Detail Letting Schedule for Kinney County (FY 2017)
Kinney County (FY 2017) |
CCSJ: 0023-04-065 |
|||
District: | LAREDO | Let Date: | Apr 2017 |
Highway: | US 90 | Let Status: | Actual |
Project ID: | NH 2017(587) | CSJ: | 0023-04-065 |
Description: | RESURFACE OF EXISTING HIGHWAY | Handling Code: | |
Limits From: | 0.375 MI EAST OF SH 131 | Fund Cat: | 1 |
Limits To: | KINNEY/UVALDE COUNTY LINE | ESTIMATE: | $7,575,768 |
Length: | 18.7 | Actual | $5,717,523 |
District: | LAREDO | Let Date: | Apr 2017 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | NH 2017(587) | CSJ: | 0023-09-011 |
Description: | CONCRETE PAVEMENT DIAMOND GRINDING | Handling Code: | |
Limits From: | US 90 | Fund Cat: | 1 |
Limits To: | 0.185 MILES SOUTH OF US 90 | ESTIMATE: | $103,728 |
Length: | 0.2 | Actual | $130,988 |
District: | LAREDO | Let Date: | Apr 2017 |
Highway: | US 277 | Let Status: | Actual |
Project ID: | NH 2017(587) | CSJ: | 0299-01-071 |
Description: | CONCRETE PAVEMENT DIAMOND GRINDING | Handling Code: | |
Limits From: | 0.185 MILES SOUTH OF US 90 | Fund Cat: | 1 |
Limits To: | 0.248 MILES SOUTH OF US 90 | ESTIMATE: | $41,957 |
Length: | 0.1 | Actual | $42,059 |
District: | LAREDO | Let Date: | Apr 2017 |
Highway: | SH 85 | Let Status: | Actual |
Project ID: | STP 2017(588) | CSJ: | 0301-01-083 |
Description: | RESURFACE OF EXISTING HIGHWAY | Handling Code: | |
Limits From: | 3.88 MI WEST OF FM 1867 | Fund Cat: | 1 |
Limits To: | 1.20 MI WEST OF FM 1867 | ESTIMATE: | $844,032 |
Length: | 2.7 | Actual | $713,043 |
District: | LAREDO | Let Date: | Apr 2017 |
Highway: | SH 85 | Let Status: | Actual |
Project ID: | STP 2017(588) | CSJ: | 0301-02-048 |
Description: | RESURFACE OF EXISTING HIGHWAY | Handling Code: | |
Limits From: | 1.20 MI WEST OF FM 1867 | Fund Cat: | 1 |
Limits To: | FRIO COUNTY LINE | ESTIMATE: | $4,049,279 |
Length: | 12.6 | Actual | $3,301,882 |
District: | LAREDO | Let Date: | Apr 2017 |
Highway: | SH 85 | Let Status: | Actual |
Project ID: | STP 1702(175)HES | CSJ: | 0301-02-050 |
Description: | MILLED EDGELINE AND CENTER LINE RUMBLE STRIPS | Handling Code: | |
Limits From: | 1.208 MI W OF FM 1867 | Fund Cat: | 8 |
Limits To: | FRIO COUNTY LINE | ESTIMATE: | $4,000 |
Length: | 12.6 | Actual | $28,994 |
District: | LAREDO | Let Date: | Apr 2017 |
Highway: | FM 1021 | Let Status: | Actual |
Project ID: | STP 2017(588) | CSJ: | 1229-01-065 |
Description: | RESURFACE EXISTING HIGHWAY | Handling Code: | |
Limits From: | SS240 | Fund Cat: | 1 |
Limits To: | BLISS STREET | ESTIMATE: | $99,816 |
Length: | 0.4 | Actual | $79,642 |
Proposal Request List Showing Order Bid List Addenda Bid Tabulations Award Status Back... | Totals for 0023-04-065 | ||
---|---|---|---|
Length: | 47.3 | ||
Estimate: | $12,718,579 | ||
Actual: | $10,014,131 |
Handling Code | Definition |
---|---|
XX | Project not processed through statewide letting |
TR | Transfer of funds |
LC | Project let through local entity |
LC | Project not charged against district apportionment |
Let Status | Definition |
---|---|
Tentative | Estimated letting date for this project |
Approved | Project has administrative approval to be let |
Actual | Project was let to contract |