Monthly State Let Construction Report For Corpus Christi District As Of Apr 10, 2015 Page 1 Of 3

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLIVE OAK
Highway IH 37
From 3 MI N. OF FM 2049
To 5.5 MI N. OF FM 2049
CSJ 0073-07-061
Proj ID STP 1502(068)HES
Work Type GRADE, BASE, SURF
 
40.732 12504557.22 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-07-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153202
Totals 12504557.22 0.00 0.00 0.0

CountyLIVE OAK
Highway US 281A ETC
From ATASC0SA COUNTY LINE
To IH 37
CSJ 0073-14-007
Proj ID STP 2015(200)
Work Type DISTRICT WIDE SEAL COAT PROJECT
 
211.349 11208531.14 753897.53 1304764.93 11.6
Work Order 01-27-15
Work Began 00-00-00
Work Completed  
Time Computed 02-12-15
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0073-14-007
FLASHER EQUIPMENT COMPANY(0.99%)
VIZCAINO, L.P. ( 12.31%)
Contract # 10143204
Totals 11208531.14 753897.53 1304764.93 11.6

CountyLIVE OAK
Highway IH 37
From US 59
To SAN PAT COUNTY LINE
CSJ 0074-02-070
Proj ID NH 2015(576)
Work Type SPOT BASE REPAIR AND OVERLAY
 
24.883 7901610.43 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-15
Work Began 00-00-00
Work Completed  
Time Computed 04-03-15
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-02-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153213
Totals 7901610.43 0.00 0.00 0.0

CountyLIVE OAK
Highway IH 37
From .7 MI N OF US 59 INTERS.
To SAN PATRICIO COUNTY LINE
CSJ 0074-02-072
Proj ID NH 2015(883)
Work Type NOVACHIP ROADWAY
 
17.785 3901795.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-02-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153026
Totals 3901795.11 0.00 0.00 0.0

CountySAN PATRICIO
Highway IH 37 ETC
From 2.886 MI. N. OF CR 1136 (CONTROL BR
To LIVE OAK COUNTY LINE
CSJ 0074-03-041
Proj ID IM 0371(137)
Work Type MILL, SEAL AND OVERLAY
 
31.906 8894788.55 0.00 0.00 0.0
Work Order 04-15-14
Work Began 00-00-00
Work Completed  
Time Computed 05-01-14
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-03-041
COWBELL TRAFFIC SERVICE, INC.(0.56%)
D & S TEXAS ICON CONSTRUCTION, LLC.(0.24%)
MPB, INC.(0.95%)
PERFORMANCE EQUIPMENT SERVICE(2.98%)
HIGHWAY BARRICADES AND SERVICES, LLC (3.67%)
BLACKTOPPER TECHNOLOGY, INC. ( 14.44%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.33%)
Contract # 02143202
Totals 8894788.55 0.00 0.00 0.0

CountySAN PATRICIO
Highway IH 37
From LIVE OAK COUNTY LINE
To 2.866 N OF SH 188 (CONTROL BREAK)
CSJ 0074-03-042
Proj ID NH 2015(884)
Work Type MILL, SEAL AND OVERLAY
 
5.470 1979318.56 0.00 0.00 0.0
CountySAN PATRICIO
Highway IH 37
From 2.866 MI N OF SH 188 (CONTR BREAK)
To SH 188
CSJ 0074-04-042
Proj ID NH 2015(884)
Work Type MILL, SEAL AND OVERLAY
 
2.800 1215762.09 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-03-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153235
Totals 3195080.65 0.00 0.00 0.0

CountyNUECES
Highway IH 37
From NUECES BAY BLVD
To SH 358
CSJ 0074-06-222
Proj ID NH 2015(885)
Work Type MILL, UNDERSEAL AND OVERLAY
 
2.500 5938687.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-222
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153030
Totals 5938687.40 0.00 0.00 0.0

CountyJIM WELLS
Highway SH 44
From US 281
To .148 MI. S. OF FM 1554 CONTROL BRK.
CSJ 0086-11-043
Proj ID HP 2013(115)
Work Type TRAFFIC SIGNAL IMPROVEMENTS
 
1.208 256420.05 0.00 229025.81 100.0
CountyJIM WELLS
Highway SH 44
From .148 MI S. OF FM1554 CONTROL BREAK
To DR. N. W. ATKINSON BLVD.
CSJ 0087-01-102
Proj ID HP 2013(115)
Work Type TRAFFIC SIGNAL IMPROVEMENTS
 
3.555 786264.40 0.00 746040.35 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-28-12
Work Began 05-02-13
Work Completed 12-31-14
Time Computed 12-14-12
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 152
Percent Time Used 104
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-11-043
FLASHER EQUIPMENT COMPANY(1.18%)
Contract # 10123009
Totals 1042684.45 0.00 975066.16 100.0

CountyJIM WELLS
Highway FM 665
From FM 1352
To O.284 MI. EAST OF CR 344
CSJ 0086-19-030
Proj ID STP 2014(895)
Work Type GRADE, BASE, SURF, STRS
 
2.638 2878085.20 89812.23 925835.20 32.1
Work Order 09-30-14
Work Began 10-20-14
Work Completed  
Time Computed 10-16-14
Contract Working Days 112
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 59
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0086-19-030
HIGHWAY BARRICADES AND SERVICES, LLC (2.03%)
JHABORES CONSTRUCTION CO, INC. ( 11.54%)
A BROTHERS MILLING, LLC(1.96%)
MURRAY CONSTRUCTION(0.73%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.76%)
Contract # 07143226
Totals 2878085.20 89812.23 925835.20 32.1

CountyJIM WELLS
Highway SH 44
From APPROX. 0.15 MI E. OF FM 1554
To SH 359
CSJ 0087-01-103
Proj ID NH 2013(555)
Work Type OVERLAY, SEAL & FULL - DEPTH REPAIR
 
2.269 3877169.75 0.00 4086907.45 100.0
CountyNUECES
Highway SH 44
From NUECES/JIM WELLS CO. LINE
To AGUA DULCE
CSJ 0373-03-052
Proj ID NH 2013(555)
Work Type GRADE, BASE, SURF
 
1.069 900128.37 0.00 890702.20 100.0
CountyJIM WELLS
Highway SH 44
From SH 359, EAST
To JIM WELLS/NUECES COUNTY LINE
CSJ 0373-04-034
Proj ID NH 2013(555)
Work Type GRADE, BASE, SURF
 
5.192 3759636.15 0.00 3547034.18 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-13
Work Began 08-01-13
Work Completed 11-13-14
Time Computed 07-17-13
Contract Working Days 124
Addl Days Granted 12
Working Days Charged 171
Percent Time Used 125
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0087-01-103
HIGHWAY BARRICADES AND SERVICES, LLC (3.10%)
MURRAY CONSTRUCTION(0.35%)
R.P.V. CONSTRUCTION(2.52%)
PENNTEX MILLING, LLC (1.99%)
PRIMATE CONSTRUCTION, INC. (0.12%)
PENHALL COMPANY(0.13%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.89%)
Contract # 04133022
Totals 8536934.27 0.00 8524643.83 100.0

CountyJIM WELLS
Highway SH 44
From FM 1931 (FLOURNOY RD.)
To SAN FERNANDO CREEK
CSJ 0087-01-104
Proj ID NH 2014(565)
Work Type PAVEMENT REPAIR & RAISED MEDIAN
 
1.095 3126804.84 198068.66 2296232.43 73.4
Work Order 06-20-14
Work Began 09-22-14
Work Completed  
Time Computed 07-06-14
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 77
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0087-01-104
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (7.23%)
HIGHWAY BARRICADES AND SERVICES, LLC (3.63%)
SOIL-TECH, INC.(5.16%)
SOUTHERN LANDSCAPES(1.42%)
Contract # 04143012
Totals 3126804.84 198068.66 2296232.43 73.4

CountyJIM WELLS
Highway SH 359 ETC
From 0.5 MI N OF SH 44
To 0.3 MI N OF CR 325 (CONTROL BREAK)
CSJ 0087-01-105
Proj ID STP 2015(891)HES
Work Type TEXTURIZE SHLDRS, CENTERLINE TEXTUR
 
67.663 690908.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-15
Work Began 00-00-00
Work Completed  
Time Computed 05-08-15
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 0087-01-105
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153037
Totals 690908.10 0.00 0.00 0.0

CountyKARNES
Highway US 181
From 1.761 MI S. OF US 181-G
To KARNES/BEE COUNTY LINE
CSJ 0100-06-059
Proj ID NH 2013(253)
Work Type GRADE, BASE, SURF, STRS
 
6.682 3346386.76 0.00 3899636.46 100.0
CountyBEE
Highway US 181
From KARNES/BEE COUNTY LINE
To S. OF FM 1465
CSJ 0100-07-046
Proj ID NH 2013(253)
Work Type GRADE, BASE, SURF, STRS
 
8.500 3886662.76 0.00 4015503.24 100.0
CountyBEE
Highway US 181
From S. OF FM 1465
To 0.10 MI N. OF CR 104
CSJ 0100-08-089
Proj ID C 100-8-89
Work Type GRADE, BASE, SURF, STRS
 
1.877 1330284.02 0.00 1448489.88 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-22-13
Work Began 03-10-13
Work Completed 10-14-14
Time Computed 03-10-13
Contract Working Days 173
Addl Days Granted 62
Working Days Charged 233
Percent Time Used 99
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-06-059
DUSTROL, INC.(0.16%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.11%)
MURRAY CONSTRUCTION(0.63%)
ROADWAY SPECIALTIES, INC.(5.93%)
VEGETATION MANAGEMENT SERVICES, LLC(0.33%)
BRANNAN PAVING CO., LTD. (6.54%)
Contract # 12123004
Totals 8563333.54 0.00 9363629.58 100.0

CountyBEE
Highway US 181
From SH 359
To 1 MI SOUTH (CONTROL BREAK)
CSJ 0101-01-066
Proj ID STP 2015(886)
Work Type GRADE, BASE, SURF
 
0.965 58120.86 0.00 0.00 0.0
CountyBEE
Highway US 181
From 1 MI SOUTH SH 359 (CONTROL BREAK)
To SAN PATRICIO COUNTY LINE
CSJ 0101-02-035
Proj ID STP 2015(886)
Work Type MILL, SEAL AND OVERLAY, BASE REPAIR
 
10.370 4030242.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 69
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0101-01-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153006
Totals 4088363.68 0.00 0.00 0.0

CountySAN PATRICIO
Highway US 181
From FM 893
To NUECES BAY CAUSEWAY (CO.LINE)
CSJ 0101-05-035
Proj ID NH 1502(060)
Work Type OVERLAY ROADWAY
 
2.379 1689178.70 0.00 0.00 0.0
CountySAN PATRICIO
Highway SH 361
From END OF DIVIDED SECTION
To FM 1069
CSJ 0180-10-076
Proj ID NH 1502(060)
Work Type MILL, OVERLAY, BASE REPAIR
 
0.200 325780.10 0.00 0.00 0.0
CountyREFUGIO
Highway US 77
From REFUGIO S. CITY LIMITS
To 0.362 M. N OF FM 2441
CSJ 0371-03-116
Proj ID NH 1502(060)
Work Type MILL, SEAL AND OVERLAY
 
0.100 1247999.10 0.00 0.00 0.0
CountySAN PATRICIO
Highway US 77
From 0.68 M SOUTH OF BS 77T
To 0.65 MI. N OF SH 188
CSJ 0371-04-060
Proj ID NH 1502(060)
Work Type GRADE, BASE, SURF
 
1.800 2030820.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0101-05-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153236
Totals 5293778.15 0.00 0.00 0.0

CountyNUECES
Highway US 77
From SH 44
To FM 892
CSJ 0102-02-095
Proj ID HP 2012(652)
Work Type GRADE, BASE, SURF, STRS
 
1.116 11246983.53 106730.71 9341707.69 83.0
Work Order 09-13-12
Work Began 01-16-13
Work Completed  
Time Computed 09-29-12
Contract Working Days 319
Addl Days Granted 69
Working Days Charged 385
Percent Time Used 99
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-02-095
WEBBER BARRIER SERVICES, INC.(3.22%)
TROUT TRUCKING_COMPANY INC.(5.57%)
STAR OPERATIONS, INC.(2.23%)
FARR FOUNDATION, INC.(2.77%)
RICE ENVIRONMENTAL SERVICES(0.52%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.79%)
PENNTEX MILLING, LLC (0.64%)
SCOTT DERR PAINTING CO, LLC(0.03%)
PERFORMANCE EQUIPMENT SERVICE(0.17%)
MURRAY CONSTRUCTION(0.19%)
Contract # 07123207
Totals 11246983.53 106730.71 9341707.69 83.0

CountyNUECES
Highway US 77
From FM 892
To S OF CR 28
CSJ 0102-02-096
Proj ID C 102-2-96
Work Type GRADE, BASE, SURF, STRS
 
4.039 38721708.43 586868.03 2083970.75 5.3
Work Order 12-17-13
Work Began 00-00-00
Work Completed  
Time Computed 09-01-13
Contract Working Days 527
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-02-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07133202
Totals 38721708.43 586868.03 2083970.75 5.3

CountyNUECES
Highway SH 44
From AT FM 1694/SH 44 INTERSECTION
To .
CSJ 0102-02-099
Proj ID NH 2013(656)
Work Type GRADE, BASE, SURF, STRS
 
0.756 12713097.88 529968.00 12357869.15 97.2
Work Order 07-31-13
Work Began 09-25-13
Work Completed  
Time Computed 08-16-13
Contract Working Days 302
Addl Days Granted 0
Working Days Charged 280
Percent Time Used 92
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-02-099
PRIMATE CONSTRUCTION, INC. (0.05%)
WEBBER BARRIER SERVICES, LLC.(1.04%)
D&S TEXAS ICON CONSTRUCTION, LLC (0.51%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.72%)
D & C CONCRETE CUTTING, INC. (0.32%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.93%)
BEAVER CONTRACTORS, LLC(5.68%)
SCOTT DERR PAINTING CO, LLC(0.34%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.50%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(1.72%)
BEDO CONSTRUCTION PRODUCTS, INC. (4.21%)
CP REBAR AND PT INSTALLATION (0.14%)
CABCOS CONTRACTORS LLC (2.46%)
CERTIFIED PLACERS LLC(0.15%)
TEX OP CONSTRUCTION, LP(0.63%)
ADVANCED PUMPING, LLC(0.03%)
Contract # 05133203
Totals 12713097.88 529968.00 12357869.15 97.2

CountyKLEBERG
Highway US 77
From S. OF SH 141
To N. OF FM 425
CSJ 0102-04-095
Proj ID NH 2012(313)
Work Type GRAD, BASE.SURF.STRS
 
0.798 14562421.93 0.00 14859709.78 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-12
Work Began 10-24-12
Work Completed 01-05-15
Time Computed 07-02-12
Contract Working Days 352
Addl Days Granted 47
Working Days Charged 399
Percent Time Used 100
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-04-095
HIGHWAY TECHNOLOGIES, INC. (0.31%)
WEST TEXAS RUMBLE STRIP(0.03%)
WEBBER BARRIER SERVICES, INC.(1.36%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(0.63%)
SOIL-TECH, INC.(0.85%)
MURRAY CONSTRUCTION(0.36%)
FLASHER EQUIPMENT COMPANY(0.73%)
DUSTROL, INC.(0.45%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.03%)
KELLYSTONE, INC(0.48%)
SCOTT DERR PAINTING CO, LLC(0.48%)
W. W. FOUNDATION DRILLING, LTD.(0.50%)
TRIPLE J CONSTRUCTION, LTD (1.92%)
STAR OPERATIONS, INC.(1.59%)
TAHOE TRUCKING, INC. (5.69%)
D & C CONCRETE CUTTING, INC. (0.01%)
LHOIST NORTH AMERICA (1.39%)
CABCOS CONTRACTORS LLC (0.72%)
Contract # 04123001
Totals 14562421.93 0.00 14859709.78 100.0

CountyKLEBERG
Highway SH 285
From US 77
To BROOKS COUNTY LINE
CSJ 0102-06-030
Proj ID STP 2015(495)
Work Type MILL, FILL MAINLANES, SC FULL WIDTH
 
12.100 11207164.46 0.00 0.00 0.0
CountyKLEBERG
Highway SH 285
From 4.9 MI E OF FM 2191
To 0.3 MI W OF US 77
CSJ 0102-06-031
Proj ID STP 2015(638)HES
Work Type TEXTURIZE SHLDRS, CENTERLINE TEXTUR
 
11.800 79213.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-15
Work Began 00-00-00
Work Completed  
Time Computed 04-03-15
Contract Working Days 162
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0102-06-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153216
Totals 11286378.44 0.00 0.00 0.0

page 1 | page 2 | page 3