Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCROSBY
Highway US0082
From VARIOUS COUNTIES WITHIN THE
To NORTHWESTERN TEXAS REGION
CSJ 6221-75-001
Proj ID RMC - 622175001
Work Type TOTAL REST AREA MAINTENANCE
 
0.010 3737760.00 230822.83 11942811.79 99.9
Work Order 04-18-11
Work Began 05-01-11
Work Completed  
Time Computed 05-01-11
Contract Working Days 730
Addl Days Granted 1,462
Working Days Charged 2,072
Percent Time Used 94
Contractor(s)
ICA MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03114019
Totals 3737760.00 230822.83 11942811.79 99.9

CountyNAVARRO
Highway IH0045
From NAVARRO COUNTY
To NAVARRO COUNTY
CSJ 6227-15-001
Proj ID SUP - 622715001
Work Type TOTAL REST AREA OPS, MNT, RPRS
 
1.000 42000.00 0.00 84000.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-01-11
Work Began 05-01-11
Work Completed  
Time Computed 05-01-11
Contract Working Days 92
Addl Days Granted 0
Working Days Charged 184
Percent Time Used 200
Contractor(s)
TIBH INDUSTRIES, INC.
ON OUR OWN SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6227-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04114039
Totals 42000.00 0.00 84000.00 99.9

CountyNAVARRO
Highway IH0045
From IH0045 NB, SUP 15
To IH0045 SB, SUP 16
CSJ 6232-35-001
Proj ID SUP - 623235001
Work Type TOTAL RA MNT, OPS, RPR 24 / 7
 
0.010 1008000.00 0.00 797473.70 79.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-01-11
Work Began 08-01-11
Work Completed  
Time Computed 08-01-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 639
Percent Time Used 87
Contractor(s)
TIBH INDUSTRIES, INC.
ON OUR OWN SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6232-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08114029
Totals 1008000.00 0.00 797473.70 79.1

CountyGILLESPIE
Highway US0290
From US 290, IH 35, US 77, US 281
To IH 45
CSJ 6258-24-001
Proj ID SUP - 625824001
Work Type TOTAL REST AREA OPS MNT & REPAIR
 
0.010 7789411.36 529585.97 17496327.31 99.9
Work Order 05-01-13
Work Began 05-01-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 731
Addl Days Granted 732
Working Days Charged 1,341
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
ON OUR OWN SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05134031
Totals 7789411.36 529585.97 17496327.31 99.9

CountyBEXAR
Highway IH0010
From KERR CO,MEDINA LIVE OAK
To COKE, CONCHO COUNTIES
CSJ 6258-25-001
Proj ID SUP - 625825001
Work Type REST AREA TOTAL; OPS. MNT, & RPR
 
0.010 2602160.16 251961.60 6855991.11 99.9
Work Order 05-01-13
Work Began 05-01-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 731
Addl Days Granted 732
Working Days Charged 1,341
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6258-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05134030
Totals 2602160.16 251961.60 6855991.11 99.9

CountyEL PASO
Highway IH0010
From VARIOUS COUNTIES WITHIN THE
To WESTERN TEXAS REGION
CSJ 6258-50-001
Proj ID RMC - 625850001
Work Type TOTAL REST AREA MAINTENANCE
 
0.001 7060800.00 150769.44 6116048.53 86.6
Work Order 08-01-13
Work Began 08-01-13
Work Completed  
Time Computed 08-01-13
Contract Working Days 1,460
Addl Days Granted 0
Working Days Charged 1,249
Percent Time Used 85
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06134018
Totals 7060800.00 150769.44 6116048.53 86.6

CountyHARRIS
Highway US0059
From VARIOUS COUNTIES IN THE HOUSTON DISTRICT
To VARIOUS COUNTIES IN THE HOUSTON DISTRICT
CSJ 6281-62-001
Proj ID RMC - 628162001
Work Type DEBRIS REMOVAL AND DISPOSAL
 
0.001 2271900.00 0.00 646215.29 28.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-29-15
Work Completed  
Time Computed 06-29-15
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 52
Contractor(s)
DRC EMERGENCY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6281-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04154020
Totals 2271900.00 0.00 646215.29 28.4

CountyVICTORIA
Highway US0077
From VARIOUS HIGHWAYS IN DISTRICT 13
To VARIOUS HIGHWAYS IN DISTRICT 13
CSJ 6281-63-001
Proj ID RMC - 628163001
Work Type DEBRIS REMOVAL AND DISPOSAL
 
0.001 1047300.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-08-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DRC EMERGENCY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6281-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04154218
Totals 1047300.00 0.00 0.00 0.0

CountyNUECES
Highway US0077
From VARIOUS HIGHWAYS
To VARIOUS HIGHWAYS
CSJ 6281-64-001
Proj ID RMC - 628164001
Work Type DEBRIS REMOVAL AND DISPOSAL
 
0.001 1047300.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DRC EMERGENCY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6281-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04154219
Totals 1047300.00 0.00 0.00 0.0

CountyCAMERON
Highway US0083
From VARIOUS COUNTIES IN DISTRICT 21
To VARIOUS COUNTIES IN DISTRICT 21
CSJ 6281-65-001
Proj ID RMC - 628165001
Work Type DEBRIS REMOVAL AND DISPOSAL
 
0.001 620600.00 0.00 523046.25 84.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-05-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 36
Contractor(s)
T.F.R. ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04154220
Totals 620600.00 0.00 523046.25 84.2

CountyWICHITA
Highway US0287
From VARIOUS COUNTIES, FROM EASTLAND
To WICHITA
CSJ 6290-50-001
Proj ID SUP - 629050001
Work Type TOTAL REST AREA MNT, OPS, RPR
 
0.001 1697780.64 0.00 846726.50 49.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 11-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 427
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10154031
Totals 1697780.64 0.00 846726.50 49.8

page 1 | page 2