FM 2275 from FM 3272 in White Oak East to SH 300 in Longview

Project Overview

The Texas Department of Transportation (TxDOT) is developing plans to improve FM 2275 from FM 3272 in White Oak east to SH 300 in Longview.

Details

Improvements to this east/west corridor would include:

  • Widening from the existing two-lane road to a four-lane roadway with a flush median 
  • Adding a continuous left-turn lane to provide additional safety
  • Incorporating a designated bicycle lane
  • Redesigning the roadway’s alignment to improve grades and curves.

The project will require the acquisition of new right-of-way from adjacent property owners.

Get Involved

The first public meeting was held on June 28, 2016, to present three widening alternatives for the project (shown below) and to offer property owners and interested citizens a chance to provide input, voice concerns and have their questions answered.

A second public meeting was held on Nov. 17, 2016, to present the preferred alternative. The preferred alignment was formulated based on public comments received at the first public meeting. It most closely resembled Alternative #3. 

TxDOT will schedule a public hearing in late spring/early summer 2017 to present the recommended preferred alternative for public comment.

Downloads

Schedule

TxDOT and its consultants  are working toward a recommended preferred alignment and environmental assessment. The recommended alignment and environmental assessment will be presented for public comment at a public hearing by summer 2017.

The environmental assessment will examine potential project-related impacts as well as measures to avoid, minimize or mitigate those impacts.  The environmental assessment will be subject to an extensive review process and coordination with agencies such as the Texas Parks and Wildlife Department, the Texas Historical Commission and others. A decision on the environmental assessment (possible environmental clearance) is anticipated in 2017.

Assuming environmental clearance is received, the next steps would be right-of-way acquisitions and the development of construction plans. Right-of-way acquisition is expected to begin in 2018. TxDOT plans to construct the project in two phases. The first phase will extend from FM 1845 (Pine Tree Road) to SH 300 (Gilmer Road) and the second phase from FM 3272 in White Oak to FM 1845 (Pine Tree Road). For Phase 1, the current financial forecasts show construction funds will be available in 2021. No financial funding is identified for Phase 2 at this time.