Letting Schedule for December, 2013 (FY 2014)

Last Update: Monday, November 17, 2014
December, 2013 (FY 2014) (see Links)
SEP 2013 | OCT 2013 | NOV 2013 | DEC 2013 | JAN 2014 | FEB 2014 | MAR 2014 | APR 2014 | MAY 2014 | JUN 2014 | JUL 2014 | AUG 2014
CCSJ County/
District
Highway Let Status Contract
Cost
Fund
Cat
Description
0914-18-094 Bastrop/
Austin
VA Actual $2,020,306 3 DOWNTOWN TRANSIT STOP & BIKE / PED CONNS
0020-11-048 Brewster/
El Paso
US 67 Actual $4,102,196 1 REHABILITATION
0648-03-050 Burleson/
Bryan
FM 60 Actual $10,487,721 3 NEW LOCATION NON - FREEWAY FACILITY CONSISTING OF GRADING,
0047-06-139 Collin/
Dallas
US 75 Actual $47,531,667 3 WIDEN AND RECONSTRUCT 6 LANE FREEWAY TO 8 LANES; IMPROVE 2 / 3
0016-05-107 Comal/
San Antonio
IH 35 Actual $2,452,584 1 RECONFIGURE INTERSECTION
0724-05-008 Coryell/
Waco
FM 1113 Actual $10,327,655 1 SEAL COAT
0442-02-148 Dallas/
Dallas
IH 35E Actual $948,487 1 INSTALL HIGH MAST ILLUMINATION
0918-00-235 Dallas/
Dallas
VA Actual $311,000 5 NCTCOG - - 511 TRAVELER INFORMATION SYSTEM; DEVELOP 511 SYSTEM
0136-03-044 Delta/
Paris
SH 24 Actual $39,277,747 6 UPGRADING OF EXISTING 2 - LANE TO A 4 - LANE DIVIDED HIGHWAY
0086-08-026 Duval/
Laredo
SH 359 Actual $2,550,396 1 RESURFACE OF EXISTING HIGHWAY
0007-06-086 Eastland/
Brownwood
IH 20 Actual $2,844,514 1 RECONSTRUCT CENTER CONCRETE TRAFFIC BARRIER, LIGHTING,
0924-06-406 El Paso/
El Paso
CS Actual $1,356,724 3 WALK / BIKE PATH
2121-02-151 El Paso/
El Paso
IH 10 Actual $7,584,730 1 AESTHETIC DEVELOPMENT, PHASE II
2552-02-027 El Paso/
El Paso
LP 375 Actual $4,613,077 1 CONSTRUCT AUXILIARY LANES AND INTERSECTION IMPROVEMENTS
0901-32-044 Fannin/
Paris
CR Actual $1,410,706 6 REPLACE BRIDGE AND APPROACHES
0027-12-134 Fort Bend/
Houston
US 59 Actual $696,611 1 INSTALL CTMS
0913-22-042 Gonzales/
Yoakum
CR Actual $232,210 6 REPLACE BRIDGE AND APPROACHES
0065-14-023 Hardin/
Beaumont
BU 96-F Actual $8,159,060 1 SEAL COAT
0720-03-102 Harris/
Houston
SH 249 Actual $39,448,254 3 CONSTRUCT 6 - LANE TOLLWAY WITH BRIDGES AT WILLOW CREEK,
0912-00-441 Harris/
Houston
VA Actual $1,210,348 1 UPGRADE / RECONSTRUCT TRAFFIC SIGNALS
0912-00-443 Harris/
Houston
VA Actual $243,957 1 INSTALL SUPPLEMENTAL CCTV CAMERAS AT CRITICAL LOCAITONS
0016-02-142 Hays/
Austin
IH 35 Actual $682,761 1 MILL, SEAL & OVERLAY SOUTHBOUND FRONTAGE ROAD
0030-06-054 Hemphill/
Amarillo
US 83 Actual $3,516,834 1 REHAB EXISTING ROADWAY
0005-05-103 Howard/
Abilene
IH 20 Actual $624,313 1 UPGRADE SAFETY LIGHTING
0908-12-019 Howard/
Abilene
VA Actual $44,837,999 1 CONSTRUCT NEW RELIEF ROUTE
0902-40-022 Jack/
Fort Worth
CR Actual $364,644 6 REPLACE BRIDGE AND APPROACHES
0876-02-032 Kinney/
Laredo
RM 334 Actual $2,535,441 1 RESURFACE OF EXISTING HIGHWAY
0680-01-014 Lamar/
Paris
FM 196 Actual $858,792 1 REHABILITATION OF EXISTING ROAD
0017-05-093 Medina/
San Antonio
IH 35 Actual $1,339,999 1 WIDEN EXISTING FRONTAGE ROADS TO PROVIDE SHOULDERS
0887-01-036 Midland/
Odessa
FM 307 Actual $6,382,355 1 ROADWAY REHABILITATION
0044-06-071 Montague/
Wichita Falls
US 82 Actual $4,997,746 1 OVERLAY
1610-01-011 Montague/
Wichita Falls
FM 1758 Actual $3,323,150 11 PROVIDE ADDITIONAL PAVED SURFACE WIDTH
0006-02-111 Nolan/
Abilene
IH 20 Actual $423,645 1 INSTALL SAFETY LIGHTING
0247-03-030 Panola/
Atlanta
US 79 Actual $2,402,706 8 RESTORE SECTION AND RESURFACE EXISTING HIGHWAY
0176-05-175 Polk/
Lufkin
US 59 Actual $1,316,346 1 RESURFACE WITH MICROSURFACING
0957-09-016 Presidio/
El Paso
FM 170 Actual $4,573,857 1 SEAL COAT
0725-02-016 Rains/
Paris
FM 514 Actual $987,748 1 REHAB EXIST ROAD
2635-02-022 Randall/
Amarillo
LP 335 Actual $32,232,647 3 ADDITIONAL 2 LANES AND BRIDGES
0138-03-140 Rusk/
Tyler
US 259 Actual $574,528 8 TEXTURIZE SHOULDERS WITH PROFILE PAVEMENT MARKERS
0902-48-775 Tarrant/
Fort Worth
CS Actual $10,742,245 3 RECONSTRUCT BRIDGE TO ACCOMMODATE THE UPGRADE OF DIRKS / ALTA
0902-48-879 Tarrant/
Fort Worth
VA Actual $2,000,000 7 VANPOOL PROGRAM FY 15; OPER VANPOOL SUBSIDY INITIATIVE FOR
0902-48-880 Tarrant/
Fort Worth
VA Actual $2,000,000 7 VANPOOL PROGRAM FY 14; OPER VANPOOL SUBSIDY INITIATIVE FOR
0902-48-881 Tarrant/
Fort Worth
VA Actual $6,467,375 5 PRELIMINARY ENGINEERING AND NEPA CLEARANCE FOR TEXRAIL
0902-48-882 Tarrant/
Fort Worth
VA Actual $2,000,438 5 FOR CONSTRUCTION OF STRUCTURES,
0907-00-147 Tom Green/
San Angelo
VA Actual $615,232 1 PAVEMENT MARKINGS
0015-13-360 Travis/
Austin
IH 35 Actual $2,905,019 3 ADD ACCESS FROM NBFR TO 53RD STREET
0152-01-077 Travis/
Austin
US 183 Actual $698,386 1 OVERLAY
0683-02-058 Travis/
Austin
RM 620 Actual $2,734,591 1 SEAL & OVERLAY
1200-03-028 Travis/
Austin
FM 973 Actual $13,848,704 ROW REPLACE BRIDGE & APPROACHES


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract