1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4134001 MGR.NO. 010 PAGE 001 CONT 6251 SEC 04 JOB 001 RES ENGR HALLUM, MIKE PROJ RMC - 625104001 HWY FM0922 1601 SOUTHWEST PKWY WICHI CNTY COOKE DIST 03 CONTRACT PRICE $ 479,862.00 REPORT DATE 09/09/2013 10.34.34 CONTRACTOR JAGOE-PUBLIC COMPANY 1003 EST PERIOD JUL 01,2013 TO SEP 01,2013 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 01, 2013 TIME COMPUTED FROM JUL 08, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 45 62 29 33 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 13 1 1 WORK COMPLETED AND ACCEPTED TOTAL DAYS ALLOWED = 45 DATE WORK COMPLETED 09/01/13 DAYS CHARGED TO DATE = 29 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 590 0 LIQUIDATED DAMAGES 0 DAYS AT $ 590 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 63 29 34 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4134001 MGR.NO. 010 PAGE 001 CONT 6251 SEC 04 JOB 001 RES ENGR HALLUM, MIKE PROJ RMC - 625104001 HWY FM0922 1601 SOUTHWEST PKWY WICHI CNTY COOKE DIST 03 CONTRACT PRICE $ 479,862.00 REPORT DATE 09/09/2013 10.34.35 CONTRACTOR JAGOE-PUBLIC COMPANY 1003 EST PERIOD JUL 01,2013 TO SEP 01,2013 EST NO 003 & FINAL DIST. 03 COUNTY COOKE CONTROL 6251-04-001 PROJECT RMC - 625104001 HIGHWAY FM0922 0LIMITS- MONTAGUE COUNTY LINE WEST OF ERA 0TYPE OF WORK- SPOT FULL DEPTH REPAIR 0 0005 PREPRAED BY LARRY TEGTMEYER PE 0 0055 SPOT FULL DEPTH REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 12,470.000 14,010.000 33.000 462,330.00 0065 0500 MOBILIZATION LS 1.000 1.000 45,000.000 45,000.00 0070 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 7,500.000 22,500.00 0075 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 852.000 852.000 1.000 852.00 0 SUBTOTAL BID ITEMS $ 530,682.00 0 TOTAL AMOUNT WORK DONE SPOT FULL DEPTH REPAIR $ 530,682.00 0 TOTAL AMOUNT WORK DONE CONTROL 6251-04-001 $ 530,682.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4134001 MGR.NO. 010 PAGE 001 CONT 6251 SEC 04 JOB 001 RES ENGR HALLUM, MIKE PROJ RMC - 625104001 HWY FM0922 1601 SOUTHWEST PKWY WICHI CNTY COOKE DIST 03 CONTRACT PRICE $ 479,862.00 REPORT DATE 09/09/2013 10.34.35 CONTRACTOR JAGOE-PUBLIC COMPANY 1003 EST PERIOD JUL 01,2013 TO SEP 01,2013 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - MONTAGUE COUNTY LINE 0 WEST OF ERA DATE WORK BEGAN JUL 1 , 2013 WORKING DAYS USED 29 PERCENT COMPLETE 100.00 PERCENT TIME USED 64.40 DATE COMPLETED SEP 1 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6251-04-001 RMC - 625104001 03 FM0922 COOKE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 12,470.000 14,010.000 33.000 462,330.00 0500 MOBILIZATION LS 1.000 1.000 45,000.000 45,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 7,500.000 22,500.00 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 852.000 852.000 1.000 852.00 0 SUBTOTAL BID ITEMS $ 530,682.00 0 CONTRACT TOTAL ALL ITEMS $ 530,682.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4134001 MGR.NO. 010 PAGE 001 CONT 6251 SEC 04 JOB 001 RES ENGR HALLUM, MIKE PROJ RMC - 625104001 HWY FM0922 1601 SOUTHWEST PKWY WICHI CNTY COOKE DIST 03 CONTRACT PRICE $ 479,862.00 REPORT DATE 09/09/2013 10.34.35 CONTRACTOR JAGOE-PUBLIC COMPANY 1003 EST PERIOD JUL 01,2013 TO SEP 01,2013 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 49 RMC - 625104001 6251-04-001 530,682.00 .00 530,682.00 .00 .00 530,682.00 530,682.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 530,682.00 .00 530,682.00 .00 .00 530,682.00 530,682.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4134001 MGR.NO. 010 PAGE 001 CONT 6251 SEC 04 JOB 001 RES ENGR HALLUM, MIKE PROJ RMC - 625104001 HWY FM0922 1601 SOUTHWEST PKWY WICHI CNTY COOKE DIST 03 CONTRACT PRICE $ 479,862.00 REPORT DATE 09/09/2013 10.34.35 CONTRACTOR JAGOE-PUBLIC COMPANY 1003 EST PERIOD JUL 01,2013 TO SEP 01,2013 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6251-04-001 RMC - 625104001 03 FM0922 COOKE -LIMITS - MONTAGUE COUNTY LINE WEST OF ERA - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 530,682.00