1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2120111 MGR.NO. 007 PAGE 001 CONT 6228 SEC 69 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 622869001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 190,751.30 REPORT DATE 01/09/2013 16.09.12 CONTRACTOR FLOWER MOUND WATER BLAST, INC 15400 EST PERIOD MAY 15,2012 TO NOV 14,2012 EST NO 008 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 15, 2012 TIME COMPUTED FROM MAY 22, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 66 170 24 146 BROUGHT FORWARD ADDL DAYS GRANTED = 1 NOV 12 1 1 TOTAL DAYS ALLOWED = 67 2 1 DATE WORK COMPLETED 11/14/12 3 1 SATURDAY DAYS CHARGED TO DATE = 33 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 590 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 590 PER DAY 9 1 TOTAL = $ .00 10 1 SATURDAY 11 1 SUNDAY CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 WORK COMPLETED AND ACCEPTED 0 ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 184 33 151 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2120111 MGR.NO. 007 PAGE 001 CONT 6228 SEC 69 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 622869001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 190,751.30 REPORT DATE 01/09/2013 16.09.12 CONTRACTOR FLOWER MOUND WATER BLAST, INC 15400 EST PERIOD MAY 15,2012 TO NOV 14,2012 EST NO 008 & FINAL DIST. 01 COUNTY LAMAR CONTROL 6228-69-001 PROJECT RMC - 622869001 HIGHWAY US0082 0LIMITS- VARIOUS ROADWAYS IN LAMAR COUNTY 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 ENTERED BY R. COSTON OTHER WW 0 0055 MOWING HIGHWAY ROW NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 7,307.000 7,355.000 25.900 190,494.50 0065 0730 SPOT MOWING AC 20.000 0.000 75.000 .00 0 SUBTOTAL BID ITEMS $ 190,494.50 0 TOTAL AMOUNT WORK DONE MOWING HIGHWAY ROW $ 190,494.50 0 TOTAL AMOUNT WORK DONE CONTROL 6228-69-001 $ 190,494.50 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2120111 MGR.NO. 007 PAGE 001 CONT 6228 SEC 69 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 622869001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 190,751.30 REPORT DATE 01/09/2013 16.09.12 CONTRACTOR FLOWER MOUND WATER BLAST, INC 15400 EST PERIOD MAY 15,2012 TO NOV 14,2012 EST NO 008 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN 0 LAMAR COUNTY DATE WORK BEGAN MAY 15, 2012 WORKING DAYS USED 33 PERCENT COMPLETE 100.00 PERCENT TIME USED 49.20 DATE COMPLETED NOV 14 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6228-69-001 RMC - 622869001 01 US0082 LAMAR - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 7,307.000 7,355.000 25.900 190,494.50 0 SUBTOTAL BID ITEMS $ 190,494.50 0 CONTRACT TOTAL ALL ITEMS $ 190,494.50 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2120111 MGR.NO. 007 PAGE 001 CONT 6228 SEC 69 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 622869001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 190,751.30 REPORT DATE 01/09/2013 16.09.12 CONTRACTOR FLOWER MOUND WATER BLAST, INC 15400 EST PERIOD MAY 15,2012 TO NOV 14,2012 EST NO 008 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 139 RMC - 622869001 6228-69-001 190,494.50 .00 190,494.50 .00 .00 190,494.50 190,494.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 190,494.50 .00 190,494.50 .00 .00 190,494.50 190,494.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2120111 MGR.NO. 007 PAGE 001 CONT 6228 SEC 69 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 622869001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 190,751.30 REPORT DATE 01/09/2013 16.09.13 CONTRACTOR FLOWER MOUND WATER BLAST, INC 15400 EST PERIOD MAY 15,2012 TO NOV 14,2012 EST NO 008 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6228-69-001 RMC - 622869001 01 US0082 LAMAR -LIMITS - VARIOUS ROADWAYS IN LAMAR COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 190,494.50