Monthly State Let Construction Report For Childress District As Of Feb 11, 2016 Page 1 Of 2

Last Update: Thursday, February 11, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWHEELER
Highway US 83
From 250 FT. NORTH OF WHEELER NCL, NORTH
To HEMPHILL COUNTY LINE
CSJ 0030-08-035
Proj ID STP 1502(376)
Work Type WIDENING OF A NON - FREEWAY FACILITY
 
12.458 9811524.17 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-08-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153031
Totals 9811524.17 0.00 0.00 0.0

CountyWHEELER
Highway US 83
From 0.500 MI N OF SHAMROCK NCL, NORTH
To WHEELER SCL
CSJ 0030-09-047
Proj ID STP 1502(377)
Work Type WIDENING OF A NON FREEWAY FACILITY
 
14.092 9018908.40 0.00 92656.20 1.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 5
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-09-047
DALE BROWN, INC. (3.50%)
BARRICADES UNLIMITED (1.24%)
DUSTROL, INC.(0.25%)
HJC FARMS, INC.(1.97%)
Contract # 07153259
Totals 9018908.40 0.00 92656.20 1.0

CountyCHILDRESS
Highway US 62
From PRAIRIE DOG TOWN FORK OF RR, NORTH
To US 62/83 SPLIT
CSJ 0031-05-042
Proj ID NH 2016(613)
Work Type REHABILITATION OF EXISTING ROADWAY
 
6.557 4890499.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0031-05-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153041
Totals 4890499.30 0.00 0.00 0.0

CountyKING
Highway US 83
From COTTLE C/L, S
To GUTHRIE
CSJ 0032-05-038
Proj ID C 32-5-38
Work Type MISCELLANEOUS WORK
 
15.270 77364.00 0.00 0.00 100.0
CountyKING
Highway US 83
From US 82, S
To STONEWALL C/L
CSJ 0032-06-036
Proj ID C 32-6-36
Work Type MISCELLANEOUS WORK
 
14.440 8596.00 0.00 0.00 100.0
CountyHALL
Highway SH 256
From 0.3 MILES E OF SH 70, E
To FM 2361
CSJ 0541-02-030
Proj ID C 541-2-30
Work Type REPLACE BRIDGERAIL
 
30.323 581853.35 0.00 119526.24 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-12
Work Began 00-00-00
Work Completed 06-23-14
Time Computed 09-05-12
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0541-02-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06123013
Totals 667813.35 0.00 119526.24 100.0

CountyDONLEY
Highway US 287
From ARMSTRONG C/L
To CLARENDON WCL (SBL)
CSJ 0042-06-067
Proj ID NH 2014(061)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
11.635 2248102.73 0.00 2331175.41 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 09-25-14
Work Completed 02-10-15
Time Computed 02-02-14
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 85
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-06-067
FLAT LINE, INC.(1.29%)
HJC FARMS, INC.(5.20%)
BARRICADES UNLIMITED (0.66%)
WEST TEXAS RUMBLE STRIP(0.36%)
E. DIAZ TRUCKING (3.00%)
Contract # 10133207
Totals 2248102.73 0.00 2331175.41 100.0

CountyDONLEY
Highway US 287
From HEDLEY SCL, SE
To HALL C/L_(SBL)
CSJ 0042-08-056
Proj ID NH 2016(308)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
9.813 2680662.61 0.00 32000.00 1.1
CountyHALL
Highway US 287
From MEMPHIS SCL, SE
To RED RIVER BRIDGE (NBL)
CSJ 0042-09-122
Proj ID NH 2016(308)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
11.956 3169557.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-08-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153015
Totals 5850220.34 0.00 32000.00 0.5

CountyHALL
Highway US 287
From RED RIVER BRIDGE, SE
To CHILDRESS C/L (NBL)
CSJ 0042-09-120
Proj ID NH 2014(752)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
3.350 1106400.71 0.00 1197485.85 100.0
CountyCHILDRESS
Highway US 287
From HALL C/L, SE
To 0.36 MILES WEST OF FM 164(NBL)
CSJ 0042-12-063
Proj ID NH 2014(752)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
9.172 3136409.13 0.00 3592350.34 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-09-14
Work Began 10-07-14
Work Completed 06-08-15
Time Computed 05-25-14
Contract Working Days 73
Addl Days Granted 11
Working Days Charged 70
Percent Time Used 83
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-12-063
ALTUS TRAFFIC MANAGEMENT LLC (0.23%)
DUSTROL, INC.(2.33%)
PENHALL COMPANY(0.21%)
SCR CONSTRUCTION CO., INC. (0.67%)
TEXAS ALTERNATIVE GRASSER, INC.(0.23%)
BARRICADES UNLIMITED (1.17%)
Contract # 04143032
Totals 4242809.84 0.00 4789836.19 100.0

CountyCHILDRESS
Highway US 287
From 17TH STREET, EAST
To 340 FT. EAST OF FM 2530
CSJ 0043-01-078
Proj ID NH 1502(313)
Work Type REHABILITATION OF EXISTING ROAD
 
2.007 2560131.56 85223.15 85223.15 3.3
CountyHARDEMAN
Highway US 287
From 55 FT WEST OF FM 2568, EAST
To SH 6
CSJ 0043-02-072
Proj ID NH 1502(313)
Work Type REHABILITATION OF EXISTING ROAD
 
0.840 442291.10 0.00 0.00 0.0
CountyHARDEMAN
Highway US 287
From SH 6, EAST
To 65 FT. WEST OF FM 2568
CSJ 0043-04-077
Proj ID NH 1502(313)
Work Type REHABILITATION OF EXISTING ROAD
 
1.226 6912523.04 0.00 0.00 0.0
Work Order 08-26-15
Work Began 00-00-00
Work Completed  
Time Computed 01-14-16
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 5
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-01-078
DUSTROL, INC.(0.07%)
LINDAMOOD DEMOLITION, INC. (5.22%)
LUZ LERMA CONSTRUCTION, INC. (4.67%)
MCL CONTRACTING, LLC (1.45%)
PRIMATE CONSTRUCTION, INC. (1.81%)
TEXAS PANHANDLE CONSTRUCTION, INC. (0.72%)
BARRICADES UNLIMITED (0.59%)
Contract # 06153213
Totals 9914945.70 85223.15 85223.15 0.8

CountyCHILDRESS
Highway US 287
From DISTRICT WIDE
To .
CSJ 0043-01-079
Proj ID NH 2016(310)
Work Type INSTALL DMS & UPGRADE TRAFFIC SIGNA
 
0.009 1893993.41 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-01-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153208
Totals 1893993.41 0.00 0.00 0.0

CountyHARDEMAN
Highway US 287 ETC
From FM 2568, SOUTH
To WANDERER'S CREEK (SBL)
CSJ 0043-04-078
Proj ID NH 2016(014)
Work Type SEALCOAT
 
122.883 3997851.76 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-02-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-04-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153205
Totals 3997851.76 0.00 0.00 0.0

CountyHARDEMAN
Highway SH 6
From @ BNSF RR OVERPASS
To .
CSJ 0097-02-037
Proj ID BR 2014(756)
Work Type MISCELLANEOUS WORK
 
0.453 2936931.42 0.00 2993296.77 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-29-14
Work Began 12-08-14
Work Completed  
Time Computed 09-14-14
Contract Working Days 197
Addl Days Granted 14
Working Days Charged 199
Percent Time Used 94
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0097-02-037
GARY A. CRAIN, INC.(0.18%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 10.72%)
CONTRACTORS SERVICE COMPANY(0.31%)
BARRICADES UNLIMITED (0.33%)
DUSTROL, INC.(1.85%)
GIBSON & ASSOCIATES, INC.(2.46%)
LANCO TURF & SEEDING, INC. (1.42%)
DUSTY ALLEN, INC.(2.65%)
MCL CONTRACTING, LLC (0.40%)
DUININCK, INC. ( 13.99%)
Contract # 06143217
Totals 2936931.42 0.00 2993296.77 99.9

CountyHARDEMAN
Highway SH 6
From US 287, S
To 6 MILES
CSJ 0098-01-036
Proj ID STP 2014(757)
Work Type REHABILITATION OF EXISTING ROADWAY
 
6.000 4804257.07 0.00 4506756.10 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-14
Work Began 04-15-15
Work Completed 09-14-15
Time Computed 09-25-14
Contract Working Days 103
Addl Days Granted 10
Working Days Charged 72
Percent Time Used 63
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0098-01-036
DUSTROL, INC.(0.40%)
BARRICADES UNLIMITED (4.25%)
E. DIAZ TRUCKING (5.00%)
Contract # 06143019
Totals 4804257.07 0.00 4506756.10 100.0

CountyFOARD
Highway SH 6
From @ RAGGEDY CREEK
To .
CSJ 0098-02-025
Proj ID BR 1102(556)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.094 1135621.40 0.00 1148933.00 100.0
CountyFOARD
Highway FM 267
From @ BEAVER CREEK
To .
CSJ 2164-02-017
Proj ID BR 1102(557)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.114 644822.40 0.00 635420.60 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-14
Work Began 10-20-14
Work Completed 10-19-15
Time Computed 00-00-00
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 176
Percent Time Used 100
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0098-02-025
PENHALL COMPANY (AUSTIN) (0.17%)
DUSTIN ALLEN, INC. (2.87%)
TEXAS ALTERNATIVE GRASSER, INC.(0.87%)
CONTRACTORS SERVICE COMPANY(0.75%)
BARRICADES UNLIMITED (0.88%)
J. LEE MILLIGAN, INC.( 11.83%)
DUININCK, INC. (7.04%)
Contract # 06143215
Totals 1780443.80 0.00 1784353.60 100.0

CountyKNOX
Highway SH 6
From HASKELL C/L, N
To 2ND STREET
CSJ 0098-05-033
Proj ID STP 2015(838)
Work Type REHABILITATION OF EXISTING ROAD
 
1.587 1413454.41 0.00 1438355.80 100.0
CountyKNOX
Highway US 277
From HASKELL C/L, N
To FM 267
CSJ 0157-02-045
Proj ID NH 2015(837)
Work Type REHABILITATION OF EXISTING ROAD
 
2.603 1495602.83 0.00 1423858.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-14-15
Work Began 06-22-15
Work Completed 10-30-15
Time Computed 06-14-15
Contract Working Days 92
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 69
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0157-02-045
ALTUS TRAFFIC MANAGEMENT LLC (0.63%)
DUSTROL, INC.(1.96%)
TEXAS ALTERNATIVE GRASSER, INC.(0.40%)
TEXAS PANHANDLE CONSTRUCTION, INC. (1.96%)
WEST TEXAS RUMBLE STRIP(0.21%)
Contract # 04153025
Totals 2909057.24 0.00 2862213.80 100.0

CountyMOTLEY
Highway SH 70
From NORTH PEASE RIVER
To .
CSJ 0105-04-042
Proj ID BR 2013(663)
Work Type REPLACEMENT OF EXISTING BRIDGE
 
0.240 2085247.00 0.00 2152204.82 100.0
CountyMOTLEY
Highway SH 70
From @ MIDDLE PEASE RIVER
To .
CSJ 0105-04-043
Proj ID BR 2013(663)
Work Type REPLACEMENT OF EXISTING BRIDGE
 
0.315 2182953.50 0.00 2203372.31 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-31-13
Work Began 09-03-13
Work Completed 05-19-15
Time Computed 08-16-13
Contract Working Days 275
Addl Days Granted 12
Working Days Charged 285
Percent Time Used 99
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0105-04-042
BARRICADES UNLIMITED (0.82%)
DUSTROL, INC.(0.19%)
LANCO TURF & SEEDING, INC. (0.47%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.58%)
MASTERPIECE GRINDING & GROOVING, LLC (0.13%)
ROSS GRAHAM(0.40%)
G & L REBAR(0.49%)
MCL CONTRACTING, LLC (0.71%)
HOLMES CONSTRUCTION CO., L.P.(1.22%)
PENHALL COMPANY (AUSTIN) (0.19%)
DUININCK, INC. (3.25%)
Contract # 05133233
Totals 4268200.50 0.00 4355577.13 100.0

CountyKING
Highway US 82
From 1.210 MILES EAST OF US 83, EAST
To 0.599 MILES WEST OF SH 222
CSJ 0133-01-048
Proj ID NH 2016(614)
Work Type REHABILITATION OF EXISTING ROADWAY
 
12.052 5930781.41 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 136
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-01-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153042
Totals 5930781.41 0.00 0.00 0.0

CountyMOTLEY
Highway US 62 ETC
From FM 1380, E
To COTTLE C/L
CSJ 0146-01-048
Proj ID STP 2016(199)HES
Work Type CENTERLINE TEXTURING
 
104.334 699984.33 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0146-01-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153021
Totals 699984.33 0.00 0.00 0.0

CountyFOARD
Highway US 70
From 4.361 MI WEST OF CROWELL WCL, E
To CROWELL WCL
CSJ 0146-05-033
Proj ID STP 2015(059)
Work Type REHABILITATION OF EXISTING ROAD
 
4.361 4032532.41 0.00 4011645.49 99.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-09-14
Work Began 04-16-15
Work Completed  
Time Computed 10-25-14
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 100
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0146-05-033
WEST TEXAS RUMBLE STRIP(0.09%)
W.S. CONSTRUCTION COMPANY(0.71%)
TEXAS ALTERNATIVE GRASSER, INC.(0.52%)
DUSTROL, INC.(3.23%)
DUSTIN ALLEN, INC. (1.43%)
BARRICADES UNLIMITED (2.57%)
Contract # 09143229
Totals 4032532.41 0.00 4011645.49 99.4

CountyHALL
Highway SH 86
From 118 FT E OF CR 3
To SH 70
CSJ 0303-05-018
Proj ID STP 2014(473)
Work Type REHABILITATION OF EXISTING ROADWAY
 
0.616 2600383.20 78578.30 2862254.19 99.9
CountyHALL
Highway SH 86
From 118 FT E OF CR 3
To SH 70
CSJ 0303-05-019
Proj ID STP 1302(074)
Work Type ROW UTL. ADJ.
 
0.616 408330.05 0.00 409233.82 99.9
Work Order 05-01-14
Work Began 06-02-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 212
Addl Days Granted 8
Working Days Charged 172
Percent Time Used 78
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0303-05-018
ALAMO BROTHERS CONCRETE, INC.( 20.20%)
BARRICADES UNLIMITED (1.08%)
WEST TEXAS UTILITY CONTRACTORS, INC. ( 12.33%)
Contract # 03143216
Totals 3008713.25 78578.30 3271488.01 99.9

CountyBRISCOE
Highway SH 207
From 4538 FT NORTH OF FM146
To 1435 FT NORTH OF FM146
CSJ 0357-06-020
Proj ID STP 2014(868)HES
Work Type REALIGN INTERSECTIONS
 
1.293 1025196.80 209678.50 995686.07 97.1
CountyBRISCOE
Highway SH 207
From 1435 FT NORTH OF FM146
To 1222 FT SOUTH OF FM146
CSJ 0970-03-021
Proj ID STP 2014(869)HES
Work Type REALIGN INTERSECTIONS
 
0.503 169641.70 24998.97 141116.64 83.1
Work Order 09-30-14
Work Began 00-00-00
Work Completed  
Time Computed 10-16-14
Contract Working Days 102
Addl Days Granted 10
Working Days Charged 107
Percent Time Used 95
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0357-06-020
BARRICADES UNLIMITED (0.99%)
E. DIAZ TRUCKING (2.02%)
HJC FARMS, INC.(1.35%)
TEXAS ALTERNATIVE GRASSER, INC.(2.02%)
WILLIS ELECTRIC CO., LP(3.25%)
Contract # 07143232
Totals 1194838.50 234677.47 1136802.71 95.1

page 1 | page 2