1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1110604 MGR.NO. 770 PAGE 001 CONT 6214 SEC 29 JOB 001 RES ENGR DILL, CAROLYN PROJ RMC - 621429001 HWY IH0020 3901 E. HWY 80 ODESSA CNTY MIDLAND DIST 06 CONTRACT PRICE $ 248,429.20 REPORT DATE 01/31/2013 10.50.46 CONTRACTOR MIJELUM 12196 EST PERIOD JUN 01,2011 TO JAN 30,2013 EST NO 020 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 04, 2011 TIME COMPUTED FROM JUN 01, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 119 580 76 504 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JAN 13 1 1 NO CREW AVALIABLE/ DAY CHARGED TOTAL DAYS ALLOWED = 119 2 1 NO CREW AVALIABLE/ DAY CHARGED DATE WORK COMPLETED 01/30/13 3 1 SNOW DAYS CHARGED TO DATE = 92 4 1 SNOW ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 400 6 1 SUNDAY 7 1 NO CREW AVALIABLE/ DAY CHARGED LIQUIDATED DAMAGES 8 1 NO CREW AVALIABLE/ DAY CHARGED 0 DAYS AT $ 400 PER DAY 9 1 RAIN TOTAL = $ .00 10 1 TOO WET 11 1 NO CREW AVALIABLE/ DAY CHARGED CERTIFIED AS CORRECT AND 12 1 SATURDAY ONE COPY HAS BEEN GIVEN 13 1 SUNDAY TO THE CONTRACTOR 14 1 NO CREW AVALIABLE/ DAY CHARGED 15 1 NO CREW AVALIABLE/ DAY CHARGED 16 1 NO CREW AVALIABLE/ DAY CHARGED ---------------------------- 17 1 NO CREW AVALIABLE/ DAY CHARGED AREA/PROJECT ENGINEER 18 1 NO CREW AVALIABLE/ DAY CHARGED 19 1 SATURDAY 20 1 SUNDAY 21 1 HOLIDAY 22 1 CREW WORKED IN MIDLAND COUNTY 23 1 CREW WORKED IN MIDLAND COUNTY 24 1 CREW WORKED IN MIDLAND COUNTY 25 1 CREW WORKED IN MIDLAND COUNTY 26 1 SATURDAY 27 1 SUNDAY 28 1 CREW WORKED IN MIDLAND COUNTY 29 1 CREW WORKED IN MIDLAND COUNTY 30 1 WORK ACCEPTED 0 ----- ----- ----- 610 92 518 4 SATURDAY 4 SUNDAY 1 HOLIDAY 2 SNOW 1 RAIN 1 TOO WET 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1110604 MGR.NO. 770 PAGE 001 CONT 6214 SEC 29 JOB 001 RES ENGR DILL, CAROLYN PROJ RMC - 621429001 HWY IH0020 3901 E. HWY 80 ODESSA CNTY MIDLAND DIST 06 CONTRACT PRICE $ 248,429.20 REPORT DATE 01/31/2013 10.50.47 CONTRACTOR MIJELUM 12196 EST PERIOD JUN 01,2011 TO JAN 30,2013 EST NO 020 & FINAL DIST. 06 COUNTY MIDLAND CONTROL 6214-29-001 PROJECT RMC - 621429001 HIGHWAY IH0020 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- ROADSIDE MOWING 0 0050 ROADSIDE MOWING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0055 0730 STRIP MOWING AC 616.000 0.000 16.700 .00 0060 0730 FULL-WIDTH MOWING AC 14,260.000 9,027.000 16.700 150,750.90 0 SUBTOTAL BID ITEMS $ 150,750.90 0 TOTAL AMOUNT WORK DONE ROADSIDE MOWING $ 150,750.90 0 TOTAL AMOUNT WORK DONE CONTROL 6214-29-001 $ 150,750.90 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1110604 MGR.NO. 770 PAGE 001 CONT 6214 SEC 29 JOB 001 RES ENGR DILL, CAROLYN PROJ RMC - 621429001 HWY IH0020 3901 E. HWY 80 ODESSA CNTY MIDLAND DIST 06 CONTRACT PRICE $ 248,429.20 REPORT DATE 01/31/2013 10.50.48 CONTRACTOR MIJELUM 12196 EST PERIOD JUN 01,2011 TO JAN 30,2013 EST NO 020 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN NOV 4 , 2011 WORKING DAYS USED 92 PERCENT COMPLETE 100.00 PERCENT TIME USED 77.30 DATE COMPLETED JAN 30 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6214-29-001 RMC - 621429001 06 IH0020 MIDLAND - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 14,260.000 9,027.000 16.700 150,750.90 0 SUBTOTAL BID ITEMS $ 150,750.90 0 CONTRACT TOTAL ALL ITEMS $ 150,750.90 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1110604 MGR.NO. 770 PAGE 001 CONT 6214 SEC 29 JOB 001 RES ENGR DILL, CAROLYN PROJ RMC - 621429001 HWY IH0020 3901 E. HWY 80 ODESSA CNTY MIDLAND DIST 06 CONTRACT PRICE $ 248,429.20 REPORT DATE 01/31/2013 10.50.48 CONTRACTOR MIJELUM 12196 EST PERIOD JUN 01,2011 TO JAN 30,2013 EST NO 020 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 165 RMC - 621429001 6214-29-001 150,750.90 .00 150,750.90 .00 .00 150,750.90 139,411.60 11,339.30 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 150,750.90 .00 150,750.90 .00 .00 150,750.90 139,411.60 11,339.30 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1110604 MGR.NO. 770 PAGE 001 CONT 6214 SEC 29 JOB 001 RES ENGR DILL, CAROLYN PROJ RMC - 621429001 HWY IH0020 3901 E. HWY 80 ODESSA CNTY MIDLAND DIST 06 CONTRACT PRICE $ 248,429.20 REPORT DATE 01/31/2013 10.50.48 CONTRACTOR MIJELUM 12196 EST PERIOD JUN 01,2011 TO JAN 30,2013 EST NO 020 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6214-29-001 RMC - 621429001 06 IH0020 MIDLAND -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING AC 14,260.000 679.000 16.700 11,339.30 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 11,339.30 0 TOTAL AMOUNT WORK DONE TO DATE - $ 150,750.90