1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8131004 MGR.NO. 770 PAGE 001 CONT 6257 SEC 63 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625763001 HWY FM0321 2709 W FRONT ST TYLER CNTY ANDERSON DIST 10 CONTRACT PRICE $ 87,920.00 REPORT DATE 03/06/2014 18.27.49 CONTRACTOR KASPARIAN UNDERGROUND, INC. 15588 EST PERIOD OCT 01,2013 TO FEB 19,2014 EST NO 005 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 01, 2013 TIME COMPUTED FROM OCT 01, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 63 123 56 67 BROUGHT FORWARD ADDL DAYS GRANTED = 0 FEB 14 1 1 SATURDAY TOTAL DAYS ALLOWED = 63 2 1 SUNDAY DATE WORK COMPLETED 02/19/14 3 1 DAYS CHARGED TO DATE = 63 4 1 RAIN ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 570 6 1 7 1 RAIN LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 570 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 RAIN 11 1 SNOW CERTIFIED AS CORRECT AND 12 1 SNOW ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 SATURDAY 16 1 SUNDAY ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 WORK COMPLETED AND ACCEPTED - - - - ----- ----- ----- 142 63 79 3 SATURDAY 3 SUNDAY 0 HOLIDAY 3 RAIN 2 SNOW 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8131004 MGR.NO. 770 PAGE 001 CONT 6257 SEC 63 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625763001 HWY FM0321 2709 W FRONT ST TYLER CNTY ANDERSON DIST 10 CONTRACT PRICE $ 87,920.00 REPORT DATE 03/06/2014 18.27.50 CONTRACTOR KASPARIAN UNDERGROUND, INC. 15588 EST PERIOD OCT 01,2013 TO FEB 19,2014 EST NO 005 & FINAL DIST. 10 COUNTY ANDERSON CONTROL 6257-63-001 PROJECT RMC - 625763001 HIGHWAY FM0321 0LIMITS- VARIOUS RADWAYS IN SMITH COUNTY 0TYPE OF WORK- TREE TRIMMING AND BRUSH REMOVAL 0 0005 PREPARED BY BRAD BASSETT 0 0055 TREE TRIMMING NET LENGTH 62.800 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0752 TREE TRIMMING/BRUSH REMOVAL MI 62.800 62.800 1,400.000 87,920.00 0 SUBTOTAL BID ITEMS $ 87,920.00 0 TOTAL AMOUNT WORK DONE TREE TRIMMING $ 87,920.00 0 TOTAL AMOUNT WORK DONE CONTROL 6257-63-001 $ 87,920.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8131004 MGR.NO. 770 PAGE 001 CONT 6257 SEC 63 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625763001 HWY FM0321 2709 W FRONT ST TYLER CNTY ANDERSON DIST 10 CONTRACT PRICE $ 87,920.00 REPORT DATE 03/06/2014 18.27.50 CONTRACTOR KASPARIAN UNDERGROUND, INC. 15588 EST PERIOD OCT 01,2013 TO FEB 19,2014 EST NO 005 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS RADWAYS 0 IN SMITH COUNTY DATE WORK BEGAN OCT 1 , 2013 WORKING DAYS USED 63 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED FEB 19 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6257-63-001 RMC - 625763001 10 FM0321 ANDERSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0752 TREE TRIMMING/BRUSH REMOVAL MI 62.800 62.800 1,400.000 87,920.00 0 SUBTOTAL BID ITEMS $ 87,920.00 0 CONTRACT TOTAL ALL ITEMS $ 87,920.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8131004 MGR.NO. 770 PAGE 001 CONT 6257 SEC 63 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625763001 HWY FM0321 2709 W FRONT ST TYLER CNTY ANDERSON DIST 10 CONTRACT PRICE $ 87,920.00 REPORT DATE 03/06/2014 18.27.50 CONTRACTOR KASPARIAN UNDERGROUND, INC. 15588 EST PERIOD OCT 01,2013 TO FEB 19,2014 EST NO 005 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 1 RMC - 625763001 6257-63-001 87,920.00 .00 87,920.00 .00 .00 87,920.00 71,960.00 15,960.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 87,920.00 .00 87,920.00 .00 .00 87,920.00 71,960.00 15,960.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8131004 MGR.NO. 770 PAGE 001 CONT 6257 SEC 63 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625763001 HWY FM0321 2709 W FRONT ST TYLER CNTY ANDERSON DIST 10 CONTRACT PRICE $ 87,920.00 REPORT DATE 03/06/2014 18.27.50 CONTRACTOR KASPARIAN UNDERGROUND, INC. 15588 EST PERIOD OCT 01,2013 TO FEB 19,2014 EST NO 005 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6257-63-001 RMC - 625763001 10 FM0321 ANDERSON -LIMITS - VARIOUS RADWAYS IN SMITH COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0752 TREE TRIMMING/BRUSH REMOVAL MI 62.800 11.400 1,400.000 15,960.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 15,960.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 87,920.00