Monthly State Let Construction Report For Tyler District As Of Apr 12, 2024 Page 6 Of 6

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGREGG
HighwayFM 2206
From2.05 MI E OF SH 42 (FISHER RD), E
ToSL 281 IN LONGVIEW
CSJ2073-01-009
Proj IDSTP 2013(212)
Work TypeWIDEN NON-FREEWAY
 
15164540.8912775851.9585.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-09-20
Work Began07-06-20
Work Completed
Time Computed00-00-00
Contract Working Days302
Addl Days Granted89
Working Days Charged576
Percent Time Used147
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2073-01-009
ISAACS CONSTRUCTION SERVICES LLC (0.73)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.25)
PANOLA SIGN & BARRICADE, INC. (0.34)
SOUTHWEST ENVIRONMENT SERIVES, LLC (1.43)
STRIPING TECHNOLOGY, L.P. (2.10)
WITHERS CONSTRUCTION, LLC (0.74)
CARTHAGE DRILLING, INC. (0.08)
REYNOLDS & KAY, LTD. (0.16)
Contract #04203004
Totals15164540.89249542.6112775851.9585.8

CountyGREGG
HighwayFM 2206
FromSH 42, E
To1.6 MI W OF SL281(FISHER RD)IN LGVW
CSJ2073-01-010
Proj IDSTP 2020(788)
Work TypeWIDEN NON-FREEWAY
 
13220500.1310758356.1183.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-20
Work Began11-09-20
Work Completed
Time Computed00-00-00
Contract Working Days396
Addl Days Granted25
Working Days Charged602
Percent Time Used142
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2073-01-010
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.58)
STRIPING TECHNOLOGY, L.P. (2.11)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.23)
SOUTHWEST ENVIRONMENT SERIVES, LLC (1.05)
PANOLA SIGN & BARRICADE, INC. (0.28)
ISAACS CONSTRUCTION SERVICES LLC (0.81)
TORO BRAVO CONSTRUCTION, LLC (0.00)
REYNOLDS & KAY, LTD. (0.12)
PENHALL COMPANY (0.10)
TEX OP CONSTRUCTION, LP (0.13)
Contract #08203005
Totals13220500.1379372.4610758356.1183.1

CountySMITH
HighwaySL 323
From.3 MI N OF SH31, ELM ST IN WEST TYLER, N
To0.25 MI E OF US 69
CSJ2075-01-058
Proj IDC 2075-1-58
Work TypeOVERLAY
 
4548986.943521510.0877.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-28-23
Work Began09-11-23
Work Completed
Time Computed00-00-00
Contract Working Days144
Addl Days Granted0
Working Days Charged66
Percent Time Used45
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2075-01-058
MORRIS COUNTY CONTRACTORS, L.L.C. (0.30)
PANOLA SIGN & BARRICADE, INC. (0.69)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.03)
STRIPING TECHNOLOGY, L.P. (4.79)
TRUE ROADS CONSTRUCTION, LLC (4.06)
Contract #02233020
Totals4548986.9416437.533521510.0877.4

CountyGREGG
HighwaySL 281
From0.2 MI W OF FM 2208
ToHARRISON CL
CSJ2642-01-049
Proj IDSTP 2B23(070)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
225254.70238234.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-23
Work Began09-20-23
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged23
Percent Time Used51
Contractor(s)
THK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 2642-01-049
FLEX SUPPLY, LLC (2.42)
MORRIS COUNTY CONTRACTORS, L.L.C. (12.93)
Contract #08233267
Totals225254.700.00238234.4099.9

CountyRUSK
HighwayFM 2658
FromFM 2658
ToBRIDGE REPLACEMENT
CSJ2653-01-016
Proj IDBR 2B23(067)
Work TypeBRIDGE REPLACEMENT
 
3094483.610.000.0
CountyRUSK
HighwayFM 2658
From1.571 MI S OF SH 43
To0.427 MILES N OF FM 1251
CSJ2653-01-017
Proj IDF 2B23(068)
Work TypeREHABILITATION OF EXISTING ROAD
 
6517754.7468800.001.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-23
Work Began03-19-24
Work Completed
Time Computed00-00-00
Contract Working Days220
Addl Days Granted0
Working Days Charged3
Percent Time Used1
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 2653-01-016
TEX OP CONSTRUCTION, LP (0.13)
FLEX SUPPLY, LLC (0.13)
STRIPING TECHNOLOGY, L.P. (1.64)
SCOTT DERR PAINTING CO, LLC (0.28)
PENHALL COMPANY (0.04)
A. E. MOORE CONSTRUCTION, INC. (2.93)
Contract #08233009
Totals9612238.3568400.0068800.000.7