1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8121011 MGR.NO. 770 PAGE 001 CONT 6244 SEC 52 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 624452001 HWY FM0855 2709 W FRONT ST TYLER CNTY CHEROKEE DIST 10 CONTRACT PRICE $ 198,900.00 REPORT DATE 03/19/2013 16.11.27 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD NOV 12,2012 TO MAR 05,2013 EST NO 005 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 16, 2012 TIME COMPUTED FROM NOV 12, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 102 109 57 52 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 13 1 1 TOTAL DAYS ALLOWED = 102 2 1 DATE WORK COMPLETED 03/05/13 3 1 SUNDAY DAYS CHARGED TO DATE = 60 4 1 ASSESSED LIQ DAMAGES = 0 5 1 WORK COMPLETED AND ACCEPTED LIQ DAMAGE RATE $ 590 0 LIQUIDATED DAMAGES 0 DAYS AT $ 590 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 114 60 54 0 SATURDAY 1 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8121011 MGR.NO. 770 PAGE 001 CONT 6244 SEC 52 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 624452001 HWY FM0855 2709 W FRONT ST TYLER CNTY CHEROKEE DIST 10 CONTRACT PRICE $ 198,900.00 REPORT DATE 03/19/2013 16.11.28 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD NOV 12,2012 TO MAR 05,2013 EST NO 005 & FINAL DIST. 10 COUNTY CHEROKEE CONTROL 6244-52-001 PROJECT RMC - 624452001 HIGHWAY FM0855 0LIMITS- VARIOUS LOCATIONS IN JVILLE/RUSK MTCE CHEROKEE CO., ETC. 0TYPE OF WORK- TREE TRIMMING AND BRUSH REMOVAL 0 0005 PREPARED BY RHEATIA GANDY 0 0055 TREE TRIMMING AND BRUSH CONTROL NET LENGTH153.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0752 TREE TRIMMING/BRUSH REMOVAL MI 153.000 153.000 1,300.000 198,900.00 0 SUBTOTAL BID ITEMS $ 198,900.00 0 TOTAL AMOUNT WORK DONE TREE TRIMMING AND BRUSH CONTROL $ 198,900.00 0 TOTAL AMOUNT WORK DONE CONTROL 6244-52-001 $ 198,900.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8121011 MGR.NO. 770 PAGE 001 CONT 6244 SEC 52 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 624452001 HWY FM0855 2709 W FRONT ST TYLER CNTY CHEROKEE DIST 10 CONTRACT PRICE $ 198,900.00 REPORT DATE 03/19/2013 16.11.28 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD NOV 12,2012 TO MAR 05,2013 EST NO 005 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN JVILLE/RUSK MTCE 0 CHEROKEE CO., ETC. DATE WORK BEGAN NOV 16, 2012 WORKING DAYS USED 60 PERCENT COMPLETE 100.00 PERCENT TIME USED 58.80 DATE COMPLETED MAR 5 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6244-52-001 RMC - 624452001 10 FM0855 CHEROKEE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0752 TREE TRIMMING/BRUSH REMOVAL MI 153.000 153.000 1,300.000 198,900.00 0 SUBTOTAL BID ITEMS $ 198,900.00 0 CONTRACT TOTAL ALL ITEMS $ 198,900.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8121011 MGR.NO. 770 PAGE 001 CONT 6244 SEC 52 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 624452001 HWY FM0855 2709 W FRONT ST TYLER CNTY CHEROKEE DIST 10 CONTRACT PRICE $ 198,900.00 REPORT DATE 03/19/2013 16.11.28 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD NOV 12,2012 TO MAR 05,2013 EST NO 005 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 37 RMC - 624452001 6244-52-001 198,900.00 .00 198,900.00 .00 .00 198,900.00 188,500.00 10,400.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 198,900.00 .00 198,900.00 .00 .00 198,900.00 188,500.00 10,400.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8121011 MGR.NO. 770 PAGE 001 CONT 6244 SEC 52 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 624452001 HWY FM0855 2709 W FRONT ST TYLER CNTY CHEROKEE DIST 10 CONTRACT PRICE $ 198,900.00 REPORT DATE 03/19/2013 16.11.28 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD NOV 12,2012 TO MAR 05,2013 EST NO 005 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6244-52-001 RMC - 624452001 10 FM0855 CHEROKEE -LIMITS - VARIOUS LOCATIONS IN JVILLE/RUSK MTCE CHEROKEE CO., ETC. LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0752 TREE TRIMMING/BRUSH REMOVAL MI 153.000 8.000 1,300.000 10,400.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 10,400.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 198,900.00