Detail Letting Schedule for Callahan County (FY 2015)
Last Update: Tuesday, February 18, 2014
Callahan County (FY 2015) |
CCSJ: 0437-04-025
|
District: |
Abilene |
Let Date: |
SEP 2014 |
Highway: |
US 283 |
Let Status: |
Tentative |
Project ID: |
STP 2014(266) |
CSJ: |
0437-04-025 |
Description: |
REHAB AND WIDENING |
Handling Code: |
|
Limits From: |
SH 36 |
Fund Cat: |
1 |
Limits To: |
COLEMAN COUNTY LINE |
Estimate: |
$4,099,464 |
Length: |
10.6 Miles |
Actual: |
|
|
Back...
|
Totals for 0437-04-025 |
Length: |
10.6 Miles |
Estimate: |
$4,099,464 |
Actual: |
|
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|