Monthly Local Let Maintenance Report For Austin District As Of Jan 11, 2017 Page 1 Of 4

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwayLP0001
FromTRAVIS AND WILLIAMSON COUNTIES
To.
CSJ6182-61-001
Proj IDSUP - 618261001
Work TypeJANITORIAL SERVICES FOR TOLL ROADS
 
0.001280300.44887401.3899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-25-08
Work Began07-01-08
Work Completed
Time Computed07-01-08
Contract Working Days365
Addl Days Granted0
Working Days Charged1,157
Percent Time Used316
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES OF CENTRAL TEXAS
SUBCONTRACTOR(S) FOR CCSJ: 6182-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06081431
Totals280300.440.00887401.3899.9

CountyMASON
HighwaySH0029
FromMASON COUNTY MAINTENANCE OFFICE
To.
CSJ6231-23-001
Proj IDSUP - 623123001
Work TypeJANITORIAL MAINTENANCE IN MASON
 
0.00113355.3212900.5321.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-11
Work Began08-16-11
Work Completed
Time Computed08-16-11
Contract Working Days730
Addl Days Granted0
Working Days Charged747
Percent Time Used102
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6231-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08111430
Totals13355.320.0012900.5321.6

CountyTRAVIS
HighwayLP0001
FromTRAVIS AND WILLIAMSON COUNTIES
To.
CSJ6235-86-001
Proj IDSUP - 623586001
Work TypeJANITORIAL SERVICES FOR TOLL ROADS
 
0.001719997.41625964.0187.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-12-11
Work Began08-15-11
Work Completed
Time Computed08-15-11
Contract Working Days1,048
Addl Days Granted0
Working Days Charged1,051
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6235-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08111432
Totals719997.410.00625964.0187.8

CountyTRAVIS
HighwayFM0969
FromTRAVIS EAST MAINTENANCE OFFICE
To.
CSJ6260-08-001
Proj IDSUP - 626008001
Work TypeJANITORIAL MAINTENANCE
 
0.0018147.768147.7699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-03-13
Work Began06-03-13
Work Completed
Time Computed06-03-13
Contract Working Days730
Addl Days Granted0
Working Days Charged721
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05131432
Totals8147.760.008147.7699.9

CountyTRAVIS
HighwayUS0183
FromVARIOUS LOCATIONS IN
ToTRAVIS AND HAYS COUNTY
CSJ6264-02-001
Proj IDRMC - 626402001
Work TypeREMOVAL AND DISPOSAL OF TREES &
 
0.010184732.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FST CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6264-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10131403
Totals184732.000.000.000.0

CountyTRAVIS
HighwayRM2322
FromSH 71
ToEND STATE MAINTENANCE
CSJ6268-21-001
Proj IDRMC - 626821001
Work TypeTIER 1 SEAL
 
4.564298395.12329641.9899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-23-14
Work Began05-05-14
Work Completed
Time Computed05-05-14
Contract Working Days18
Addl Days Granted0
Working Days Charged19
Percent Time Used105
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6268-21-001
FLASHER EQUIPMENT COMPANY (23.70)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.93)
Contract #03141402
Totals298395.120.00329641.9899.9

CountyGILLESPIE
HighwayUS0290
FromVARIOUS LOCATIONS IN GILLESPIE
To.
CSJ6269-64-001
Proj IDSUP - 626964001
Work TypeLITTER REMOVAL
 
0.00184585.8260167.5571.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-14
Work Began04-01-14
Work Completed
Time Computed04-07-14
Contract Working Days60
Addl Days Granted0
Working Days Charged32
Percent Time Used53
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6269-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02141430
Totals84585.820.0060167.5571.1

CountyMASON
HighwayUS0087
FromVARIOUS LOCATIONS IN MASON, LLANO AND
ToGILLESPIE COUNTIES
CSJ6271-62-001
Proj IDRMC - 627162001
Work TypeLITTER REMOVAL
 
0.00192146.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days76
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLAGSHIP SWEEPING SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04141404
Totals92146.200.000.000.0

CountyTRAVIS
HighwayLP0001
FromTRAVIS AND WILLIAMSON COUNTIES
To.
CSJ6274-83-001
Proj IDSUP - 627483001
Work TypeJANITORIAL SERVICES FOR TOLL ROADS
 
0.001299990.94291428.8297.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged293
Percent Time Used40
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06141432
Totals299990.940.00291428.8297.4

CountyTRAVIS
HighwayIH0035
FromVARIOUS LOCATIONS DISTRICTWIDE
ToVARIOUS LOCATIONS DISTRICTWIDE
CSJ6275-79-001
Proj IDRMC - 627579001
Work TypeREPLACE LARGE SIGNS
 
0.100233904.02308365.8099.9
Work Order00-00-00
Work Began11-03-14
Work Completed
Time Computed11-03-14
Contract Working Days730
Addl Days Granted180
Working Days Charged781
Percent Time Used85
Contractor(s)
THE LEVY COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6275-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09141403
Totals233904.020.00308365.8099.9

CountyBASTROP
HighwaySH0071
FromVARIOUS LOCATIONS IN
ToBASTROP COUNTY
CSJ6276-24-001
Proj IDRMC - 627624001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001257824.00278510.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-15-15
Work Completed
Time Computed06-15-15
Contract Working Days90
Addl Days Granted0
Working Days Charged39
Percent Time Used43
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6276-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141403
Totals257824.000.00278510.0099.9

CountyWILLIAMSON
HighwayFM1466
FromAT LITTLE DRY BRUSHY CREEK
To.
CSJ6276-25-001
Proj IDBPM - 627625001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.10057350.0054083.6094.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days22
Addl Days Granted0
Working Days Charged9
Percent Time Used40
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151406
Totals57350.000.0054083.6094.3

CountyLEE
HighwayUS0290
FromVARIOUS LOCATIONS IN
ToLEE COUNTY
CSJ6276-26-001
Proj IDRMC - 627626001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001257013.20224348.6087.2
Work Order00-00-00
Work Began06-25-15
Work Completed
Time Computed06-25-15
Contract Working Days90
Addl Days Granted0
Working Days Charged31
Percent Time Used34
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6276-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141404
Totals257013.2049198.60224348.6087.2

CountyMASON
HighwayUS0087
FromVARIOUS LOCATIONS IN MASON, LLANO
ToAND GILLESPIE COUNTIES
CSJ6276-88-001
Proj IDRMC - 627688001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001221836.00221712.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged37
Percent Time Used71
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6276-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141406
Totals221836.000.00221712.0099.9

CountyTRAVIS
HighwayIH0035
FromAUSTIN DISTRICT
ToVARIOUS LOCATIONS
CSJ6279-85-001
Proj IDRMC - 627985001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.001223610.00247489.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-18-15
Work Completed
Time Computed00-00-00
Contract Working Days349
Addl Days Granted211
Working Days Charged523
Percent Time Used93
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01151402
Totals223610.000.00247489.6099.9

CountyLEE
HighwayUS0290
FromVARIOUS LOCATIONS IN
ToLEE MAINTENANCE SECTION
CSJ6280-14-001
Proj IDSUP - 628014001
Work TypeLITTER REMOVAL
 
0.001137724.88124574.6890.4
Work Order04-13-15
Work Began04-13-15
Work Completed
Time Computed04-13-15
Contract Working Days120
Addl Days Granted0
Working Days Charged41
Percent Time Used34
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6280-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01151430
Totals137724.8818044.97124574.6890.4

CountyTRAVIS
HighwayIH0035
FromAUSTIN DISTRICT HEADQUARTERS
To.
CSJ6281-88-001
Proj IDSUP - 628188001
Work TypeJANITORIAL MAINTENANCE
 
0.001173668.89166662.5795.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-01-15
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged700
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6281-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12141430
Totals173668.890.00166662.5795.9

CountyBASTROP
HighwayFM3000
FromELGIN TO 3.7 MILES NE
To.
CSJ6284-16-001
Proj IDSUP - 628416001
Work TypeLITTER PICKUP AND REMOVAL
 
0.001176356.04168800.7595.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-24-15
Work Completed
Time Computed00-00-00
Contract Working Days146
Addl Days Granted0
Working Days Charged77
Percent Time Used52
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6284-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01151431
Totals176356.040.00168800.7595.7

CountyTRAVIS
HighwayFM0734
FromTRAVIS CENTRAL/NORTH TRAVIS AO
To.
CSJ6287-65-001
Proj IDSUP - 628765001
Work TypeJANITORIAL MAINTENANCE
 
0.00119152.7215761.0982.2
Work Order00-00-00
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged605
Percent Time Used82
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04151430
Totals19152.72798.0315761.0982.2

CountyTRAVIS
HighwayIH0035
FromVARIOUS LOCATIONS DISTRICT-WIDE
ToVARIOUS LOCATIONS DISTRICT-WIDE
CSJ6288-81-001
Proj IDRMC - 628881001
Work TypeMAINTENANCE OF ILLUMINATION
 
0.001251109.00309025.7699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged300
Percent Time Used41
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10151405
Totals251109.000.00309025.7699.9

page 1 | page 2 | page 3 | page 4