Monthly State Let Construction Report For Laredo District As Of Feb 10, 2017 Page 1 Of 2

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLASALLE
HighwayIH 35
From4.44 MI S OF FM469 AT THE UPRR WYE
To4.160 MI S OF FM469
CSJ0017-08-079
Proj IDBR 1402(071)
Work TypeBRIDGE REHABILITATION
 
0.3573430660.253586871.1899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-14-14
Work Began10-28-15
Work Completed
Time Computed00-00-00
Contract Working Days129
Addl Days Granted60
Working Days Charged274
Percent Time Used144
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-08-079
DUSTROL, INC. (0.16)
S & S BRIDGE PAINTING, INC. (4.57)
HIGHWAY BARRICADES AND SERVICES, LLC (2.54)
RPV CONSTRUCTION (3.57)
Contract #08143227
Totals3430660.250.003586871.1899.9

CountyLASALLE
HighwayIH 35
From@ FM 468
To.
CSJ0017-08-102
Proj IDSTP 2017(581)HES
Work TypeINSTALL TRAFFIC SIGNAL
 
0.800541921.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-08-102
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173021
Totals541921.200.000.000.0

CountyLASALLE
HighwayIH 35
From0.775 MI NORTH OF BI35C (SOUTH INT)
To1.031 MI SOUTH OF BI35C (SOUTH INT)
CSJ0018-01-078
Proj IDNH 1402(072)
Work TypeSMA OVERLAY AND PAVEMENT MRK
 
3.5872087043.783149944.7299.9
Work Order11-03-14
Work Began11-02-15
Work Completed
Time Computed11-19-14
Contract Working Days35
Addl Days Granted0
Working Days Charged35
Percent Time Used100
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-01-078
FLASHER EQUIPMENT COMPANY (2.39)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (6.62)
CHEROKEE SERVICES (2.75)
WEST TEXAS RUMBLE STRIP (0.49)
FOUR J TRAFFIC CONTROLS, INC. (0.00)
Contract #08143038
Totals2087043.785479.503149944.7299.9

CountyLASALLE
HighwayIH 35
FromSH 44 EAST FRONTAGE ROAD
ToCAIMAN CREEK INTERCHANGE
CSJ0018-02-064
Proj IDIM 0351(094)
Work TypeGRADE,BASE,STRUCT,ACP,PAV MKS, SIGN
 
9.3566908417.381744487.1925.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-16
Work Began10-26-16
Work Completed
Time Computed00-00-00
Contract Working Days195
Addl Days Granted0
Working Days Charged56
Percent Time Used28
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0018-02-064
BEAVER CONTRACTORS, LLC (11.14)
D&S TEXAS ICON CONSTRUCTION (1.40)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.32)
MV HENKE COMPANY, LLC (0.50)
FLASHER EQUIPMENT COMPANY (2.24)
Contract #08163056
Totals6908417.380.001744487.1925.2

CountyLASALLE
HighwayIH 35
FromWEBB COUNTY LINE
To2.6 MI S OF FM 133
CSJ0018-02-067
Proj IDNH 2016(648)
Work TypeACP, OVERLAY, PAV MARK
 
23.6585671465.402370922.3741.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-07-16
Work Began10-17-16
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged51
Percent Time Used72
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0018-02-067
WEST TEXAS RUMBLE STRIP (0.25)
FLASHER EQUIPMENT COMPANY (2.41)
Contract #02163222
Totals5671465.400.002370922.3741.8

CountyVAL VERDE
HighwayUS 90
FromAVENUE F
To0.546 MI EAST OF LAUGHLIN AFB
CSJ0023-01-087
Proj IDNH 1602(292)
Work TypeTHIN OVERLAY MIXTURE
 
9.6605319276.012445805.7445.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-16
Work Began10-27-16
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged63
Percent Time Used78
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0023-01-087
CHEROKEE SERVICES (0.97)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.68)
FLASHER EQUIPMENT COMPANY (0.42)
THE LEVY COMPANY, L.P. (0.22)
PAVEMENT MARKINGS INC. (2.27)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.40)
Contract #07163031
Totals5319276.010.002445805.7445.9

CountyDIMMIT
HighwayFM 1917
FromSH 85
To0.243 MI S OF US 83
CSJ0037-15-009
Proj IDSTP 1602(503)HES
Work TypePROVIDE ADDITIONAL PVD SURF WIDTH
 
1.089527358.79183999.5434.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-16
Work Began11-17-16
Work Completed
Time Computed00-00-00
Contract Working Days24
Addl Days Granted0
Working Days Charged8
Percent Time Used33
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0037-15-009
FLASHER EQUIPMENT COMPANY (8.49)
FUQUAY, INC. (0.33)
BEAVER CONTRACTORS, LLC (16.66)
Contract #08163220
Totals527358.790.00183999.5434.8

CountyWEBB
HighwayUS 83
FromESPEJO MOLINA ROAD(NB &SB LANE)
ToZAPATA/WEBB COUNTY LINE
CSJ0038-01-086
Proj IDNH 2017(582)
Work TypeTHIN OVERLAY MIXTURE, PAV MRKS
 
15.5587577537.740.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days161
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0038-01-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173230
Totals7577537.740.000.000.0

CountyWEBB
HighwayUS 83 ETC
FromIH 35
ToKCS RAILROAD CROSSING
CSJ0086-01-084
Proj IDSTP 1602(295)
Work TypeTOM OVERLAY & PAV MRKS
 
7.8164395787.290.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-20-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0086-01-084
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07163212
Totals4395787.290.000.000.0

CountyDUVAL ETC
HighwaySH 359 ETC
From2.260 MI NORTH OF FM 2295
ToFM 1329
CSJ0086-10-049
Proj IDSTP 2016(475)
Work TypeACP, OVERLAY PAV MRK
 
43.11314344014.4512932159.4590.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-16
Work Began07-05-16
Work Completed
Time Computed00-00-00
Contract Working Days263
Addl Days Granted0
Working Days Charged140
Percent Time Used53
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-10-049
CLARK CONSTRUCTION OF TEXAS, INC. (11.01)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (4.00)
D. I. J. CONSTRUCTION, INC. (2.10)
FLASHER EQUIPMENT COMPANY (0.20)
RELMCO, INC. (7.90)
WEST TEXAS RUMBLE STRIP (0.11)
ROVAN TEXAS, LLC (0.21)
Contract #01163004
Totals14344014.450.0012932159.4590.1

CountyWEBB
HighwaySL 20
From0.457 MI S OF SS 400 (KCS RR OVP)
To0.450 MI N OF US 59 (STA. 140+00)
CSJ0086-14-046
Proj IDCBI 2013(281)
Work TypeGRAD, WID STRS, BASE AND PAV
 
1.75133883949.2018651121.7555.0
CountyWEBB
HighwaySL 20
From0.457 MI S OF SS 400 (KCS RR OVP)
To0.450 MI N OF US 59 (STA. 140+00)
CSJ0086-14-056
Proj IDROW 86-14-56
Work TypeACQUISITION & UTILITY ADJUSTMENTS
 
1.7511993938.701532504.2576.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-03-14
Work Began07-27-15
Work Completed
Time Computed00-00-00
Contract Working Days535
Addl Days Granted0
Working Days Charged367
Percent Time Used68
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-046
ANGEL BROTHERS ENTERPRISES, LTD. (19.52)
CABCOS CONTRACTORS LLC (3.32)
HIGHWAY BARRICADES AND SERVICES, LLC (0.80)
LAREDO STRIPING INC. (0.78)
SOIL-TECH, INC. (0.55)
STAR OPERATIONS, INC. (3.77)
VOGES DRILLING CO. (0.61)
WEBBER BARRIER SERVICES, LLC. (0.72)
SAN ANTONIO TELEPHONE COMPANY INC. (0.07)
REIM CONSTRUCTION, INC. (0.78)
AARON CONCRETE CONTRACTORS, L.P. (2.09)
FRANK JR REINFORCEMENT LLC (0.03)
Contract #08143002
Totals35877887.900.0020183626.0056.2

CountyWEBB
HighwaySL 20
FromSH 359
ToSPUR 400
CSJ0086-14-061
Proj IDSTP 1502(617)MM
Work TypeGRADING, BASE, STRUCTURES & SURFACE
 
2.40525541056.408876185.7334.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-04-15
Work Began03-07-16
Work Completed
Time Computed00-00-00
Contract Working Days596
Addl Days Granted0
Working Days Charged209
Percent Time Used35
Contractor(s)
OSCAR RENDA CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-061
ANGEL BROTHERS ENTERPRISES, LTD. (11.40)
HIGHWAY BARRICADES AND SERVICES, LLC (1.53)
LAREDO STRIPING INC. (2.36)
S & S BRIDGE PAINTING, INC. (0.19)
SOIL-TECH, INC. (1.05)
W. W. FOUNDATION DRILLING, LTD. (2.97)
TEXAS STEEL (1.85)
CANTU ELECTRIC CO., INC. (2.46)
RRR SEALCOAT & STRIPING, LLC (0.05)
Contract #08153003
Totals25541056.400.008876185.7334.7

CountyWEBB
HighwaySL 20
From0.45 MI EAST OF INTERNATIONAL BLVD
To0.25 MI WEST OF MCPHERSON ROAD
CSJ0086-14-066
Proj IDNH 2016(400)
Work TypeFLEX BSE, SURF, BRIDGE, PAV MRK ETC
 
1.41721976081.155064349.6423.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-16-16
Work Began05-23-16
Work Completed
Time Computed00-00-00
Contract Working Days387
Addl Days Granted0
Working Days Charged231
Percent Time Used59
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-066
AARON CONCRETE CONTRACTORS, L.P. (0.75)
ALTUS TRAFFIC MANAGEMENT LLC (0.15)
ATS DRILLING, INC. (0.82)
D&S TEXAS ICON CONSTRUCTION (1.25)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.19)
FLASHER EQUIPMENT COMPANY (0.35)
FOREMOST PAVING, INC. (9.45)
FUQUAY, INC. (0.25)
PENHALL COMPANY (0.05)
PRIMATE CONSTRUCTION, INC. (0.06)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.14)
SOUTH TEXAS PAINTING COMPANY (0.12)
THE LEVY COMPANY, L.P. (4.89)
CUATRO T CONSTRUCTION, INC. (3.59)
Contract #12153003
Totals21976081.150.005064349.6423.0

CountyWEBB
HighwaySH 44
FromLOS OLMOS CREEK
ToIN WEBB COUNTY
CSJ0237-03-030
Proj IDBR 1602(506)
Work TypeREPLACEMENT OF AN EXISTING BRIDGE
 
0.3023538171.8641865.911.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days256
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0237-03-030
RIO GRANDE REBAR PLACING, LTD. (2.26)
D&S TEXAS ICON CONSTRUCTION (0.43)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.13)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.36)
FLASHER EQUIPMENT COMPANY (1.22)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25)
MUNOZ FOUNDATION DRILLING, INC. (0.71)
SCOTT DERR PAINTING CO, LLC (0.01)
Contract #08163016
Totals3538171.860.0041865.911.1

CountyWEBB ETC
HighwaySH 44 ETC
From13.947 MILES EAST OF LA SALLE CL
ToDUVAL COUNTY LINE
CSJ0237-03-032
Proj IDSTP 1502(157)
Work TypeACP OVERLAY, MBGF, PAV MRK
 
65.96612273762.9310751138.1188.0
Work Order06-30-15
Work Began10-05-15
Work Completed
Time Computed07-31-15
Contract Working Days228
Addl Days Granted0
Working Days Charged276
Percent Time Used121
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0237-03-032
CLARK CONSTRUCTION OF TEXAS, INC. (15.51)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.24)
FLASHER EQUIPMENT COMPANY (2.63)
PRIMATE CONSTRUCTION, INC. (0.24)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.24)
D&S TEXAS ICON CONSTRUCTION (1.08)
Contract #05153006
Totals12273762.9377468.4410751138.1188.0

CountyDUVAL
HighwaySH 44
FromWEBB/DUVAL COUNTY LINE
ToUS 59
CSJ0237-04-013
Proj IDSTP 2016(855)
Work TypeBASE, GRADE, SURF TRT, PAV MRK
 
9.6324178905.314073406.5297.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-16
Work Began07-05-16
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged122
Percent Time Used67
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0237-04-013
BEAVER CONTRACTORS, LLC (13.63)
FLASHER EQUIPMENT COMPANY (1.77)
FUQUAY, INC. (0.66)
Contract #03163007
Totals4178905.310.004073406.5297.4

CountyDUVAL
HighwaySH 44
From1 MI WEST OF FM 3196
To2.427 MI WEST OF SH 359
CSJ0237-06-043
Proj IDSTP 1602(131)
Work TypePLANNING AND ACP OVERLAY PAV MRKS
 
17.7026984698.926156648.1688.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-02-16
Work Began07-05-16
Work Completed
Time Computed00-00-00
Contract Working Days128
Addl Days Granted0
Working Days Charged117
Percent Time Used91
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0237-06-043
D&S TEXAS ICON CONSTRUCTION (0.29)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.45)
FLASHER EQUIPMENT COMPANY (1.14)
HIGHWAY BARRICADES AND SERVICES, LLC (0.17)
PAVETEX ENGINEERING & TESTING, INC. (0.51)
WEST TEXAS RUMBLE STRIP (0.18)
Contract #04163036
Totals6984698.920.006156648.1688.1

CountyMAVERICK ETC
HighwayUS 57 ETC
From2.887 MI EAST OF FM 481
ToZAVALA COUNTY LINE
CSJ0276-02-028
Proj IDSTP 2017(027)
Work TypeSEAL COAT & PAV MRKS
 
51.9941770045.30237924.6313.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days145
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0276-02-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163004
Totals1770045.300.00237924.6313.4

CountyMAVERICK ETC
HighwayUS 277 ETC
From@ NORTH ST
To.
CSJ0299-04-070
Proj IDSTP 2016(066)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.000315267.2976101.0024.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-15
Work Began04-25-16
Work Completed
Time Computed00-00-00
Contract Working Days112
Addl Days Granted0
Working Days Charged109
Percent Time Used97
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0299-04-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09153021
Totals315267.290.0076101.0024.1

CountyMAVERICK ETC
HighwayUS 277 ETC
FromSL 480
To11.960 MI W OF DIMMIT COUNTY LINE
CSJ0300-01-091
Proj IDSTP 1602(174)HESG
Work TypeTEXTURIZE SHOULDERS CENTERLINE TEXT
 
50.697307234.0455324.9018.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-29-16
Work Began10-31-16
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged7
Percent Time Used13
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0300-01-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06163024
Totals307234.040.0055324.9018.0

page 1 | page 2