1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7131015 MGR.NO. 770 PAGE 001 CONT 6257 SEC 80 JOB 001 RES ENGR DAVIDSON, MICKEY PROJ SUP - 625780001 HWY US0084 2709 W. FRONT ST. TYLER CNTY ANDERSON DIST 10 CONTRACT PRICE $ 116,294.72 REPORT DATE 08/04/2014 10.13.19 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 011 RUCON, INC. 10168 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 12, 2013 TIME COMPUTED FROM SEP 01, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 303 303 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 14 1 1 TOTAL DAYS ALLOWED = 730 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 334 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 334 334 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7131015 MGR.NO. 770 PAGE 001 CONT 6257 SEC 80 JOB 001 RES ENGR DAVIDSON, MICKEY PROJ SUP - 625780001 HWY US0084 2709 W. FRONT ST. TYLER CNTY ANDERSON DIST 10 CONTRACT PRICE $ 116,294.72 REPORT DATE 08/04/2014 10.13.20 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 011 RUCON, INC. 10168 DIST. 10 COUNTY ANDERSON CONTROL 6257-80-001 PROJECT SUP - 625780001 HIGHWAY US0084 0LIMITS- PALESTINE MAINTENANCE SECTION ANDERSON COUNTY, ETC. 0TYPE OF WORK- LITTER PICK-UP 0 0005 PREPARED BY MICKEY DAVIDSON 0 0055 LITTER PICK UP/DISPOSAL PALESTINE NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL - TRACT (1) CYC 4.000 1.000 3,589.040 3,589.04 0065 0734 LITTER REMOVAL - TRACT (2) CYC 2.000 0.000 2,517.510 .00 0070 0734 LITTER REMOVAL - TRACT (3) CYC 2.000 0.000 9.970 .00 0075 0734 LITTER REMOVAL - TRACT (4) CYC 2.000 0.000 123.310 .00 0080 0734 LITTER REMOVAL - TRACT (5) CYC 2.000 0.000 2,397.580 .00 0085 0734 LITTER REMOVAL - TRACT (6) CYC 2.000 1.000 4,031.540 4,031.54 0090 0734 LITTER REMOVAL - TRACT (7) CYC 4.000 1.000 3,157.280 3,157.28 0095 0734 LITTER REMOVAL - TRACT (8) CYC 4.000 1.000 1,689.230 1,689.23 0100 0734 LITTER REMOVAL - TRACT (9) CYC 6.000 1.000 94.720 94.72 0105 0734 LITTER REMOVAL - TRACT (10) CYC 6.000 1.000 3,942.580 3,942.58 0110 0734 LITTER REMOVAL - TRACT (11) CYC 6.000 1.000 867.480 867.48 0115 0734 LITTER REMOVAL - TRACT (12) CYC 4.000 1.000 1,020.160 1,020.16 0120 0734 LITTER REMOVAL - TRACT (13) CYC 4.000 1.000 1,652.210 1,652.21 0125 0734 LITTER REMOVAL - TRACT (14) CYC 4.000 1.000 276.180 276.18 0130 0734 LITTER REMOVAL - TRACT (15) CYC 4.000 1.000 1,031.080 1,031.08 0135 0734 LITTER REMOVAL - TRACT (16) CYC 4.000 1.000 397.940 397.94 0140 0734 LITTER REMOVAL - TRACT (17) CYC 4.000 1.000 57.010 57.01 0145 0734 LITTER REMOVAL - TRACT (18) CYC 2.000 0.000 3,738.490 .00 0150 0734 LITTER REMOVAL - TRACT (19) CYC 2.000 1.000 1,101.520 1,101.52 0155 0734 LITTER REMOVAL - TRACT (20) CYC 4.000 1.000 761.420 761.42 0160 0734 LITTER REMOVAL(SPOT) AC 300.000 0.000 15.000 .00 0 SUBTOTAL BID ITEMS $ 23,669.39 0 TOTAL AMOUNT WORK DONE LITTER PICK UP/DISPOSAL PALESTINE $ 23,669.39 0 TOTAL AMOUNT WORK DONE CONTROL 6257-80-001 $ 23,669.39 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7131015 MGR.NO. 770 PAGE 001 CONT 6257 SEC 80 JOB 001 RES ENGR DAVIDSON, MICKEY PROJ SUP - 625780001 HWY US0084 2709 W. FRONT ST. TYLER CNTY ANDERSON DIST 10 CONTRACT PRICE $ 116,294.72 REPORT DATE 08/04/2014 10.13.20 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 011 RUCON, INC. 10168 0*********************************************************************************************************************************** -LIMITS - PALESTINE MAINTENANCE SECTION 0 ANDERSON COUNTY, ETC. DATE WORK BEGAN NOV 12, 2013 WORKING DAYS USED 334 PERCENT COMPLETE 20.35 PERCENT TIME USED 45.70 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6257-80-001 SUP - 625780001 10 US0084 ANDERSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL - TRACT (1) CYC 4.000 1.000 3,589.040 3,589.04 0734 LITTER REMOVAL - TRACT (6) CYC 2.000 1.000 4,031.540 4,031.54 0734 LITTER REMOVAL - TRACT (7) CYC 4.000 1.000 3,157.280 3,157.28 0734 LITTER REMOVAL - TRACT (8) CYC 4.000 1.000 1,689.230 1,689.23 0734 LITTER REMOVAL - TRACT (9) CYC 6.000 1.000 94.720 94.72 0734 LITTER REMOVAL - TRACT (10) CYC 6.000 1.000 3,942.580 3,942.58 0734 LITTER REMOVAL - TRACT (11) CYC 6.000 1.000 867.480 867.48 0734 LITTER REMOVAL - TRACT (12) CYC 4.000 1.000 1,020.160 1,020.16 0734 LITTER REMOVAL - TRACT (13) CYC 4.000 1.000 1,652.210 1,652.21 0734 LITTER REMOVAL - TRACT (14) CYC 4.000 1.000 276.180 276.18 0734 LITTER REMOVAL - TRACT (15) CYC 4.000 1.000 1,031.080 1,031.08 0734 LITTER REMOVAL - TRACT (16) CYC 4.000 1.000 397.940 397.94 0734 LITTER REMOVAL - TRACT (17) CYC 4.000 1.000 57.010 57.01 0734 LITTER REMOVAL - TRACT (19) CYC 2.000 1.000 1,101.520 1,101.52 0734 LITTER REMOVAL - TRACT (20) CYC 4.000 1.000 761.420 761.42 0 SUBTOTAL BID ITEMS $ 23,669.39 0 CONTRACT TOTAL ALL ITEMS $ 23,669.39 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7131015 MGR.NO. 770 PAGE 001 CONT 6257 SEC 80 JOB 001 RES ENGR DAVIDSON, MICKEY PROJ SUP - 625780001 HWY US0084 2709 W. FRONT ST. TYLER CNTY ANDERSON DIST 10 CONTRACT PRICE $ 116,294.72 REPORT DATE 08/04/2014 10.13.20 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 011 RUCON, INC. 10168 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 1 SUP - 625780001 6257-80-001 23,669.39 .00 23,669.39 .00 .00 23,669.39 23,669.39 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 23,669.39 .00 23,669.39 .00 .00 23,669.39 23,669.39 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7131015 MGR.NO. 770 PAGE 001 CONT 6257 SEC 80 JOB 001 RES ENGR DAVIDSON, MICKEY PROJ SUP - 625780001 HWY US0084 2709 W. FRONT ST. TYLER CNTY ANDERSON DIST 10 CONTRACT PRICE $ 116,294.72 REPORT DATE 08/04/2014 10.13.20 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 011 RUCON, INC. 10168 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6257-80-001 SUP - 625780001 10 US0084 ANDERSON -LIMITS - PALESTINE MAINTENANCE SECTION ANDERSON COUNTY, ETC. - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 23,669.39