1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2120102 MGR.NO. 009 PAGE 001 CONT 6237 SEC 65 JOB 001 RES ENGR SIMS, TAMMY PROJ RMC - 623765001 HWY IH0030 1100 HILLCREST SULPHUR SP CNTY HOPKINS DIST 01 CONTRACT PRICE $ 57,296.00 REPORT DATE 06/04/2013 13.52.39 CONTRACTOR 4C CONSTRUCTION 15478 EST PERIOD MAY 01,2012 TO APR 19,2013 EST NO 013 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 01, 2012 TIME COMPUTED FROM MAY 08, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 255 335 228 107 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 TOTAL DAYS ALLOWED = 255 2 1 DATE WORK COMPLETED 04/19/13 3 1 DAYS CHARGED TO DATE = 242 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 570 6 1 SATURDAY 7 1 SUNDAY LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 570 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 SATURDAY TO THE CONTRACTOR 14 1 SUNDAY 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 CONTRACT TERMINATED - - - - ----- ----- ----- 354 242 112 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 CONTRACT TERMINATED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2120102 MGR.NO. 009 PAGE 001 CONT 6237 SEC 65 JOB 001 RES ENGR SIMS, TAMMY PROJ RMC - 623765001 HWY IH0030 1100 HILLCREST SULPHUR SP CNTY HOPKINS DIST 01 CONTRACT PRICE $ 57,296.00 REPORT DATE 06/04/2013 13.52.40 CONTRACTOR 4C CONSTRUCTION 15478 EST PERIOD MAY 01,2012 TO APR 19,2013 EST NO 013 & FINAL DIST. 01 COUNTY HOPKINS CONTROL 6237-65-001 PROJECT RMC - 623765001 HIGHWAY IH0030 0LIMITS- VARIOUS ROADWAYS IN HOPKINS AND FRANKLIN COUNTIES 0TYPE OF WORK- REMOVAL AND DISPOSAL OF DEBRIS 0 0005 PREPARED BY D EVANS 11/10/11 0 0055 REMOVAL AND DISPOSAL OF DEBRIS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (1) CYC 104.000 95.000 221.000 20,995.00 0065 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (3) CYC 12.000 11.000 150.000 1,650.00 0070 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (4) CYC 12.000 11.000 150.000 1,650.00 0075 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (5) CYC 12.000 11.000 150.000 1,650.00 0080 0735 DEBRIS - FRONTAGE ROADS - AREA (2) CYC 104.000 95.000 139.000 13,205.00 0085 0735 DEBRIS-ENTRANCE/EXIT RAMPS - AREA (1) CYC 104.000 95.000 139.000 13,205.00 0 SUBTOTAL BID ITEMS $ 52,355.00 0 TOTAL AMOUNT WORK DONE REMOVAL AND DISPOSAL OF DEBRIS $ 52,355.00 0 TOTAL AMOUNT WORK DONE CONTROL 6237-65-001 $ 52,355.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2120102 MGR.NO. 009 PAGE 001 CONT 6237 SEC 65 JOB 001 RES ENGR SIMS, TAMMY PROJ RMC - 623765001 HWY IH0030 1100 HILLCREST SULPHUR SP CNTY HOPKINS DIST 01 CONTRACT PRICE $ 57,296.00 REPORT DATE 06/04/2013 13.52.40 CONTRACTOR 4C CONSTRUCTION 15478 EST PERIOD MAY 01,2012 TO APR 19,2013 EST NO 013 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN HOPKINS 0 AND FRANKLIN COUNTIES DATE WORK BEGAN MAY 1 , 2012 WORKING DAYS USED 242 PERCENT COMPLETE 100.00 PERCENT TIME USED 94.90 DATE COMPLETED APR 19 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6237-65-001 RMC - 623765001 01 IH0030 HOPKINS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (1) CYC 104.000 95.000 221.000 20,995.00 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (3) CYC 12.000 11.000 150.000 1,650.00 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (4) CYC 12.000 11.000 150.000 1,650.00 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (5) CYC 12.000 11.000 150.000 1,650.00 0735 DEBRIS - FRONTAGE ROADS - AREA (2) CYC 104.000 95.000 139.000 13,205.00 0735 DEBRIS-ENTRANCE/EXIT RAMPS - AREA (1) CYC 104.000 95.000 139.000 13,205.00 0 SUBTOTAL BID ITEMS $ 52,355.00 0 CONTRACT TOTAL ALL ITEMS $ 52,355.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2120102 MGR.NO. 009 PAGE 001 CONT 6237 SEC 65 JOB 001 RES ENGR SIMS, TAMMY PROJ RMC - 623765001 HWY IH0030 1100 HILLCREST SULPHUR SP CNTY HOPKINS DIST 01 CONTRACT PRICE $ 57,296.00 REPORT DATE 06/04/2013 13.52.40 CONTRACTOR 4C CONSTRUCTION 15478 EST PERIOD MAY 01,2012 TO APR 19,2013 EST NO 013 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 113 RMC - 623765001 6237-65-001 52,355.00 .00 52,355.00 .00 .00 52,355.00 52,355.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 52,355.00 .00 52,355.00 .00 .00 52,355.00 52,355.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2120102 MGR.NO. 009 PAGE 001 CONT 6237 SEC 65 JOB 001 RES ENGR SIMS, TAMMY PROJ RMC - 623765001 HWY IH0030 1100 HILLCREST SULPHUR SP CNTY HOPKINS DIST 01 CONTRACT PRICE $ 57,296.00 REPORT DATE 06/04/2013 13.52.40 CONTRACTOR 4C CONSTRUCTION 15478 EST PERIOD MAY 01,2012 TO APR 19,2013 EST NO 013 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6237-65-001 RMC - 623765001 01 IH0030 HOPKINS -LIMITS - VARIOUS ROADWAYS IN HOPKINS AND FRANKLIN COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 52,355.00