1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1114027 MGR.NO. 002 PAGE 001 CONT 6220 SEC 46 JOB 001 RES ENGR BOLOM, JOCELYN PROJ RMC - 622046001 HWY US0087 403 HUCK ST YOAKUM CNTY DEWITT DIST 13 CONTRACT PRICE $ 264,798.00 REPORT DATE 01/04/2013 14.42.50 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUL 25,2011 TO DEC 12,2012 EST NO 019 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 25, 2011 TIME COMPUTED FROM JUL 25, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 80 495 90 405 BROUGHT FORWARD ADDL DAYS GRANTED = 19 DEC 12 1 1 TOTAL DAYS ALLOWED = 99 2 1 SUNDAY DATE WORK COMPLETED 12/12/12 3 1 DAYS CHARGED TO DATE = 99 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 500 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 WORK COMPLETED AND ACCEPTED ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 507 99 408 0 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1114027 MGR.NO. 002 PAGE 001 CONT 6220 SEC 46 JOB 001 RES ENGR BOLOM, JOCELYN PROJ RMC - 622046001 HWY US0087 403 HUCK ST YOAKUM CNTY DEWITT DIST 13 CONTRACT PRICE $ 264,798.00 REPORT DATE 01/04/2013 14.42.51 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUL 25,2011 TO DEC 12,2012 EST NO 019 & FINAL DIST. 13 COUNTY DEWITT CONTROL 6220-46-001 PROJECT RMC - 622046001 HIGHWAY US0087 0LIMITS- VARIOUS LIMITS . 0TYPE OF WORK- MOWING HIGHWAY RIGHTS OF WAY 0 0050 MOWING HIGHWAY RIGHTS OF WAY NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY DISTRICT MAINTENANCE 11/2010 0 0075 0730 FULL-WIDTH MOWING AC 11,268.000 9,809.000 23.500 230,511.50 0076 0730*STRIP MOWING AC 600.000 600.000 25.000 15,000.00 0100 9001*LIQUIDATED DAMAGES DAY 1.000 24.000 -500.000 -12,000.00 0 SUBTOTAL BID ITEMS $ 233,511.50 0 TOTAL AMOUNT WORK DONE MOWING HIGHWAY RIGHTS OF WAY $ 233,511.50 0 TOTAL AMOUNT WORK DONE CONTROL 6220-46-001 $ 233,511.50 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1114027 MGR.NO. 002 PAGE 001 CONT 6220 SEC 46 JOB 001 RES ENGR BOLOM, JOCELYN PROJ RMC - 622046001 HWY US0087 403 HUCK ST YOAKUM CNTY DEWITT DIST 13 CONTRACT PRICE $ 264,798.00 REPORT DATE 01/04/2013 14.42.52 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUL 25,2011 TO DEC 12,2012 EST NO 019 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LIMITS 0 . DATE WORK BEGAN JUL 25, 2011 WORKING DAYS USED 99 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED DEC 12 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6220-46-001 RMC - 622046001 13 US0087 DEWITT - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 11,268.000 9,809.000 23.500 230,511.50 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00730* STRIP MOWING AC 600.000 600.000 25.000 15,000.00 9001* LIQUIDATED DAMAGES DAY 1.000 24.000 -500.000 -12,000.00 0 SUBTOTAL BID ITEMS $ 233,511.50 0 CONTRACT TOTAL ALL ITEMS $ 233,511.50 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1114027 MGR.NO. 002 PAGE 001 CONT 6220 SEC 46 JOB 001 RES ENGR BOLOM, JOCELYN PROJ RMC - 622046001 HWY US0087 403 HUCK ST YOAKUM CNTY DEWITT DIST 13 CONTRACT PRICE $ 264,798.00 REPORT DATE 01/04/2013 14.42.52 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUL 25,2011 TO DEC 12,2012 EST NO 019 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 62 RMC - 622046001 6220-46-001 233,511.50 .00 233,511.50 .00 .00 233,511.50 209,400.50 24,111.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 233,511.50 .00 233,511.50 .00 .00 233,511.50 209,400.50 24,111.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1114027 MGR.NO. 002 PAGE 001 CONT 6220 SEC 46 JOB 001 RES ENGR BOLOM, JOCELYN PROJ RMC - 622046001 HWY US0087 403 HUCK ST YOAKUM CNTY DEWITT DIST 13 CONTRACT PRICE $ 264,798.00 REPORT DATE 01/04/2013 14.42.52 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUL 25,2011 TO DEC 12,2012 EST NO 019 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6220-46-001 RMC - 622046001 13 US0087 DEWITT -LIMITS - VARIOUS LIMITS . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 75 0730 FULL-WIDTH MOWING AC 11,268.000 1,026.000 23.500 24,111.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 24,111.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 233,511.50