Monthly State Let Construction Report For Corpus Christi District As Of Feb 10, 2017 Page 1 Of 4

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIVE OAK
HighwayIH 37
FromUS 281
ToATASCOSA COUNTY LINE
CSJ0073-07-060
Proj IDNH 1502(238)
Work TypeSPOT BASE REPAIR AND OVERLAY
 
11.0486295218.907377244.1299.9
Work Order07-15-15
Work Began03-11-16
Work Completed
Time Computed10-14-15
Contract Working Days136
Addl Days Granted27
Working Days Charged162
Percent Time Used99
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-07-060
ENVIRONMENTAL SAFETY SERVICES, INC. (0.87)
CHEROKEE SERVICES (0.51)
WEST TX RUMBLE STRIP (0.25)
FLASHER EQUIPMENT COMPANY (2.80)
Contract #06153047
Totals6295218.90437149.577377244.1299.9

CountyLIVE OAK
HighwayIH 37
From3 MI N. OF FM 2049
To5.5 MI N. OF FM 2049
CSJ0073-07-061
Proj IDSTP 1502(068)HES
Work TypeGRADE,BASE,SURF
 
40.73212504557.2212137003.2497.0
Work Order04-20-15
Work Began08-10-15
Work Completed
Time Computed05-21-15
Contract Working Days119
Addl Days Granted141
Working Days Charged251
Percent Time Used96
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-07-061
HIGHWAY BARRICADES AND SERVICES, LLC (0.22)
LONE STAR EROSION CONTROL (0.23)
MURRAY CONSTRUCTION (0.34)
ROADWAY SPECIALTIES, INC. (0.14)
COX PAVING COMPANY OF TEXAS, INC. (10.68)
DIAMOND SURFACE, INC. (0.28)
PAVEMENT MARKINGS INC. (1.87)
PRIMATE CONSTRUCTION, INC. (0.77)
Contract #03153202
Totals12504557.220.0012137003.2497.0

CountyLIVE OAK
HighwayIH 37
From3.022 MI S OF ATASCOSA CO LINE
ToATASCOSA CO LINE
CSJ0073-07-063
Proj IDSTP 1602(446)HES
Work TypeINSTALL MEDIAN BARRIER
 
3.022421488.150.000.0
CountyLIVE OAK
HighwayIH 37
From.883 MI N. OF US 59
To2.198 MI N. OF US 59
CSJ0074-01-053
Proj IDSTP 1602(447)
Work TypeINSTALL MEDIAN BARRIER
 
1.315192664.440.000.0
CountyLIVE OAK
HighwayIH 37
FromUS 59
To.883 MI N. OF US 59
CSJ0074-02-077
Proj IDSTP 1602(447)
Work TypeINSTALL MEDIAN BARRIER
 
0.883114010.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days81
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-07-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173023
Totals728162.740.000.000.0

CountyLIVE OAK ETC
HighwayIH 37
FromUS 59
ToSAN PAT COUNTY LINE
CSJ0074-02-070
Proj IDNH 2015(576)
Work TypeSPOT BASE REPAIR AND OVERLAY
 
24.8837901610.438687126.6799.9
Work Order03-18-15
Work Began10-01-15
Work Completed
Time Computed04-03-15
Contract Working Days170
Addl Days Granted126
Working Days Charged329
Percent Time Used111
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-02-070
MV HENKE COMPANY, LLC (0.10)
HIGHWAY BARRICADES AND SERVICES, LLC (3.83)
CHEROKEE SERVICES (0.41)
WEST TEXAS RUMBLE STRIP (0.21)
ROADWAY SPECIALTIES, INC. (1.07)
Contract #02153213
Totals7901610.4330435.008687126.6799.9

CountyLIVE OAK ETC
HighwayIH 37 ETC
FromLIVE OAK COUNTY LINE
ToFM 888
CSJ0074-02-079
Proj IDNH 2017(219)
Work TypeSEAL C008907148AY
 
182.0135498583.780.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-07-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0074-02-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163225
Totals5498583.780.000.000.0

CountyNUECES
HighwayIH 37
FromSH 358
ToSOUTHERN MINERALS
CSJ0074-06-226
Proj IDNH 1602(215)
Work TypeMILL, SEAL AND OVERALY
 
2.2006667563.5735805.000.5
Work Order12-06-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-226
CHEROKEE SERVICES (0.57)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.03)
HAAS-ANDERSON CONSTRUCTION, LTD. (1.79)
HIGHWAY BARRICADES AND SERVICES, LLC (1.07)
N-LINE TRAFFIC MAINTENANCE, L.P. (2.22)
S.A. CONCEPTS CONSTRUCTION (4.58)
SOIL-TECH, INC. (0.08)
THE LEVY COMPANY, L.P. (2.02)
WEBBER BARRIER SERVICES, LLC. (0.74)
Contract #07163023
Totals6667563.5735805.0035805.000.5

CountyJIM WELLS
HighwayFM 665
From15OOFT W. OF FM 1931
ToINTERSECTION OF FM 1931
CSJ0086-19-031
Proj IDSTP 2016(960)
Work TypeWIDEN EXISTING BRIDGE
 
0.290642139.91248711.8838.7
Work Order06-08-16
Work Began09-19-16
Work Completed
Time Computed07-08-16
Contract Working Days124
Addl Days Granted0
Working Days Charged76
Percent Time Used61
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0086-19-031
HIGHWAY BARRICADES AND SERVICES, LLC (3.00)
FUQUAY, INC. (1.91)
W. W. FOUNDATION DRILLING, LTD. (10.83)
Contract #04163221
Totals642139.9133342.18248711.8838.7

CountyBEE
HighwayUS 59
FromBEE COUNTY LINE
To5 LANE SECTION
CSJ0088-01-067
Proj IDNH 1602(586)
Work TypeHOT RUBBER SEAL
 
43.4353243062.350.000.0
Work Order08-23-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days88
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0088-01-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07163240
Totals3243062.350.000.000.0

CountyKARNES
HighwayUS 181
FromFM 1144
ToCONTROL BREAK AT (2MI NO OF CR368)
CSJ0100-05-075
Proj IDNH 1502(571)
Work TypeREHAB ROADWAY
 
2.0205184264.933618558.8369.7
CountyKARNES
HighwayUS 181
FromCONTROL BREAK (.2MI N OF CR 638)
ToUS 181-G
CSJ0100-06-062
Proj IDNH 1502(571)
Work TypeREHAB ROADWAY
 
4.5006800161.933857141.8156.7
Work Order11-10-15
Work Began02-01-16
Work Completed
Time Computed10-01-15
Contract Working Days284
Addl Days Granted0
Working Days Charged210
Percent Time Used73
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-05-075
CHEROKEE SERVICES (0.13)
COWBELL TRAFFIC SERVICES, INC. (0.18)
COX PAVING COMPANY OF TEXAS, INC. (6.30)
LONE STAR EROSION CONTROL (0.18)
MURRAY CONSTRUCTION (0.13)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.51)
ROADWAY SPECIALTIES, INC. (1.56)
PERFORMANCE EQUIPMENT SERVICE (0.18)
Contract #08153010
Totals11984426.8689881.387475700.6462.3

CountyKARNES
HighwayUS 181
FromCR 151
ToBEE COUNTY LINE
CSJ0100-06-064
Proj IDNH 2017(302)
Work TypeGRADE,BASE,SURF
 
6.6801182121.810.000.0
CountyBEE
HighwayUS 181
FromKARNES COUNTY LINE
To.3 MI S. OF KING LN
CSJ0100-07-049
Proj IDNH 2017(302)
Work TypeGRADE,BASE,SURF
 
8.500974975.300.000.0
CountyBEE
HighwayUS 181
From.3 MI S OF KING LN
ToBU 181J
CSJ0100-08-094
Proj IDNH 2017(302)
Work TypeGRADE,BASE,SURF
 
5.410578543.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-17-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days48
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-06-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163031
Totals2735640.960.000.000.0

CountyNUECES
HighwayUS 181
FromAT US 181 NUECES BAY CAUSEWAY
To.
CSJ0101-06-110
Proj IDBR 1502(572)
Work TypeCONCRETE STRUCTURE REPAIR
 
0.2001496152.321509998.2699.9
Work Order09-11-15
Work Began02-29-16
Work Completed
Time Computed10-11-15
Contract Working Days119
Addl Days Granted70
Working Days Charged169
Percent Time Used89
Contractor(s)
IHS CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0101-06-110
HIGHWAY BARRICADES AND SERVICES, LLC (0.32)
NATIONAL MARINE DIVING SERVICES (22.93)
Contract #08153045
Totals1496152.323152.401509998.2699.9

CountyNUECES
HighwaySH 44
FromW. END OF CLARKWOOD RELIEF ROUTE
ToWEST OF FM 3386
CSJ0102-01-106
Proj IDNH 2013(751)
Work TypeGRADE,BASE,S URF,STRS
 
1.14616390152.9613249449.9980.8
Work Order09-11-15
Work Began01-04-16
Work Completed
Time Computed09-01-15
Contract Working Days356
Addl Days Granted0
Working Days Charged240
Percent Time Used67
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-01-106
HIGHWAY BARRICADES AND SERVICES, LLC (0.59)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.07)
WEBBER BARRIER SERVICES, LLC. (0.89)
SCOTT DERR PAINTING CO, LLC (0.20)
K.L. DURHAM CONSTRUCTION, LLC (0.41)
STAR OPERATIONS, INC. (2.14)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.97)
D & S TEXAS ICON CONSTRUCTION, LLC. (0.62)
CABCOS CONTRACTORS LLC (2.53)
MCL CONTRACTING, LLC (0.05)
D & C CONCRETE CUTTING, INC. (0.08)
GUERRA UNDERGROUND, LLC (0.52)
NATIONAL POWER RODDING GROUP (0.07)
Contract #07153007
Totals16390152.961204054.3913249449.9980.8

CountyNUECES
HighwayUS 77
FromFM 892
ToS OF CR 28
CSJ0102-02-096
Proj IDC 102-2-96
Work TypeGRADE,BASE,SURF,STRS
 
4.03938721708.4314818213.2638.2
Work Order12-17-13
Work Began01-04-16
Work Completed
Time Computed09-01-13
Contract Working Days527
Addl Days Granted0
Working Days Charged228
Percent Time Used43
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-02-096
IOC COMPANY LLC (5.78)
PANTHER CREEK TRANSPORTATION, INC. (3.94)
K.L. DURHAM CONSTRUCTION, LLC (0.25)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.45)
HIGHWAY BARRICADES AND SERVICES, LLC (0.71)
LAYFIELD CONSTRUCTION, INC (0.47)
ACTION CONSTRUCTORS (3.28)
SHINN & GREGORY, INC. (0.85)
MICA CORPORATION (1.75)
MCL CONTRACTING, LLC (0.19)
SOIL-TECH, INC. (0.85)
Contract #07133202
Totals38721708.43485405.8614818213.2638.2

CountyKLEBERG
HighwayUS 77
FromSH 285
ToEND OF FIVE LANE SECTION
CSJ0102-04-104
Proj IDNH 2017(156)
Work TypeMILL AND OVERLAY
 
1.4901551557.310.000.0
CountyKLEBERG
HighwayUS 77
FromSH 285
ToKENEDY COUNTY LINE
CSJ0327-01-032
Proj IDNH 2017(156)
Work TypeMILL AND OVERLAY
 
2.0401765567.340.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-17-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0102-04-104
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163216
Totals3317124.650.000.000.0

CountyKLEBERG
HighwaySH 285
FromUS 77
ToBROOKS COUNTY LINE
CSJ0102-06-030
Proj IDSTP 2015(495)
Work TypeMILL, FILL MAINLANES, SC FULL WIDTH
 
12.10011207164.4611497354.9199.9
CountyKLEBERG
HighwaySH 285
From4.9 MI E OF FM 2191
To0.3 MI W OF US 77
CSJ0102-06-031
Proj IDSTP 2015(638)HES
Work TypeTEXTURIZE SHLDRS, CENTERLINE TEXTUR
 
11.80079213.9871533.7790.3
Work Order03-18-15
Work Began04-28-15
Work Completed
Time Computed04-03-15
Contract Working Days162
Addl Days Granted122
Working Days Charged366
Percent Time Used128
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0102-06-030
HIGHWAY BARRICADES AND SERVICES, LLC (2.31)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.89)
DUSTROL, INC. (3.53)
ALTUS TRAFFIC MANAGEMENT LLC (0.21)
TREV-CORT TRUCKING INC (1.45)
CEDOSCA CONSTRUCTION, LLC (0.00)
WEST TEXAS RUMBLE STRIP (0.15)
IZAGUIRRE CONSTRUCTION (0.21)
Contract #01153216
Totals11286378.4416200.5711568888.6899.9

CountyGOLIAD ETC
HighwayUS 183
FromFRANKLIN ST.
ToSH 239
CSJ0155-04-051
Proj IDSTP 2015(887)
Work TypeMILL AND INLAY
 
44.0414784121.154542254.6695.5
Work Order10-21-15
Work Began01-07-16
Work Completed
Time Computed11-01-15
Contract Working Days114
Addl Days Granted0
Working Days Charged142
Percent Time Used124
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0155-04-051
ALL MATERIALS CONSTRUCTION, LLC (0.71)
CHEROKEE SERVICES (0.32)
COX PAVING COMPANY OF TEXAS, INC. (17.51)
FUQUAY, INC. (0.07)
INTERSTATE BARRICADES & MARKINGS, INC. (0.36)
ROADSAFE TRAFFIC SYSTEMS, INC. (4.19)
PENHALL COMPANY (0.04)
Contract #09153214
Totals4784121.1541639.984542254.6695.5

CountyREFUGIO
HighwayUS 183
From4 MILES N OF SH 202
ToUS 77
CSJ0155-05-039
Proj IDSTP 1502(433)
Work TypeGRADE,BASE SURF
 
1.7006324506.656001101.2994.8
Work Order12-21-15
Work Began07-01-16
Work Completed
Time Computed01-01-16
Contract Working Days153
Addl Days Granted0
Working Days Charged128
Percent Time Used83
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0155-05-039
FUQUAY, INC. (0.07)
HIGHWAY BARRICADES AND SERVICES, LLC (0.90)
Contract #11153030
Totals6324506.65332376.606001101.2994.8

CountyARANSAS
HighwaySH 35
From549 FT. S OF PR13
To1 MI. N. OF PR13
CSJ0180-03-035
Proj IDSTP 1102(113)
Work TypeGR,BS,SURF
 
1.0005196117.408864188.6299.9
CountyARANSAS
HighwaySH 35
FromN OF COPANO BAY CAUSEWAY
ToS OF COPANO BAY CAUSEWAY
CSJ0180-04-083
Proj IDBR 1102(114)
Work TypeREPLACE EXISTING BRIDGE & REWK APRO
 
2.08792966472.6590545336.5097.3
Work Order06-15-11
Work Began08-03-11
Work Completed
Time Computed11-14-11
Contract Working Days968
Addl Days Granted543
Working Days Charged1,496
Percent Time Used99
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0180-03-035
HAAS - ANDERSON CONSTRUCTION, INC. (0.27)
INTERSTATE BARRICADES & MARKINGS, INC. (0.21)
SCOTT DERR PAINTING CO (0.28)
STAR OPERATIONS, INC. (0.45)
A.Z. REBAR CONSTRUCTION, INC. (5.74)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09)
ROADWAY SPECIALTIES, INC. (0.16)
LAND SOLUTIONS CONSTRUCTION, LLC (0.15)
ROADWAY CONSTRUCTION, INC. (0.77)
ARROW DIRECTIONAL DRILLING, INC. (0.00)
Contract #05113234
Totals98162590.05816542.5299409525.1299.9

CountyARANSAS
HighwayBS 35-L
From0.32 MI E OF FM 2165
ToFM 1069
CSJ0180-05-064
Proj IDSTP 2017(631)HES
Work TypeIMPROVE TRAFFIC SIGNAL, INTER. SIG
 
0.532265591.550.000.0
CountyLIVE OAK
HighwayUS 281
From.5 MI N OF BU 59
To.5 MI S OF US 59
CSJ0254-01-143
Proj IDSTP 2017(632)HES
Work TypeIMPROVE TRAFFIC SIGNAL, INTER. SIGN
 
1.504165028.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days154
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0180-05-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173209
Totals430619.900.000.000.0

CountySAN PATRICIO
HighwaySH 35
FromFM 1069
ToSH 361
CSJ0180-06-101
Proj IDSTP 2017(304)
Work TypeHOT RUBBER SEAL
 
6.724831061.200.000.0
CountyJIM WELLS
HighwayUS 281
FromSH 141
ToFM 2508
CSJ0255-01-086
Proj IDNH 2017(303)
Work TypeHOT RUBBER SEAL
 
6.668407473.200.000.0
CountySAN PATRICIO
HighwaySH 188
FromIH 37
ToFM 630
CSJ1208-01-027
Proj IDSTP 2017(304)
Work TypeHOT RUBBER SEAL
 
10.652639877.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-17-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0180-06-101
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163007
Totals1878411.950.000.000.0

page 1 | page 2 | page 3 | page 4