This list provides the current status of the the project as well as upcoming and past events.
| Activity | Date |
| Begin Stringer Street Project | Dec. 6 |
| Move westbound mainlane US 290 traffic to frontage road | Dec. 3 |
| Pre-construction meeting for Stringer Street Project | Nov. 1 |
| Pour BU 290 bridge deck | Oct. 24 |
| Pour FM 577 bridge deck | Oct. 19 |
| Switch frontage road traffic to one-way operation west of SH 36 Open U-turn lane under BNSF RR bridge | Sept. 27 |
| Switch frontage road traffic to one-way operation east of SH 36 | July 5 |
| Begin drilling shafts for bridge at BU 290 (Market St.) | June 1 |
| Crossovers at Nutt Blvd. closed | May 11 |
| Begin drill shafts for bridge over FM 577 | May 10 |
| EB ramp to Lubbock St. closed - must use SH 36 exit to access Lubbock St. Frontage road turnaround at BNSF railroad closed | May 9 |
| Construction is set to begin | April 25 |
| Ground-breaking ceremony | April 22 |
| Pre-construction meeting | April 5 |
| Construction surveying has begun Project has been awarded to Webber L.L.C. from Houston, TX | Preliminary |