1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5134020 MGR.NO. 770 PAGE 001 CONT 6255 SEC 72 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625572001 HWY US0069 2709 W FRONT ST TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 482,184.50 REPORT DATE 09/10/2014 16.15.42 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD JUN 21,2013 TO JUL 02,2014 EST NO 015 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 21, 2013 TIME COMPUTED FROM JUN 21, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 255 375 254 121 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 14 1 1 TOTAL DAYS ALLOWED = 255 2 1 WORK COMPLETED AND ACCEPTED DATE WORK COMPLETED 07/02/14 DAYS CHARGED TO DATE = 255 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 590 0 LIQUIDATED DAMAGES 0 DAYS AT $ 590 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 377 255 122 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5134020 MGR.NO. 770 PAGE 001 CONT 6255 SEC 72 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625572001 HWY US0069 2709 W FRONT ST TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 482,184.50 REPORT DATE 09/10/2014 16.15.43 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD JUN 21,2013 TO JUL 02,2014 EST NO 015 & FINAL DIST. 10 COUNTY SMITH CONTROL 6255-72-001 PROJECT RMC - 625572001 HIGHWAY US0069 0LIMITS- VARIOUS ROADWAYS IN THE TYLER DISTRICT 0TYPE OF WORK- PAVEMENT MARKINGS SL& RPM'S 0 0005 PREPARED BY BRADLEY BASSETT 0 0055 SHORTLINE THERMOPLASTIC STRIPING NET LENGTH 0.100 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0666 REFL PAV MRK TY I (W) 4" (DOT)(090MIL) LF 600.000 0.000 1.000 .00 0065 0666 REFL PAV MRK TY I (W) 4" (DOT)(100MIL) LF 600.000 126.000 1.000 126.00 0070 0666 REFL PAV MRK TY I (W) 4" (SLD)(090MIL) LF 3,201.000 972.000 .850 826.20 0075 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 1,884.000 5,856.000 .850 4,977.60 0080 0666 REFL PAV MRK TY I (W) 8" (SLD)(090MIL) LF 10,005.000 8,190.000 .850 6,961.50 0085 0666 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 4,490.000 11,500.000 1.000 11,500.00 0090 0666 REFL PAV MRK TY I (W) 12"(SLD)(090MIL) LF 3,094.000 6,051.000 2.600 15,732.60 0095 0666 REFL PAV MRK TY I (W) 12"(SLD)(100MIL) LF 2,760.000 2,562.000 2.800 7,173.60 0100 0666 REFL PAV MRK TY I (W) 18"(SLD)(090MIL) LF 1,340.000 464.000 4.250 1,972.00 0105 0666 REFL PAV MRK TY I (W) 18"(SLD)(100MIL) LF 708.000 673.000 4.500 3,028.50 0110 0666 REFL PAV MRK TY I (W) 24"(SLD)(090MIL) LF 14,844.000 16,437.000 4.100 67,391.70 0115 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 6,298.000 11,457.000 4.650 53,275.05 0120 0666 REFL PAV MRK TY I (W) (ARROW) (090MIL) EA 399.000 247.000 85.000 20,995.00 0125 0666 REFL PAV MRK TY I (W) (ARROW) (100MIL) EA 193.000 185.000 95.000 17,575.00 0130 0666 REFL PAV MRK TY I(W)(DBL 1 ARROW)(090MIL) EA 16.000 23.000 150.000 3,450.00 0135 0666 REFL PAV MRK TY I(W)(DBL ARROW)(100MIL) EA 25.000 16.000 150.000 2,400.00 0140 0666 REFL PAV MRK TY I(W)(RR XING) (090MIL) EA 8.000 2.000 395.000 790.00 0145 0666 REFL PAV MRK TY I(W)(RR XING) (100MIL) EA 11.000 4.000 415.000 1,660.00 0150 0666 REFL PAV MRK TY I(W)(UTURN ARW)(090MIL) EA 2.000 0.000 215.000 .00 0155 0666 REFL PAV MRK TY I (W) (WORD) (090MIL) EA 416.000 129.000 115.000 14,835.00 0160 0666 REFL PAV MRK TY I (W) (WORD) (100MIL) EA 92.000 190.000 125.000 23,750.00 0165 0666 REFL PAV MRK TY I (Y) 4" (SLD)(090MIL) LF 15,770.000 0.000 .850 .00 0170 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 930.000 5,948.000 1.000 5,948.00 0173 0666*REFL PAV MRK TY I (Y) 12"(SLD)(100MIL) LF 2,000.000 1,329.000 2.800 3,721.20 0175 0666 REFL PAV MRK TY I (Y) 24"(SLD)(090MIL) LF 808.000 979.000 4.850 4,748.15 0180 0666 REFL PAV MRK TY I (Y) 24"(SLD)(100MIL) LF 2,690.000 591.000 4.850 2,866.35 0185 0666 PAVEMENT SEALER 4" LF 584.000 7,596.000 .200 1,519.20 0190 0666 PAVEMENT SEALER 8" LF 1,530.000 4,437.000 .300 1,331.10 0195 0666 PAVEMENT SEALER 24" LF 1,500.000 3,123.000 1.250 3,903.75 0200 0666 PAVEMENT SEALER (ARROW) EA 64.000 45.000 20.000 900.00 0205 0666 PAVEMENT SEALER (WORD) EA 26.000 25.000 30.000 750.00 0210 0666 PAVEMENT SEALER (DBL ARROW) EA 15.000 10.000 40.000 400.00 0215 0666 PAVEMENT SEALER (YLD TRI) EA 319.000 47.000 10.000 470.00 0220 0668 PRE PM TY C(ACC PRK)(BL&WH)LG W/BORDER EA 16.000 1.000 140.000 140.00 0225 0668 PREFAB PAV MRK TY C (W) (18")(YLD TRI) EA 180.000 31.000 21.000 651.00 0230 0668 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 635.000 278.000 23.000 6,394.00 0235 0672 REFL PAV MRKR TY I-A EA 7,323.000 2,547.000 2.900 7,386.30 0240 0672 REFL PAV MRKR TY I-C EA 5,521.000 5,335.000 2.900 15,471.50 0245 0672 REFL PAV MRKR TY I-R EA 600.000 252.000 4.000 1,008.00 0250 0672 REFL PAV MRKR TY II-A-A EA 43,574.000 28,578.000 2.050 58,584.90 0255 0672 REFL PAV MRKR TY II-C-R EA 1,825.000 1,801.000 3.000 5,403.00 0260 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 2,212.000 9,701.000 .300 2,910.30 0265 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 1,000.000 4,600.000 .600 2,760.00 0270 0677 ELIM EXT PAV MRK & MRKS (12") LF 220.000 600.000 1.000 600.00 0275 0677 ELIM EXT PAV MRK & MRKS (18") LF 200.000 65.000 1.000 65.00 0280 0677 ELIM EXT PAV MRK & MRKS (24") LF 4,250.000 2,387.000 1.500 3,580.50 1 0285 0677 ELIM EXT PAV MRK & MRKS (ARROW) EA 66.000 52.000 15.000 780.00 0290 0677 ELIM EXT PAV MRK & MRKS (DBL ARROW) EA 46.000 11.000 25.000 275.00 0295 0677 ELIM EXT PAV MRK & MRKS (RR XING) EA 7.000 2.000 140.000 280.00 0300 0677 ELIM EXT PAV MRK & MRKS (WORD) EA 21.000 22.000 30.000 660.00 0305 0677 ELIM EXT PAV MRK & MRKS (18")(YLD TRI) EA 100.000 19.000 5.000 95.00 0310 0677 ELIM EXT PAV MRK & MRKS (36")(YLD TRI) EA 286.000 30.000 10.000 300.00 0315 0678 PAV SURF PREP FOR MRK (24") LF 750.000 0.000 2.000 .00 0320 0678 PAV SURF PREP FOR MRK (SYMBOL) EA 8.000 0.000 35.000 .00 0325 0678 PAV SURF PREP FOR MRK (18") (YLD TRI) EA 80.000 0.000 20.000 .00 0330 0678 PAV SURF PREP FOR MRK (36") (YLD TRI) EA 325.000 0.000 30.000 .00 0 SUBTOTAL BID ITEMS $ 392,322.00 0 TOTAL AMOUNT WORK DONE SHORTLINE THERMOPLASTIC STRIPING $ 392,322.00 0 TOTAL AMOUNT WORK DONE CONTROL 6255-72-001 $ 392,322.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5134020 MGR.NO. 770 PAGE 001 CONT 6255 SEC 72 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625572001 HWY US0069 2709 W FRONT ST TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 482,184.50 REPORT DATE 09/10/2014 16.15.43 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD JUN 21,2013 TO JUL 02,2014 EST NO 015 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS 0 IN THE TYLER DISTRICT DATE WORK BEGAN JUN 21, 2013 WORKING DAYS USED 255 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED JUL 2 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6255-72-001 RMC - 625572001 10 US0069 SMITH - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0666 REFL PAV MRK TY I (W) 4" (DOT)(100MIL) LF 600.000 126.000 1.000 126.00 0666 REFL PAV MRK TY I (W) 4" (SLD)(090MIL) LF 3,201.000 972.000 .850 826.20 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 1,884.000 5,856.000 .850 4,977.60 0666 REFL PAV MRK TY I (W) 8" (SLD)(090MIL) LF 10,005.000 8,190.000 .850 6,961.50 0666 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 4,490.000 11,500.000 1.000 11,500.00 0666 REFL PAV MRK TY I (W) 12"(SLD)(090MIL) LF 3,094.000 6,051.000 2.600 15,732.60 0666 REFL PAV MRK TY I (W) 12"(SLD)(100MIL) LF 2,760.000 2,562.000 2.800 7,173.60 0666 REFL PAV MRK TY I (W) 18"(SLD)(090MIL) LF 1,340.000 464.000 4.250 1,972.00 0666 REFL PAV MRK TY I (W) 18"(SLD)(100MIL) LF 708.000 673.000 4.500 3,028.50 0666 REFL PAV MRK TY I (W) 24"(SLD)(090MIL) LF 14,844.000 16,437.000 4.100 67,391.70 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 6,298.000 11,457.000 4.650 53,275.05 0666 REFL PAV MRK TY I (W) (ARROW) (090MIL) EA 399.000 247.000 85.000 20,995.00 0666 REFL PAV MRK TY I (W) 1 (ARROW) (100MIL) EA 193.000 185.000 95.000 17,575.00 0666 REFL PAV MRK TY I(W)(DBL ARROW)(090MIL) EA 16.000 23.000 150.000 3,450.00 0666 REFL PAV MRK TY I(W)(DBL ARROW)(100MIL) EA 25.000 16.000 150.000 2,400.00 0666 REFL PAV MRK TY I(W)(RR XING) (090MIL) EA 8.000 2.000 395.000 790.00 0666 REFL PAV MRK TY I(W)(RR XING) (100MIL) EA 11.000 4.000 415.000 1,660.00 0666 REFL PAV MRK TY I (W) (WORD) (090MIL) EA 416.000 129.000 115.000 14,835.00 0666 REFL PAV MRK TY I (W) (WORD) (100MIL) EA 92.000 190.000 125.000 23,750.00 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 930.000 5,948.000 1.000 5,948.00 0666 REFL PAV MRK TY I (Y) 24"(SLD)(090MIL) LF 808.000 979.000 4.850 4,748.15 0666 REFL PAV MRK TY I (Y) 24"(SLD)(100MIL) LF 2,690.000 591.000 4.850 2,866.35 0666 PAVEMENT SEALER 4" LF 584.000 7,596.000 .200 1,519.20 0666 PAVEMENT SEALER 8" LF 1,530.000 4,437.000 .300 1,331.10 0666 PAVEMENT SEALER 24" LF 1,500.000 3,123.000 1.250 3,903.75 0666 PAVEMENT SEALER (ARROW) EA 64.000 45.000 20.000 900.00 0666 PAVEMENT SEALER (WORD) EA 26.000 25.000 30.000 750.00 0666 PAVEMENT SEALER (DBL ARROW) EA 15.000 10.000 40.000 400.00 0666 PAVEMENT SEALER (YLD TRI) EA 319.000 47.000 10.000 470.00 0668 PREFAB PAV MRK TY C (W) (18")(YLD TRI) EA 180.000 31.000 21.000 651.00 0668 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 635.000 278.000 23.000 6,394.00 0668 PRE PM TY C(ACC PRK)(BL&WH)LG W/BORDER EA 16.000 1.000 140.000 140.00 0672 REFL PAV MRKR TY I-A EA 7,323.000 2,547.000 2.900 7,386.30 0672 REFL PAV MRKR TY I-C EA 5,521.000 5,335.000 2.900 15,471.50 0672 REFL PAV MRKR TY I-R EA 600.000 252.000 4.000 1,008.00 0672 REFL PAV MRKR TY II-A-A EA 43,574.000 28,578.000 2.050 58,584.90 0672 REFL PAV MRKR TY II-C-R EA 1,825.000 1,801.000 3.000 5,403.00 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 2,212.000 9,701.000 .300 2,910.30 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 1,000.000 4,600.000 .600 2,760.00 0677 ELIM EXT PAV MRK & MRKS (12") LF 220.000 600.000 1.000 600.00 0677 ELIM EXT PAV MRK & MRKS (18") LF 200.000 65.000 1.000 65.00 0677 ELIM EXT PAV MRK & MRKS (24") LF 4,250.000 2,387.000 1.500 3,580.50 0677 ELIM EXT PAV MRK & MRKS (ARROW) EA 66.000 52.000 15.000 780.00 0677 ELIM EXT PAV MRK & MRKS (DBL ARROW) EA 46.000 11.000 25.000 275.00 10677 ELIM EXT PAV MRK & MRKS (RR XING) EA 7.000 2.000 140.000 280.00 0677 ELIM EXT PAV MRK & MRKS (WORD) EA 21.000 22.000 30.000 660.00 0677 ELIM EXT PAV MRK & MRKS (18")(YLD TRI) EA 100.000 19.000 5.000 95.00 0677 ELIM EXT PAV MRK & MRKS (36")(YLD TRI) EA 286.000 30.000 10.000 300.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00666* REFL PAV MRK TY I (Y) 12"(SLD)(100MIL) LF 2,000.000 1,329.000 2.800 3,721.20 0 SUBTOTAL BID ITEMS $ 392,322.00 0 CONTRACT TOTAL ALL ITEMS $ 392,322.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5134020 MGR.NO. 770 PAGE 001 CONT 6255 SEC 72 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625572001 HWY US0069 2709 W FRONT ST TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 482,184.50 REPORT DATE 09/10/2014 16.15.43 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD JUN 21,2013 TO JUL 02,2014 EST NO 015 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 212 RMC - 625572001 6255-72-001 392,322.00 .00 392,322.00 .00 .00 392,322.00 392,322.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 392,322.00 .00 392,322.00 .00 .00 392,322.00 392,322.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5134020 MGR.NO. 770 PAGE 001 CONT 6255 SEC 72 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625572001 HWY US0069 2709 W FRONT ST TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 482,184.50 REPORT DATE 09/10/2014 16.15.44 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD JUN 21,2013 TO JUL 02,2014 EST NO 015 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6255-72-001 RMC - 625572001 10 US0069 SMITH -LIMITS - VARIOUS ROADWAYS IN THE TYLER DISTRICT - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 392,322.00