FM 3180 and FM 2354 Corridor - Chambers County

In partnership with the Houston-Galveston Area Council (H-GAC) for funding and development, TxDOT approved a series of construction projects along the FM 3180 & FM 2354 corridor from I-10 to the Fisher Road area in the Mont Belvieu, Baytown and Beach City communities located in Chambers County. Some of these projects are under construction, while others are planned in the future.

Planned Improvements

The overall FM 3180 & FM 2354 corridor construction projects includes the following improvements:

Corridor Improvements
General Timing (subject to change)
Constructing an overpass at I-10 and FM 3180 2018 Letting (contract bid)
Widening FM 3180 to four lanes, with a continuous left turn lane from north of I-10 to FM 565 2018 Letting (contract bid)
Reconstructing the intersection at FM 3180 and FM 565 Began construction in Summer of 2016 and anticipated completion Summer 2017
Adding a continuous turn lane at FM 3180 from FM 565 to FM 2354 Completed Summer 2016
Adding a continuous turn lane on FM 2354, from FM 3180 to just south of Fisher Road (project scope is still being determined) 2018 Letting (contract bid)

The purpose of these roadway improvements is to reduce congestion, increase mobility and improve safety.

These projects do not require additional right of way or displacements.

Construction Considerations

TxDOT is committed to working with the public to minimize the environmental impact from construction projects as much as possible. Construction will be phased along this corridor due to funding constraints, and timing is subject to change.

Construction Schedule

  • Monday - Friday standard construction work hours (dawn - dusk)
  • Lane closures while school is in session will be limited to between the hours of 9 a.m. and 3 p.m.
  • No anticipated weekend work