Detail Letting Schedule for Limestone County (FY 2016)
Limestone County (FY 2016) |
CCSJ: 0419-02-041 | |||
District: | Waco | Let Date: | FEB 2016 |
Highway: | SH 171 | Let Status: | Actual |
Project ID: | STP 2016(746) | CSJ: | 0419-02-041 |
Description: | UNDERSEAL / OVERLAY | Handling Code: |
|
Limits From: | US 84 | Fund Cat: | 1 |
Limits To: | CITY OF COOLIDGE | Estimate: | $3,966,067 |
Length: | 11.1 Miles | Actual: | $3,653,777 |
Back... |
Totals for 0419-02-041 | ||
---|---|---|---|
Length: | 11.1 Miles | ||
Estimate: | $3,966,067 | ||
Actual: | $3,653,777 | ||
CCSJ: 0643-02-025 | |||
District: | Waco | Let Date: | DEC 2015 |
Highway: | FM 39 | Let Status: | Actual |
Project ID: | STP 1502(415) | CSJ: | 0643-02-025 |
Description: | WIDEN PAVEMENT TO ADD SHOULDERS, PROVIDE SAFETY UPGRADES AND | Handling Code: |
|
Limits From: | SH 164 | Fund Cat: | 1 |
Limits To: | LEON CO LINE | Estimate: | $4,822,453 |
Length: | 8.7 Miles | Actual: | $6,211,433 |
District: | Waco | Let Date: | DEC 2015 |
Highway: | FM 39 | Let Status: | Actual |
Project ID: | STP 1502(414)HES | CSJ: | 0643-02-026 |
Description: | SAFETY TREAT FIXED OBJECTS | Handling Code: |
|
Limits From: | SH 164 | Fund Cat: | 8 |
Limits To: | FM 80 | Estimate: | $1,172,080 |
Length: | 7.2 Miles | Actual: | $1,328,780 |
Back... |
Totals for 0643-02-025 | ||
Length: | 15.9 Miles | ||
Estimate: | $5,994,533 | ||
Actual: | $7,540,213 | ||
CCSJ: 0643-03-031 | |||
District: | Waco | Let Date: | JUL 2016 |
Highway: | FM 39 | Let Status: | Actual |
Project ID: | CRX 643-3-31 | CSJ: | 0643-03-031 |
Description: | RAILROAD REPLANKING | Handling Code: |
XX |
Limits From: | @ UP RR TRACKS | Fund Cat: | 10 |
Limits To: | IN MEXIA | Estimate: | $36,096 |
Length: | 0.1 Miles | Actual: | $36,096 |
Back... |
Totals for 0643-03-031 | ||
Length: | 0.1 Miles | ||
Estimate: | $36,096 | ||
Actual: | $36,096 | ||
CCSJ: 0752-06-022 | |||
District: | Waco | Let Date: | SEP 2015 |
Highway: | FM 147 | Let Status: | Actual |
Project ID: | STP 2016(103) | CSJ: | 0752-06-022 |
Description: | REHABILITATE AND WIDEN PAVEMENT TO ADD SHOULDERS, UPGRADE | Handling Code: |
|
Limits From: | SH 14 | Fund Cat: | 1 |
Limits To: | FALLS CO LINE | Estimate: | $4,311,099 |
Length: | 10.1 Miles | Actual: | $4,469,649 |
Back... |
Totals for 0752-06-022 | ||
Length: | 10.1 Miles | ||
Estimate: | $4,311,099 | ||
Actual: | $4,469,649 | ||
CCSJ: 2754-01-008 | |||
District: | Waco | Let Date: | APR 2016 |
Highway: | FM 2705 | Let Status: | Actual |
Project ID: | STP 2016(370) | CSJ: | 2754-01-008 |
Description: | WIDEN PAVEMENT TO ADD SHOULDERS, PROVIDE SAFETY UPGRADES AND | Handling Code: |
|
Limits From: | US 84 | Fund Cat: | 1 |
Limits To: | FM 1633 | Estimate: | $2,856,740 |
Length: | 3.4 Miles | Actual: | $2,938,833 |
District: | Waco | Let Date: | APR 2016 |
Highway: | FM 2705 | Let Status: | Actual |
Project ID: | STP 2016(370) | CSJ: | 2754-02-004 |
Description: | WIDEN PAVEMENT TO ADD SHOULDERS, PROVIDE SAFETY UPGRADES AND | Handling Code: |
|
Limits From: | FM 1633 | Fund Cat: | 1 |
Limits To: | SH 14 | Estimate: | $1,812,491 |
Length: | 2.4 Miles | Actual: | $1,795,110 |
Back... |
Totals for 2754-01-008 | ||
Length: | 5.8 Miles | ||
Estimate: | $4,669,231 | ||
Actual: | $4,733,943 |
|