1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2124014 MGR.NO. 010 PAGE 001 CONT 6239 SEC 05 JOB 001 RES ENGR ROHMER, DAVID PROJ RMC - 623905001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 1,045,900.00 REPORT DATE 03/06/2013 15.33.48 CONTRACTOR DOUBLE A CONTRACTING, L.P. 12178 EST PERIOD APR 16,2012 TO FEB 28,2013 EST NO 011 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 16, 2012 TIME COMPUTED FROM APR 19, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 291 283 8 BROUGHT FORWARD ADDL DAYS GRANTED = 0 FEB 13 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 02/28/13 3 1 DAYS CHARGED TO DATE = 310 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 685 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 685 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 WORK COMPLETED AND ACCEPTED - ----- ----- ----- 319 310 9 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2124014 MGR.NO. 010 PAGE 001 CONT 6239 SEC 05 JOB 001 RES ENGR ROHMER, DAVID PROJ RMC - 623905001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 1,045,900.00 REPORT DATE 03/06/2013 15.33.49 CONTRACTOR DOUBLE A CONTRACTING, L.P. 12178 EST PERIOD APR 16,2012 TO FEB 28,2013 EST NO 011 & FINAL DIST. 03 COUNTY WICHITA CONTROL 6239-05-001 PROJECT RMC - 623905001 HIGHWAY IH0044 0LIMITS- VARIOUS ROADWAYS DISTRICT WIDE 0TYPE OF WORK- ON-CALL PAVEMENT & RPM 0 0005 PREPARED BY LARRY TEGTMEYER, PE 0 0055 ON-CALL PAVEMENT MRKS & RPM NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0666 REFL PAV MRK TY I (W) 4" (BRK)(060MIL) LF 50,000.000 49,918.000 .250 12,479.50 0065 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 100,000.000 8,880.000 .330 2,930.40 0070 0666 REFL PAV MRK TY I (W) 4" (DOT)(100MIL) LF 1,000.000 410.000 .800 328.00 0075 0666 REFL PAV MRK TY I (W) 4" (SLD)(060MIL) LF 750,000.000 1,041,269.000 .240 249,904.56 0080 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 250,000.000 717,742.000 .320 229,677.44 0085 0666 REFL PAV MRK TY I (W) 8" (SLD)(060MIL) LF 30,000.000 16,791.000 .500 8,395.50 0090 0666 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 7,500.000 4,766.000 .800 3,812.80 0095 0666 REFL PAV MRK TY I (W) 12"(LNDP)(100MIL) LF 300.000 0.000 2.500 .00 0100 0666 REFL PAV MRK TY I (W) 12"(SLD)(100MIL) LF 200.000 0.000 2.500 .00 0105 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 200.000 0.000 6.000 .00 0110 0666 REFL PAV MRK TY I (Y) 4" (BRK)(060MIL) LF 100,000.000 103,441.000 .240 24,825.84 0115 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 150,000.000 90,631.000 .320 29,001.92 0120 0666 REFL PAV MRK TY I (Y) 4" (SLD)(060MIL) LF 750,000.000 781,746.000 .240 187,619.04 0125 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 750,000.000 637,739.000 .320 204,076.48 0130 0666 REFL PAV MRK TY I (Y) 8" 1 (SLD)(060MIL) LF 500.000 0.000 .800 .00 0135 0666 REFL PAV MRK TY I (Y) 24"(SLD)(100MIL) LF 100.000 0.000 6.000 .00 0140 0666 PAVEMENT SEALER 4" LF 2,500.000 0.000 .300 .00 0145 0666 PAVEMENT SEALER 8" LF 2,500.000 0.000 .300 .00 0150 0666 PAVEMENT SEALER 12" LF 100.000 0.000 1.000 .00 0155 0666 PAVEMENT SEALER 24" LF 100.000 0.000 2.000 .00 0160 0666 PAVEMENT SEALER (ARROW) EA 10.000 11.000 30.000 330.00 0165 0666 PAVEMENT SEALER (WORD) EA 20.000 17.000 30.000 510.00 0170 0666 PAVEMENT SEALER (DBL ARROW) EA 1.000 0.000 50.000 .00 0175 0666 PAVEMENT SEALER RR XING EA 8.000 0.000 100.000 .00 0180 0668 PREFAB PAV MRK TY C (W) (12") (SLD) LF 100.000 85.000 5.000 425.00 0185 0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 3,000.000 523.000 11.000 5,753.00 0190 0668 PREFAB PAV MRK TY C (W) (ARROW) EA 10.000 19.000 180.000 3,420.00 0195 0668 PREFAB PAV MRK TY C (W) (DBL ARROW) EA 1.000 4.000 200.000 800.00 0200 0668 PREFAB PAV MRK TY C (W) (RR XING) EA 8.000 4.000 350.000 1,400.00 0205 0668 PREFAB PAV MRK TY C (W) (WORD) EA 20.000 26.000 180.000 4,680.00 0210 0668 PREFAB PAV MRK TY C (Y) (24") (SLD) LF 100.000 738.000 11.000 8,118.00 0215 0672 REFL PAV MRKR TY I-A EA 100.000 0.000 4.000 .00 0220 0672 REFL PAV MRKR TY I-C EA 1,000.000 447.000 3.000 1,341.00 0225 0672 REFL PAV MRKR TY II-A-A EA 50,000.000 20,047.000 2.500 50,117.50 0230 0672 REFL PAV MRKR TY II-C-R EA 15,000.000 6,439.000 3.000 19,317.00 0235 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 1,000.000 416.000 .500 208.00 0240 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 100.000 140.000 1.000 140.00 0245 0677 ELIM EXT PAV MRK & MRKS (12") LF 100.000 15.000 2.000 30.00 0250 0677 ELIM EXT PAV MRK & MRKS (24") LF 100.000 0.000 4.000 .00 0255 0677 ELIM EXT PAV MRK & MRKS (ARROW) EA 10.000 2.000 60.000 120.00 0260 0677 ELIM EXT PAV MRK & MRKS (WORD) EA 20.000 0.000 70.000 .00 0 SUBTOTAL BID ITEMS $ 1,049,760.98 0 TOTAL AMOUNT WORK DONE ON-CALL PAVEMENT MRKS & RPM $ 1,049,760.98 0 TOTAL AMOUNT WORK DONE CONTROL 6239-05-001 $ 1,049,760.98 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2124014 MGR.NO. 010 PAGE 001 CONT 6239 SEC 05 JOB 001 RES ENGR ROHMER, DAVID PROJ RMC - 623905001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 1,045,900.00 REPORT DATE 03/06/2013 15.33.50 CONTRACTOR DOUBLE A CONTRACTING, L.P. 12178 EST PERIOD APR 16,2012 TO FEB 28,2013 EST NO 011 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS 0 DISTRICT WIDE DATE WORK BEGAN APR 16, 2012 WORKING DAYS USED 310 PERCENT COMPLETE 100.00 PERCENT TIME USED 84.90 DATE COMPLETED FEB 28 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6239-05-001 RMC - 623905001 03 IH0044 WICHITA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0666 REFL PAV MRK TY I (W) 4" (BRK)(060MIL) LF 50,000.000 49,918.000 .250 12,479.50 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 100,000.000 8,880.000 .330 2,930.40 0666 REFL PAV MRK TY I (W) 4" (DOT)(100MIL) LF 1,000.000 410.000 .800 328.00 0666 REFL PAV MRK TY I (W) 4" (SLD)(060MIL) LF 750,000.000 1,041,269.000 .240 249,904.56 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 250,000.000 717,742.000 .320 229,677.44 0666 REFL PAV MRK TY I (W) 8" (SLD)(060MIL) LF 30,000.000 16,791.000 .500 8,395.50 0666 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 7,500.000 4,766.000 .800 3,812.80 0666 REFL PAV MRK TY I (Y) 4" (BRK)(060MIL) LF 100,000.000 103,441.000 .240 24,825.84 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 150,000.000 90,631.000 .320 29,001.92 0666 REFL PAV MRK TY I (Y) 4" (SLD)(060MIL) LF 750,000.000 781,746.000 .240 187,619.04 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 750,000.000 637,739.000 .320 204,076.48 0666 PAVEMENT SEALER (ARROW) EA 10.000 11.000 30.000 330.00 0666 PAVEMENT SEALER (WORD) EA 20.000 17.000 30.000 510.00 0668 PREFAB PAV MRK TY C (W) 1 (12") (SLD) LF 100.000 85.000 5.000 425.00 0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 3,000.000 523.000 11.000 5,753.00 0668 PREFAB PAV MRK TY C (W) (ARROW) EA 10.000 19.000 180.000 3,420.00 0668 PREFAB PAV MRK TY C (W) (DBL ARROW) EA 1.000 4.000 200.000 800.00 0668 PREFAB PAV MRK TY C (W) (RR XING) EA 8.000 4.000 350.000 1,400.00 0668 PREFAB PAV MRK TY C (W) (WORD) EA 20.000 26.000 180.000 4,680.00 0668 PREFAB PAV MRK TY C (Y) (24") (SLD) LF 100.000 738.000 11.000 8,118.00 0672 REFL PAV MRKR TY I-C EA 1,000.000 447.000 3.000 1,341.00 0672 REFL PAV MRKR TY II-A-A EA 50,000.000 20,047.000 2.500 50,117.50 0672 REFL PAV MRKR TY II-C-R EA 15,000.000 6,439.000 3.000 19,317.00 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 1,000.000 416.000 .500 208.00 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 100.000 140.000 1.000 140.00 0677 ELIM EXT PAV MRK & MRKS (12") LF 100.000 15.000 2.000 30.00 0677 ELIM EXT PAV MRK & MRKS (ARROW) EA 10.000 2.000 60.000 120.00 0 SUBTOTAL BID ITEMS $ 1,049,760.98 0 CONTRACT TOTAL ALL ITEMS $ 1,049,760.98 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2124014 MGR.NO. 010 PAGE 001 CONT 6239 SEC 05 JOB 001 RES ENGR ROHMER, DAVID PROJ RMC - 623905001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 1,045,900.00 REPORT DATE 03/06/2013 15.33.50 CONTRACTOR DOUBLE A CONTRACTING, L.P. 12178 EST PERIOD APR 16,2012 TO FEB 28,2013 EST NO 011 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 243 RMC - 623905001 6239-05-001 1,049,760.98 .00 1,049,760.98 .00 .00 1,049,760.98 994,599.38 55,161.60 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 1,049,760.98 .00 1,049,760.98 .00 .00 1,049,760.98 994,599.38 55,161.60 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2124014 MGR.NO. 010 PAGE 001 CONT 6239 SEC 05 JOB 001 RES ENGR ROHMER, DAVID PROJ RMC - 623905001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 1,045,900.00 REPORT DATE 03/06/2013 15.33.50 CONTRACTOR DOUBLE A CONTRACTING, L.P. 12178 EST PERIOD APR 16,2012 TO FEB 28,2013 EST NO 011 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6239-05-001 RMC - 623905001 03 IH0044 WICHITA -LIMITS - VARIOUS ROADWAYS DISTRICT WIDE LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 80 0666 REFL PAV MRK TY I (W) 4" LF 250,000.000 172,380.000 0.320 55,161.60 (SLD)(100MIL) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 55,161.60 0 TOTAL AMOUNT WORK DONE TO DATE - $ 1,049,760.98