1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1131001 MGR.NO. 770 PAGE 001 CONT 6251 SEC 47 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 625147001 HWY SH0031 2709 W FRONT ST TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 82,442.42 REPORT DATE 05/06/2013 08.22.13 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD MAR 11,2013 TO MAR 28,2013 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 12, 2013 TIME COMPUTED FROM MAR 11, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 27 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 13 TOTAL DAYS ALLOWED = 27 DATE WORK COMPLETED 03/28/13 DAYS CHARGED TO DATE = 13 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 570 0 LIQUIDATED DAMAGES 0 DAYS AT $ 570 PER DAY TOTAL = $ .00 0 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 SATURDAY ---------------------------- 17 1 SUNDAY AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 SATURDAY 24 1 SUNDAY 25 1 26 1 27 1 28 1 WORK COMPLETED AND ACCEPTED - ----- ----- ----- 18 13 5 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1131001 MGR.NO. 770 PAGE 001 CONT 6251 SEC 47 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 625147001 HWY SH0031 2709 W FRONT ST TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 82,442.42 REPORT DATE 05/06/2013 08.22.13 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD MAR 11,2013 TO MAR 28,2013 EST NO 002 & FINAL DIST. 10 COUNTY HENDERSON CONTROL 6251-47-001 PROJECT RMC - 625147001 HIGHWAY SH0031 0LIMITS- VARIOUS ROADS IN THE ATHENS MTCE. SECTION IN THE TYLER DISTRICT 0TYPE OF WORK- RPM REPLACEMENT 0 0005 PREPARED BY RHEATIA GANDY 0 0055 RAISED PAVEMENT MARKERS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0672 REFL PAV MRKR TY I-A EA 1,494.000 1,479.000 2.200 3,253.80 0065 0672 REFL PAV MRKR TY I-C EA 6,755.000 5,407.000 2.150 11,625.05 0070 0672 REFL PAV MRKR TY I-R EA 392.000 252.000 3.000 756.00 0075 0672 REFL PAV MRKR TY II-A-A EA 28,029.000 23,783.000 2.030 48,279.49 0080 0672 REFL PAV MRKR TY II-C-R EA 3,050.000 3,448.000 2.150 7,413.20 0 SUBTOTAL BID ITEMS $ 71,327.54 0 TOTAL AMOUNT WORK DONE RAISED PAVEMENT MARKERS $ 71,327.54 0 TOTAL AMOUNT WORK DONE CONTROL 6251-47-001 $ 71,327.54 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1131001 MGR.NO. 770 PAGE 001 CONT 6251 SEC 47 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 625147001 HWY SH0031 2709 W FRONT ST TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 82,442.42 REPORT DATE 05/06/2013 08.22.13 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD MAR 11,2013 TO MAR 28,2013 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADS IN THE ATHENS MTCE. 0 SECTION IN THE TYLER DISTRICT DATE WORK BEGAN MAR 12, 2013 WORKING DAYS USED 13 PERCENT COMPLETE 100.00 PERCENT TIME USED 48.10 DATE COMPLETED MAR 28 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6251-47-001 RMC - 625147001 10 SH0031 HENDERSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0672 REFL PAV MRKR TY I-A EA 1,494.000 1,479.000 2.200 3,253.80 0672 REFL PAV MRKR TY I-C EA 6,755.000 5,407.000 2.150 11,625.05 0672 REFL PAV MRKR TY I-R EA 392.000 252.000 3.000 756.00 0672 REFL PAV MRKR TY II-A-A EA 28,029.000 23,783.000 2.030 48,279.49 0672 REFL PAV MRKR TY II-C-R EA 3,050.000 3,448.000 2.150 7,413.20 0 SUBTOTAL BID ITEMS $ 71,327.54 0 CONTRACT TOTAL ALL ITEMS $ 71,327.54 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1131001 MGR.NO. 770 PAGE 001 CONT 6251 SEC 47 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 625147001 HWY SH0031 2709 W FRONT ST TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 82,442.42 REPORT DATE 05/06/2013 08.22.13 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD MAR 11,2013 TO MAR 28,2013 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 108 RMC - 625147001 6251-47-001 71,327.54 .00 71,327.54 .00 .00 71,327.54 65,530.01 5,797.53 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 71,327.54 .00 71,327.54 .00 .00 71,327.54 65,530.01 5,797.53 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1131001 MGR.NO. 770 PAGE 001 CONT 6251 SEC 47 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 625147001 HWY SH0031 2709 W FRONT ST TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 82,442.42 REPORT DATE 05/06/2013 08.22.13 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD MAR 11,2013 TO MAR 28,2013 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6251-47-001 RMC - 625147001 10 SH0031 HENDERSON -LIMITS - VARIOUS ROADS IN THE ATHENS MTCE. SECTION IN THE TYLER DISTRICT LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0672 REFL PAV MRKR TY I-C EA 6,755.000 557.000 2.150 1,197.55 75 0672 REFL PAV MRKR TY II-A-A EA 28,029.000 2,266.000 2.030 4,599.98 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 5,797.53 0 TOTAL AMOUNT WORK DONE TO DATE - $ 71,327.54