1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2130303 MGR.NO. 010 PAGE 001 CONT 6254 SEC 06 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625406001 HWY US0287 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 93,900.00 REPORT DATE 01/28/2014 08.10.22 CONTRACTOR BIG STATE MAINTENANCE, INC. 12839 EST PERIOD JUN 19,2013 TO JAN 27,2014 EST NO 004 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 19, 2013 TIME COMPUTED FROM JUN 25, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 50 74 19 55 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JAN 14 1 1 HOLIDAY TOTAL DAYS ALLOWED = 50 2 1 TIME SUSP - LETTER SUBMITTED DATE WORK COMPLETED 01/27/14 3 1 TIME SUSP - LETTER SUBMITTED DAYS CHARGED TO DATE = 19 4 1 TIME SUSP - LETTER SUBMITTED ASSESSED LIQ DAMAGES = 0 5 1 TIME SUSP - LETTER SUBMITTED LIQ DAMAGE RATE $ 570 6 1 TIME NOT STARTED 7 1 TIME NOT STARTED LIQUIDATED DAMAGES 8 1 TIME NOT STARTED 0 DAYS AT $ 570 PER DAY 9 1 TIME NOT STARTED TOTAL = $ .00 10 1 TIME NOT STARTED 11 1 SATURDAY CERTIFIED AS CORRECT AND 12 1 SUNDAY ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 SATURDAY 19 1 SUNDAY 20 1 21 1 22 1 23 1 TOO COLD 24 1 25 1 SATURDAY 26 1 SUNDAY 27 1 WORK COMPLETED AND ACCEPTED - 0 ----- ----- ----- 101 28 73 3 SATURDAY 3 SUNDAY 1 HOLIDAY 4 TIME SUSP - LETTER SUBMITTED 5 TIME NOT STARTED 1 TOO COLD 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2130303 MGR.NO. 010 PAGE 001 CONT 6254 SEC 06 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625406001 HWY US0287 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 93,900.00 REPORT DATE 01/28/2014 08.10.22 CONTRACTOR BIG STATE MAINTENANCE, INC. 12839 EST PERIOD JUN 19,2013 TO JAN 27,2014 EST NO 004 & FINAL DIST. 03 COUNTY WICHITA CONTROL 6254-06-001 PROJECT RMC - 625406001 HIGHWAY US0287 0LIMITS- VARIOUS ROADWAYS IN WICHITA AND WILBARGER COUNTY 0TYPE OF WORK- RIGHT OF WAY MOWING 0 0005 PREPARED BY LARRY TEGTMEYER PE 0 0055 RIGHT OF WAY MOWING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 STRIP MOWING AC 750.000 750.000 20.000 15,000.00 0065 0730 FULL-WIDTH MOWING AC 3,945.000 3,945.000 20.000 78,900.00 0 SUBTOTAL BID ITEMS $ 93,900.00 0 TOTAL AMOUNT WORK DONE RIGHT OF WAY MOWING $ 93,900.00 0 TOTAL AMOUNT WORK DONE CONTROL 6254-06-001 $ 93,900.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2130303 MGR.NO. 010 PAGE 001 CONT 6254 SEC 06 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625406001 HWY US0287 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 93,900.00 REPORT DATE 01/28/2014 08.10.22 CONTRACTOR BIG STATE MAINTENANCE, INC. 12839 EST PERIOD JUN 19,2013 TO JAN 27,2014 EST NO 004 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN WICHITA 0 AND WILBARGER COUNTY DATE WORK BEGAN JUN 19, 2013 WORKING DAYS USED 19 PERCENT COMPLETE 100.00 PERCENT TIME USED 38.00 DATE COMPLETED JAN 27 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6254-06-001 RMC - 625406001 03 US0287 WICHITA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 STRIP MOWING AC 750.000 750.000 20.000 15,000.00 0730 FULL-WIDTH MOWING AC 3,945.000 3,945.000 20.000 78,900.00 0 SUBTOTAL BID ITEMS $ 93,900.00 0 CONTRACT TOTAL ALL ITEMS $ 93,900.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2130303 MGR.NO. 010 PAGE 001 CONT 6254 SEC 06 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625406001 HWY US0287 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 93,900.00 REPORT DATE 01/28/2014 08.10.22 CONTRACTOR BIG STATE MAINTENANCE, INC. 12839 EST PERIOD JUN 19,2013 TO JAN 27,2014 EST NO 004 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 243 RMC - 625406001 6254-06-001 93,900.00 .00 93,900.00 .00 .00 93,900.00 54,560.00 39,340.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 93,900.00 .00 93,900.00 .00 .00 93,900.00 54,560.00 39,340.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2130303 MGR.NO. 010 PAGE 001 CONT 6254 SEC 06 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625406001 HWY US0287 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 93,900.00 REPORT DATE 01/28/2014 08.10.22 CONTRACTOR BIG STATE MAINTENANCE, INC. 12839 EST PERIOD JUN 19,2013 TO JAN 27,2014 EST NO 004 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6254-06-001 RMC - 625406001 03 US0287 WICHITA -LIMITS - VARIOUS ROADWAYS IN WICHITA AND WILBARGER COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 STRIP MOWING AC 750.000 75.000 20.000 1,500.00 65 0730 FULL-WIDTH MOWING AC 3,945.000 1,892.000 20.000 37,840.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 39,340.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 93,900.00