Monthly State Let Maintenance Report For Houston District As Of Apr 11, 2014 Page 1 Of 4

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGALVESTON
Highway SH0087
From GALVESTON FERRY LANDING
To BOLIVAR FERRY LANDING
CSJ 6195-11-001
Proj ID EMC - 619511001
Work Type EMERGENCY DOLPHIN REPAIRS
 
1.000 2872775.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6195-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06091240
Totals 2872775.00 0.00 0.00 0.0

CountyGALVESTON
Highway IH0045
From GALVESTON CAUSEWAY
To GALVESTON CAUSEWAY
CSJ 6204-78-001
Proj ID RMC - 620478001
Work Type FENDER SYSTEM REPAIR
 
0.001 632077.00 0.00 1294369.08 99.9
Work Order 04-06-10
Work Began 08-15-11
Work Completed  
Time Computed 05-01-10
Contract Working Days 730
Addl Days Granted 120
Working Days Charged 847
Percent Time Used 99
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6204-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01104022
Totals 632077.00 0.00 1294369.08 99.9

CountyGALVESTON
Highway SH0087
From GALVESTON FERRY LANDING
To BOLIVAR FERRY LANDING
CSJ 6222-92-001
Proj ID RMC - 622292001
Work Type REPAIR OF MARINE EQUIPMENT
 
1.000 1461125.00 0.00 1777975.65 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-16-12
Work Began 04-02-12
Work Completed  
Time Computed 04-02-12
Contract Working Days 731
Addl Days Granted 36
Working Days Charged 729
Percent Time Used 95
Contractor(s)
RUSSELL MARINE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6222-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01124019
Totals 1461125.00 0.00 1777975.65 99.9

CountyHARRIS
Highway SH0225
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6232-56-001
Proj ID RMC - 623256001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 674600.00 0.00 551970.01 86.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-22-12
Work Began 07-01-12
Work Completed  
Time Computed 07-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 639
Percent Time Used 87
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6232-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05124006
Totals 674600.00 0.00 551970.01 86.4

CountyWALLER
Highway US0290
From VARIOUS HIGHWAYS IN WALLER COUNTY
To VARIOUS HIGHWAYS IN WALLER COUNTY
CSJ 6233-59-001
Proj ID RMC - 623359001
Work Type BRIDGE DECK REPAIR
 
0.001 243350.00 0.00 260825.56 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-13-12
Work Began 07-02-12
Work Completed  
Time Computed 06-18-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 652
Percent Time Used 89
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6233-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03124010
Totals 243350.00 0.00 260825.56 99.9

CountyGALVESTON
Highway FM0518
From FM 518: RIVERSIDE DR TO 0.095 MI. EAST
To FM 2351: MELODY LN TO ROYAL CT
CSJ 6234-52-001
Proj ID RMC - 623452001
Work Type STORM DRAINAGE REPAIR
 
0.001 565064.94 0.00 419816.22 87.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-12-13
Work Began 11-18-13
Work Completed  
Time Computed 11-18-13
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 108
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6234-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06134007
Totals 565064.94 0.00 419816.22 87.7

CountyMONTGOMERY
Highway US0059
From VARIOUS HWYS IN MONTGOMERY COUNTY
To VARIOUS HWYS IN MONTGOMERY COUNTY
CSJ 6235-99-001
Proj ID RMC - 623599001
Work Type ROADSIDE MOWING
 
0.001 528983.24 0.00 301557.94 57.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-08-12
Work Began 11-19-12
Work Completed  
Time Computed 11-19-12
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 26
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6235-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08124037
Totals 528983.24 0.00 301557.94 57.0

CountyHARRIS
Highway IH0045
From SH 87
To WALKER/MONTGOMERY COUNTY LINE
CSJ 6236-65-001
Proj ID RMC - 623665001
Work Type ROUTINE MAINTENANCE OF IH 45
 
100.810 26974243.67 915798.29 6801610.03 26.2
Work Order 08-01-12
Work Began 08-01-12
Work Completed  
Time Computed 08-01-12
Contract Working Days 1,826
Addl Days Granted 0
Working Days Charged 549
Percent Time Used 30
Contractor(s)
TRANSFIELD SERVICES INFRASTRUCTURE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6236-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06124003
Totals 26974243.67 915798.29 6801610.03 26.2

CountyHARRIS
Highway SH0225
From VARIOUS HWYS IN EAST HARRIS COUNTY
To VARIOUS HWYS IN EAST HARRIS COUNTY
CSJ 6238-48-001
Proj ID RMC - 623848001
Work Type FULL DEPTH CONCRETE REPAIR
 
0.001 752350.00 0.00 545066.32 77.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-12
Work Began 11-01-12
Work Completed  
Time Computed 11-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 516
Percent Time Used 70
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6238-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06124010
Totals 752350.00 0.00 545066.32 77.0

CountyHARRIS
Highway IH0010
From HARRIS/CHAMBERS COUNTY LINE
To FM 3538 (CANE BELT) OVERPASS
CSJ 6239-72-001
Proj ID RMC - 623972001
Work Type GENERAL MAINTENANCE CONTRACT
 
0.001 2336927.73 0.00 2741871.18 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-20-12
Work Began 12-01-12
Work Completed  
Time Computed 12-01-12
Contract Working Days 274
Addl Days Granted 242
Working Days Charged 486
Percent Time Used 94
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6239-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10124010
Totals 2336927.73 0.00 2741871.18 99.9

CountyHARRIS
Highway US0059
From CENTRAL HARRIS COUNTY
To .
CSJ 6239-73-001
Proj ID RMC - 623973001
Work Type GENERAL MAINTENANCE CONTRACT
 
0.001 2111402.80 0.00 2457992.58 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-29-12
Work Began 12-01-12
Work Completed  
Time Computed 12-01-12
Contract Working Days 274
Addl Days Granted 273
Working Days Charged 486
Percent Time Used 88
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6239-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10124011
Totals 2111402.80 0.00 2457992.58 99.9

CountyHARRIS
Highway IH0610
From CENTRAL HARRIS COUNTY
To .
CSJ 6239-74-001
Proj ID RMC - 623974001
Work Type GEN ROUT MNT OF IH 610, ETC.
 
0.001 1843965.01 0.00 2522924.47 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-29-12
Work Began 12-01-12
Work Completed  
Time Computed 12-01-12
Contract Working Days 274
Addl Days Granted 273
Working Days Charged 486
Percent Time Used 88
Contractor(s)
TEXAS HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6239-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10124012
Totals 1843965.01 0.00 2522924.47 99.9

CountyHARRIS
Highway LP0008
From VARIOUS HWYS IN SOUTH HARRIS COUNTY
To VARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ 6242-96-001
Proj ID RMC - 624296001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 659900.00 24600.00 419250.00 63.5
Work Order 10-24-12
Work Began 11-01-12
Work Completed  
Time Computed 11-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 516
Percent Time Used 70
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6242-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08124013
Totals 659900.00 24600.00 419250.00 63.5

CountyHARRIS
Highway US0290
From VARIOUS HIGHWAYS IN WEST HARRIS CO.
To .
CSJ 6243-38-001
Proj ID RMC - 624338001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 640420.00 0.00 411800.70 65.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-01-12
Work Began 10-01-12
Work Completed  
Time Computed 10-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 547
Percent Time Used 74
Contractor(s)
PANNELL INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6243-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07124021
Totals 640420.00 0.00 411800.70 65.6

CountyHARRIS
Highway IH0010
From VARIOUS HWYS HOUSTON DISTRICT
To VARIOUS HWYS HOUSTON DISTRICT
CSJ 6244-29-001
Proj ID RMC - 624429001
Work Type MAINT OF TRAFFIC SIGNALS
 
0.001 1189845.00 0.00 1091296.80 97.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-13-12
Work Began 11-14-12
Work Completed  
Time Computed 11-14-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 503
Percent Time Used 68
Contractor(s)
LINDSEY ELECTRIC, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6244-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09124006
Totals 1189845.00 0.00 1091296.80 97.3

CountyFORT BEND
Highway US0059
From VARIOUS AREAS OF US 59
To VARIOUS AREAS OF US 59
CSJ 6245-77-001
Proj ID RMC - 624577001
Work Type GENERAL ROUTINE MAINTENANCE OF US 59
 
1.000 2095745.22 0.00 1757226.70 86.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-01-13
Work Began 01-01-13
Work Completed  
Time Computed 01-01-13
Contract Working Days 365
Addl Days Granted 151
Working Days Charged 455
Percent Time Used 88
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10124026
Totals 2095745.22 0.00 1757226.70 86.3

CountyMONTGOMERY
Highway US0059
From VARIOUS HWYS IN MONGTOMERY COUNTY
To VARIOUS HWYS IN MONTGOMERY COUNTY
CSJ 6248-15-001
Proj ID RMC - 624815001
Work Type CONCRETE STRUCTURE REPAIR
 
0.001 435100.00 0.00 41410.92 11.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-15-13
Work Began 06-01-13
Work Completed  
Time Computed 06-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
PHILADELPHIA INDEMNITY INSURANCE COMPANY
BLUEBAY CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6248-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12124006
Totals 435100.00 0.00 41410.92 11.0

CountyMONTGOMERY
Highway US0059
From VARIOUS HWYS IN MONTGOMERY COUNTY
To VARIOUS HWYS IN MONTGOMERY COUNTY
CSJ 6248-16-001
Proj ID RMC - 624816001
Work Type ASPHALT PAVEMENT REPAIR
 
0.001 416487.00 0.00 474335.24 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-15-13
Work Began 06-01-13
Work Completed  
Time Computed 06-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6248-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12124015
Totals 416487.00 0.00 474335.24 99.9

CountyMONTGOMERY
Highway US0059
From VARIOUS HWYS IN MONTGOMERY COUNTY
To VARIOUS HWYS IN MONTGOMERY COUNTY
CSJ 6249-66-001
Proj ID RMC - 624966001
Work Type REFL PAV MRKGS (LONG LINE)
 
0.001 239865.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6249-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09134012
Totals 239865.08 0.00 0.00 0.0

CountyGALVESTON
Highway SH0003
From 0.27 MILES SOUTH OF FM 1764
To .30 MILES NORTH OF FM 1765
CSJ 6250-02-001
Proj ID RMC - 625002001
Work Type ACP OVERLAY
 
0.975 377388.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 6250-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144004
Totals 377388.05 0.00 0.00 0.0