (CURB AND GUTTER) LF 1,893.000 639.000 9.150 5,846.85 0104 ADJ EST QUANTITY TO DATE 639.000 0104 REMOVING CONC (WHEELCHAIR RAMP) SY 27.000 61.440 15.750 967.68 0104 ADJ EST QUANTITY TO DATE 61.440 0104 REMOVING CONC (PAVERS) SY 400.000 668.770 8.950 5,985.49 0104 ADJ EST QUANTITY TO DATE 668.770 0105 REMOVING STAB BASE & ASPH PAV(14") SY 800.000 225.140 21.000 4,727.94 0105 ADJ EST QUANTITY TO DATE 225.140 0340 D-GR HMA(METH) TY-B PG70-22 TON 525.000 69.840 106.000 7,403.04 0340 ADJ EST QUANTITY TO DATE 69.840 0340 D-GR HMA(METH) TY-C PG70-22 TON 179.000 125.910 131.000 16,494.21 0340 ADJ EST QUANTITY TO DATE 125.910 0360 CONC PVMT (CONT REINF-CRCP)(12") SY 60.000 66.670 95.000 6,333.65 0360 ADJ EST QUANTITY TO DATE 66.670 0464 RC PIPE (CL III)(24 IN) LF 100.000 24.000 46.000 1,104.00 10464 ADJ EST QUANTITY TO DATE 24.000 0465 INLET (COMPL)(TY C) EA 1.000 1.000 3,500.000 3,500.00 0500 MOBILIZATION LS 1.000 1.000 23,855.000 23,855.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 12.000 12.000 2,000.000 24,000.00 0528 LANDSCAPE PAVERS SY 158.000 252.840 32.000 8,090.88 0528 ADJ EST QUANTITY TO DATE 252.840 0529 CONC CURB (TY II) LF 3,034.000 2,571.000 8.000 20,568.00 0529 ADJ EST QUANTITY TO DATE 2,571.000 0529 CONC CURB AND GUTTER (TY II)(REINF) LF 558.000 91.000 12.000 1,092.00 0529 ADJ EST QUANTITY TO DATE 91.000 0531 CURB RAMPS (TY 1) EA 1.000 4.000 800.000 3,200.00 0531 ADJ EST QUANTITY TO DATE 4.000 0531 CURB RAMPS (TY 2) EA 7.000 2.000 800.000 1,600.00 0531 ADJ EST QUANTITY TO DATE 2.000 0644 INS SM RD SN SUP&AM TY 10BWG(1) SA(P) EA 3.000 5.000 400.000 2,000.00 0644 ADJ EST QUANTITY TO DATE 5.000 0644 REMOVE SM RD SN SUP & AM EA 2.000 6.000 95.000 570.00 0644 ADJ EST QUANTITY TO DATE 6.000 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 2,310.000 20.000 .720 14.40 0666 ADJ EST QUANTITY TO DATE 20.000 0666 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 3,126.000 2,530.000 1.450 3,668.50 0666 ADJ EST QUANTITY TO DATE 2,530.000 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 687.000 720.000 10.100 7,272.00 0666 ADJ EST QUANTITY TO DATE 720.000 0666 REFL PAV MRK TY I (W) (ARROW) (100MIL) EA 9.000 15.000 120.000 1,800.00 0666 ADJ EST QUANTITY TO DATE 15.000 0666 REFL PAV MRK TY I(W)(DBL ARROW)(100MIL) EA 1.000 5.000 260.000 1,300.00 0666 ADJ EST QUANTITY TO DATE 5.000 0666 REFL PAV MRK TY I (W) (WORD) (100MIL) EA 13.000 15.000 145.000 2,175.00 0666 ADJ EST QUANTITY TO DATE 15.000 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 5,542.000 1,985.000 .750 1,488.75 0666 ADJ EST QUANTITY TO DATE 1,985.000 0666 REFL PAV MRK TY I (Y) 12"(SLD)(100MIL) LF 27.000 15.000 6.370 95.55 0666 ADJ EST QUANTITY TO DATE 15.000 0666 REFL PAV MRK TY I (Y) 24"(SLD)(100MIL) LF 344.000 16.000 10.100 161.60 0666 ADJ EST QUANTITY TO DATE 16.000 0672 REFL PAV MRKR TY II-A-A EA 184.000 12.000 4.250 51.00 0672 ADJ EST QUANTITY TO DATE 12.000 0677 ELIM EXT PAV MRK & MRKS ( 1 4") LF 10,324.000 1,637.000 .720 1,178.64 0677 ADJ EST QUANTITY TO DATE 1,637.000 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 251.000 251.000 1.500 376.50 0677 ELIM EXT PAV MRK & MRKS (ARROW) EA 10.000 20.000 85.000 1,700.00 0677 ADJ EST QUANTITY TO DATE 20.000 0677 ELIM EXT PAV MRK & MRKS (DBL ARROW) EA 1.000 1.000 140.000 140.00 0677 ELIM EXT PAV MRK & MRKS (WORD) EA 11.000 12.000 115.000 1,380.00 0677 ADJ EST QUANTITY TO DATE 12.000 6834 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 1.000 4,632.000 4,632.00 6834* ADJ EST QUANTITY TO DATE 1.000 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00104* REMOVING CONC (COPING) LF 41.000 41.000 100.000 4,100.00 0105* REMOVING STAB BASE & ASPH PAV(16") SY 407.000 639.700 32.410 20,732.68 0105* ADJ EST QUANTITY TO DATE 639.700 0110* EXCAVATION (ROADWAY) CY 44.660 406.540 12.500 5,081.75 0110* ADJ EST QUANTITY TO DATE 406.540 0132* EMBANKMENT (FINAL)(ORD COMP)(TY A) CY 320.400 336.400 19.500 6,559.80 0132* ADJ EST QUANTITY TO DATE 336.400 0216* PROOF ROLLING HR 3.000 6.000 90.000 540.00 0216* ADJ EST QUANTITY TO DATE 6.000 0330* LRA PAV TY-I GR-C TON 279.000 313.670 130.000 40,777.10 0330* ADJ EST QUANTITY TO DATE 313.670 0402* TRENCH EXCAVATION PROTECTION LF 75.000 75.000 5.000 375.00 0432* RIPRAP (MOW STRIP)(5 IN) CY 2.000 2.000 500.000 1,000.00 0432* RIPRAP(CONC)(FLUME)(OPT2) CY 10.000 10.000 465.000 4,650.00 0438* CLEAN AND SEAL CRACKS LF 41.000 41.000 20.000 820.00 0479* ADJUST INLET (CAP) EA 2.000 2.000 1,800.000 3,600.00 0512* MOVE SPECIAL PORTABLE TRAFFIC BARRIER LF 41.000 41.000 50.000 2,050.00 0531* CONC SIDEWALKS (6") SY 26.000 15.000 47.750 716.25 0531* ADJ EST QUANTITY TO DATE 15.000 0644* RELOCATE SM RD SN SUP & AM TY 10BWG EA 1.000 2.000 550.000 1,100.00 0644* ADJ EST QUANTITY TO DATE 2.000 0666* REFL PAV MRK TY I (W) 8" (DOT)(100MIL) LF 126.000 33.000 4.550 150.15 0666* ADJ EST QUANTITY TO DATE 33.000 0666* REFL PAV MRK TY I (Y) 8" (SLD)(100MIL) LF 54.000 70.000 4.550 318.50 0666* ADJ EST QUANTITY TO DATE 70.000 0677* ELIM EXT PAV MRK & MRKS (24") LF 36.000 112.000 6.550 733.60 10677* ADJ EST QUANTITY TO DATE 112.000 0770* REPAIR RAIL ELEMENT (W-BEAM) LF 75.000 25.000 15.000 375.00 0770* ADJ EST QUANTITY TO DATE 25.000 0770* REM/REPL TIMBER/STL POST W/ CONC FND EA 2.000 3.000 100.000 300.00 0770* ADJ EST QUANTITY TO DATE 3.000 0770* REALIGN POSTS EA 4.000 4.000 30.000 120.00 3198* FAST TRACK (CPCD)(12") SY 1,211.000 1,470.700 104.000 152,952.80 3198* ADJ EST QUANTITY TO DATE 1,470.700 9000* MOBILIZATION LS 1.000 1.000 1,200.000 1,200.00 9000* TCP MO 1.000 1.000 2,000.000 2,000.00 9000* TWO LIGHT TOWER & FUEL WK 6.000 5.000 586.000 2,930.00 9000* ADJ EST QUANTITY TO DATE 5.000 9000* SAW-CUT ASPHALT LF 630.000 603.000 3.750 2,261.25 9000* ADJ EST QUANTITY TO DATE 603.000 0 SUBTOTAL BID ITEMS $ 434,201.72 0 CONTRACT TOTAL ALL ITEMS $ 434,201.72 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6102207 MGR.NO. 005 PAGE 001 CONT 6210 SEC 65 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 621065001 HWY LP0020 1817 BOB BULLOCK LAREDO CNTY WEBB DIST 22 CONTRACT PRICE $ 317,751.67 REPORT DATE 09/13/2012 07.44.22 CONTRACTOR GILMAR CONSTRUCTION, LTD. 10900 EST PERIOD AUG 09,2010 TO APR 24,2012 EST NO 021 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 240 RMC - 621065001 6210-65-001 434,201.72 .00 434,201.72 .00 .00 434,201.72 431,696.22 2,505.50 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 434,201.72 .00 434,201.72 .00 .00 434,201.72 431,696.22 2,505.50 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6102207 MGR.NO. 005 PAGE 001 CONT 6210 SEC 65 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 621065001 HWY LP0020 1817 BOB BULLOCK LAREDO CNTY WEBB DIST 22 CONTRACT PRICE $ 317,751.67 REPORT DATE 09/13/2012 07.44.22 CONTRACTOR GILMAR CONSTRUCTION, LTD. 10900 EST PERIOD AUG 09,2010 TO APR 24,2012 EST NO 021 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6210-65-001 RMC - 621065001 22 LP0020 WEBB -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 165 0500 MOBILIZATION LS 1.000 0.100 23,855.000 2,385.50 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 375 9000* MOBILIZATION LS 0.000 0.100 1,200.000 120.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 2,505.50 0 TOTAL AMOUNT WORK DONE TO DATE - $ 434,201.72