Monthly State Let Construction Report For Paris District As Of Feb 11, 2016 Page 1 Of 4

Last Update: Thursday, February 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHUNT
Highway SH 66 ETC
From COLLIN COUNTY LINE
To US 69
CSJ 0009-06-050
Proj ID STP 2015(325)
Work Type SEAL COAT
 
217.821 7694347.58 51120.55 7564844.19 98.5
Work Order 01-27-15
Work Began 07-08-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 64
Addl Days Granted 1
Working Days Charged 82
Percent Time Used 126
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-06-050
STRIPE-A-ZONE, INC.( 14.69%)
BRYDL CONTRACTING, INC.(0.96%)
Contract # 11143004
Totals 7694347.58 51120.55 7564844.19 98.5

CountyHOPKINS
Highway IH 30 ETC
From SH 19
To TEXAS AVE IN SULPHUR SPRINGS
CSJ 0009-09-099
Proj ID STP 2015(079)HESG
Work Type HAZARD ELIMINATION & SAFETY
 
130.476 1210344.26 3500.00 1193669.04 99.9
Work Order 02-18-15
Work Began 03-29-15
Work Completed  
Time Computed 03-06-15
Contract Working Days 80
Addl Days Granted 5
Working Days Charged 152
Percent Time Used 178
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0009-09-099
STRIPING SYSTEMS, INC. (0.00%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.68%)
BRYDL CONTRACTING, INC.(2.54%)
COWBELL TRAFFIC SERVICES, INC. ( 24.22%)
NE-TEX CONSTRUCTION, LTD.(7.35%)
TEXOMA CONCRETE CUTTING, LLC (2.94%)
J & L PAVING (1.22%)
DIAMOND SURFACE, INC.(5.78%)
Contract # 09143029
Totals 1210344.26 3500.00 1193669.04 99.9

CountyHUNT
Highway IH 30
From VARIOUS BRIDGE LOCATIONS IN HUNT CO
To .
CSJ 0009-13-161
Proj ID BR 1502(260)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
0.304 370171.75 43357.14 493526.55 99.9
Work Order 07-15-15
Work Began 09-21-15
Work Completed  
Time Computed 09-14-15
Contract Working Days 32
Addl Days Granted 30
Working Days Charged 42
Percent Time Used 67
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0009-13-161
FLEX SUPPLY, LLC (2.21%)
LONE STAR BARRIER SERVICES, LLC( 12.64%)
Contract # 06153020
Totals 370171.75 43357.14 493526.55 99.9

CountyFRANKLIN
Highway US 67
From 0.41 MI E OF SPUR 423
To TITUS C/L
CSJ 0010-05-022
Proj ID STP 2014(552)HRR
Work Type HAZARD ELIMINATION & SAFETY
 
5.284 2849816.37 0.00 2992781.89 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-25-14
Work Began 05-11-14
Work Completed 11-30-15
Time Computed 05-11-14
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 169
Percent Time Used 133
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-05-022
PANOLA SIGN & BARRICADE, INC.(0.50%)
MOORE CONSTRUCTION, INC. (1.19%)
CATOCON, INC.(2.93%)
J & M CONTRACTING, COMPANY ( 17.36%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.90%)
DUSTIN ALLEN, INC. (2.27%)
STRIPING TECHNOLOGY, L.P.(1.17%)
TEX OP CONSTRUCTION, LP(0.56%)
Contract # 03143212
Totals 2849816.37 0.00 2992781.89 100.0

CountyLAMAR
Highway US 82
From FANNIN COUNTY LINE
To FM 38 EAST
CSJ 0045-08-036
Proj ID NH 2014(736)
Work Type WIDEN NON - FREEWAY
 
15.205 8860584.85 2604.00 9043476.63 99.9
Work Order 07-22-14
Work Began 08-08-14
Work Completed  
Time Computed 08-07-14
Contract Working Days 225
Addl Days Granted 0
Working Days Charged 224
Percent Time Used 99
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-08-036
MOORE CONSTRUCTION, INC. (1.84%)
SAMMY G. SMALLWOOD (1.03%)
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
HIGHWAY 19 CONSTRUCTION, LLC (0.71%)
BAHENA CONSTRUCTION CO.,INC. (5.99%)
DUSTROL, INC.(0.97%)
RK HALL, LLC ( 68.34%)
STRIPING TECHNOLOGY, L.P.(2.05%)
CATACON, INC.(2.39%)
RED SIXTEEN CONSTRUCTION, INC(0.30%)
Contract # 06143204
Totals 8860584.85 2604.00 9043476.63 99.9

CountyGRAYSON
Highway US 82
From 2180' W OF FM 1417 W (FRTG ONLY)
To FM 1417 W (FRONTAGE ONLY)
CSJ 0045-18-033
Proj ID NH 1402(083)
Work Type OVERLAY
 
3.428 1889024.62 5136.92 1890272.47 100.0
Work Order 10-02-14
Work Began 10-23-14
Work Completed 01-11-16
Time Computed 10-18-14
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 114
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0045-18-033
ALTUS TRAFFIC MANAGEMENT LLC (0.72%)
DUSTROL, INC.(3.22%)
DUSTIN ALLEN, INC. (6.77%)
STRIPING TECHNOLOGY, L.P.(2.93%)
O. TREVINO CONSTRUCTION, LLC (5.70%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.06%)
SOUTHEAST GRINDING & GROOVING, LLC (0.23%)
Contract # 08143215
Totals 1889024.62 5136.92 1890272.47 100.0

CountyGRAYSON
Highway US 82
From FM 1897
To FANNIN COUNTY LINE
CSJ 0045-19-047
Proj ID C 45-19-47
Work Type WIDEN NON - FREEWAY
 
12.152 26059261.46 9328.91 27609068.58 99.9
Work Order 10-12-12
Work Began 11-15-12
Work Completed  
Time Computed 04-10-13
Contract Working Days 473
Addl Days Granted 55
Working Days Charged 498
Percent Time Used 94
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0045-19-047
BAHENA CONSTRUCTION CO.,INC. (3.42%)
FORTSON CONTRACTING, INC.(0.06%)
L & N BRIDGE, LLC(2.48%)
GARY A. CRAIN, INC.(0.01%)
LYON BARRICADE AND CONSTRUCTION CO.(0.18%)
MOORE CONSTRUCTION, INC. (0.65%)
MURRAY CONSTRUCTION(0.63%)
RK HALL, LLC ( 42.19%)
STRIPING TECHNOLOGY, L.P.(0.72%)
WEST TEXAS RUMBLE STRIP(0.06%)
WYLIE DRILLING & DRAINAGE, INC.(0.38%)
TEX OP CONSTRUCTION, LP(0.69%)
SOUTHEAST GRINDING & GROOVING, LLC (0.01%)
TEXAS SHAFTS, INC. (0.20%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.25%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.01%)
Contract # 08123201
Totals 26059261.46 9328.91 27609068.58 99.9

CountyGRAYSON
Highway US 82
From FRISCO ROAD (SHERMAN)
To FM 1417 EAST
CSJ 0045-19-050
Proj ID C 45-19-50
Work Type WIDEN NON - FREEWAY
 
1.617 12500127.04 992822.83 992822.83 7.9
Work Order 11-10-15
Work Began 01-20-16
Work Completed  
Time Computed 01-11-16
Contract Working Days 350
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 3
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-19-050
ALTUS TRAFFIC MANAGEMENT LLC (0.25%)
LONE STAR BARRIER SERVICES, LLC(0.77%)
WOLFE CONSTRUCTION GROUP, INC. (0.79%)
DIAMOND SURFACE, INC.(0.08%)
OVERLAND CORPORATION ( 23.31%)
EROSION CONTROL MANAGEMENT SERVICES(0.26%)
RPM XCONSTRUCTION, LLC ( 29.70%)
FARR FOUNDATION, INC.(0.22%)
STRIPING TECHNOLOGY, L.P.(0.52%)
VENUS CONSTRUCTION (5.39%)
KMB TRUCKING LLC (0.00%)
Contract # 07153207
Totals 12500127.04 992822.83 992822.83 7.9

CountyRED RIVER
Highway US 82
From @ KICKAPOO CREEK
To .
CSJ 0046-01-061
Proj ID BR 1502(210)
Work Type BRIDGE REPLACEMENT
 
0.515 2651371.11 1350.00 409536.75 15.4
Work Order 07-31-15
Work Began 10-02-15
Work Completed  
Time Computed 08-30-15
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 18
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0046-01-061
TOTAL HIGHWAY MAINTENANCE, LLC (0.34%)
RK HALL, LLC (8.77%)
DUSTIN ALLEN, INC. (1.93%)
MOORE CONSTRUCTION, INC. (2.23%)
TEX OP CONSTRUCTION, LP(0.66%)
PENHALL COMPANY(0.24%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.03%)
WITHERS CONSTRUCTION, LLC(0.16%)
STRIPING TECHNOLOGY, L.P.(0.36%)
WEST TEXAS RUMBLE STRIP(0.22%)
MCL CONTRACTING, LLC (0.17%)
Contract # 06153246
Totals 2651371.11 1350.00 409536.75 15.4

CountyRED RIVER
Highway US 82
From 0.285 MI WEST OF FM 114
To 0.185 MI EAST OF FM 412
CSJ 0046-01-062
Proj ID STP 1502(550)HES
Work Type HAZARD ELIMINATION & SAFETY
 
1.251 795946.99 80306.41 121662.98 15.2
Work Order 10-30-15
Work Began 12-08-15
Work Completed  
Time Computed 12-29-15
Contract Working Days 66
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 36
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0046-01-062
BAHENA CONSTRUCTION CO.,INC. ( 10.99%)
MOORE CONSTRUCTION, INC. (2.40%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.36%)
SAMMY SMALLWOOD COMPANY(3.28%)
STRIPING TECHNOLOGY, L.P.(2.69%)
Contract # 08153240
Totals 795946.99 80306.41 121662.98 15.2

CountyGRAYSON
Highway SH 5
From COLLIN COUNTY LINE
To US 75
CSJ 0047-03-075
Proj ID STP 1402(084)
Work Type MISCELLANEOUS CONSTRUCTION
 
9.575 3711917.79 138796.00 2317556.07 64.2
Work Order 11-12-14
Work Began 12-02-14
Work Completed  
Time Computed 02-10-15
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 175
Percent Time Used 163
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-075
ALTUS TRAFFIC MANAGEMENT LLC (0.69%)
MOORE CONSTRUCTION, INC. (0.26%)
WITHERS CONSTRUCTION, LLC(2.37%)
BAHENA CONSTRUCTION CO.,INC. (9.12%)
LONE STAR BARRIER SERVICES, LLC(0.77%)
TEXANA LAND & ASPHALT, INC.( 10.26%)
TEXAS ALTERNATIVE GRASSER, INC.(0.61%)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.(0.33%)
STRIPING TECHNOLOGY, L.P.(1.88%)
Contract # 09143041
Totals 3711917.79 138796.00 2317556.07 64.2

CountyGRAYSON
Highway US 75
From FM 902
To SHEPHERD DRIVE
CSJ 0047-03-076
Proj ID C 47-3-76
Work Type REHABILITATION OF EXISTING ROADWAY
 
1.495 8342650.77 237.25 8902509.05 99.9
Work Order 11-04-13
Work Began 01-27-14
Work Completed  
Time Computed 01-03-14
Contract Working Days 142
Addl Days Granted 47
Working Days Charged 255
Percent Time Used 134
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-076
BROCK ENVIRONMENTAL, LLC (0.10%)
DUSTROL, INC.(0.10%)
FORTSON CONTRACTING, INC.(0.14%)
ALTUS TRAFFIC MANAGEMENT LLC (0.38%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.24%)
SAMMY G. SMALLWOOD (0.42%)
W.O.E. CONSTRUCTION(0.44%)
STRIPING TECHNOLOGY, L.P.(1.27%)
ANTIGO CONSTRUCTION, INC.(0.38%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(1.29%)
VENUS CONSTRUCTION (4.15%)
MCL CONTRACTING, LLC (1.18%)
MABAK DIRECTIONAL DRILLING (0.08%)
ASPLUNDH TREE EXPERT CO(0.39%)
Contract # 08133224
Totals 8342650.77 237.25 8902509.05 99.9

CountyGRAYSON
Highway US 75
From 1.65 MILES NORTH OF FM 1417
To FM 1417
CSJ 0047-03-077
Proj ID NH 2013(907)
Work Type MISCELLANEOUS CONSTRUCTION
 
1.650 739670.03 0.00 766794.03 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-13
Work Began 01-03-14
Work Completed 09-02-14
Time Computed 12-30-13
Contract Working Days 43
Addl Days Granted 5
Working Days Charged 48
Percent Time Used 100
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0047-03-077
CROSSROADS, L.P. (1.07%)
BRENDA PRICE TRUCKING(0.71%)
BROCK ENVIRONMENTAL, LLC (0.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.80%)
RK HALL, LLC ( 26.50%)
CHRISTINE"S CONCERTE SAWING & SEALING LLC(0.27%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (7.65%)
DUSTROL, INC.(3.21%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.23%)
GJ SEEDING, LLC(0.63%)
Contract # 08133028
Totals 739670.03 0.00 766794.03 100.0

CountyGRAYSON
Highway US 75
From @ LOY LAKE ROAD (SHERMAN)
To .
CSJ 0047-18-068
Proj ID NH 2013(908)
Work Type WIDEN NON - FREEWAY
 
0.434 5248890.96 93101.88 5275404.99 99.9
Work Order 01-06-14
Work Began 01-27-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 268
Addl Days Granted 56
Working Days Charged 339
Percent Time Used 104
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0047-18-068
TOTAL HIGHWAY MAINTENANCE, LLC (1.24%)
EROSION CONTROL MANAGEMENT SERVICES(0.09%)
S & S BRIDGE PAINTING, INC.(0.67%)
WYLIE DRILLING & DRAINAGE, INC.(1.37%)
CROSSROADS, L.P. (0.48%)
A BROTHERS MILLING, LLC(0.48%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (5.62%)
MCL CONTRACTING, LLC (0.55%)
W.O.E. CONSTRUCTION(0.54%)
LONE STAR BARRIER SERVICES, LLC(0.40%)
ALVARENGA UNDERGROUND CONSTRUCTION, L.L.C. (0.22%)
PEACHTREE CONSTRUCTION, LTD. (2.49%)
PLACIDO CONSTRUCTION COMPANY (0.57%)
T & R EXCAVATION, INC. (0.96%)
BRADCO, LLC(1.96%)
NORTH TEXAS DRILLING (0.01%)
S & S BORING (0.14%)
BATTEN DRILLING, INC.(0.06%)
Contract # 09133221
Totals 5248890.96 93101.88 5275404.99 99.9

CountyGRAYSON
Highway US 75
From @ FM 84
To .
CSJ 0047-18-070
Proj ID STP 1502(552)HES
Work Type HAZARD ELIMINATION & SAFETY
 
0.100 142990.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-22-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0047-18-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153025
Totals 142990.00 0.00 0.00 0.0

CountyGRAYSON
Highway US 75
From LOY LAKE ROAD
To US 82
CSJ 0047-18-071
Proj ID NH 1502(553)
Work Type MISCELLANEOUS CONSTRUCTION
 
0.266 579502.00 153025.00 280025.00 48.3
Work Order 09-22-15
Work Began 12-10-15
Work Completed  
Time Computed 10-22-15
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 35
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0047-18-071
STRIPING TECHNOLOGY, L.P.(3.61%)
PEACHTREE CONSTRUCTION, LTD. (8.24%)
RMI WORLDWIDE, LLC (0.77%)
Contract # 08153223
Totals 579502.00 153025.00 280025.00 48.3

CountyGRAYSON
Highway US 377 ETC
From US 82
To FM 901
CSJ 0081-10-042
Proj ID STP 2016(186)
Work Type SEAL COAT
 
242.218 8437785.28 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-26-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0081-10-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153216
Totals 8437785.28 0.00 0.00 0.0

CountyGRAYSON
Highway BU 377C
From HUGHES STREET
To FM 902
CSJ 0081-16-003
Proj ID STP 2016(595)
Work Type LANDSCAPE DEVELOPMENT
 
0.001 178510.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0081-16-003
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163222
Totals 178510.00 0.00 0.00 0.0

CountyHOPKINS
Highway SH 11
From 0.08 MI SE OF COUNTY LINE
To 3.03 MI W OF FM 2653 S
CSJ 0083-02-048
Proj ID STP 1502(554)HES
Work Type HAZARD ELIMINATION & SAFETY
 
3.157 5504239.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 231
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0083-02-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163041
Totals 5504239.11 0.00 0.00 0.0

CountyHOPKINS
Highway SH 19
From SH 11
To RAINS COUNTY LINE
CSJ 0108-09-043
Proj ID STP 2013(906)
Work Type SEAL COAT
 
16.672 1364788.07 0.00 1364113.36 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-13
Work Began 11-01-13
Work Completed 06-26-15
Time Computed 11-04-13
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 98
Contractor(s)
A. K. GILLIS & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0108-09-043
PANOLA SIGN & BARRICADE, INC.(1.09%)
STRIPING TECHNOLOGY, L.P.(3.16%)
BAHENA CONSTRUCTION CO.,INC. (9.34%)
SAMMY G. SMALLWOOD (1.78%)
MOORE CONSTRUCTION, INC. (1.43%)
CATACON, INC.(1.88%)
Contract # 08133044
Totals 1364788.07 0.00 1364113.36 100.0