Monthly State Let Construction Report For Tyler District As Of Jun 10, 2015 Page 1 Of 3

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWOOD
Highway SH 11 ETC
From .2 MI N OF FM 852 IN WINNSBORO, E
To 0.6 MI E OF FM 1647 (CAMP C/L)
CSJ 0083-06-038
Proj ID STP 2015(312)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
268.064 8548703.60 0.00 2062922.93 24.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-16-15
Work Began 05-20-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 8
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0083-06-038
COWBELL TRAFFIC SERVICES, INC. (0.27%)
STRIPING TECHNOLOGY, L.P.( 15.16%)
BRYDL CONTRACTING, INC.(1.10%)
Contract # 11143203
Totals 8548703.60 0.00 2062922.93 24.1

CountyANDERSON
Highway SH 19
From 3.6 MI N OF FM 837(HENDERSON C/L),S
To 0.4 MI N OF FM 321 AT MONTALBA
CSJ 0108-06-051
Proj ID STP 2013(637)
Work Type GR, STRS, HMA BS & SURF, OCST, LVL - UP
 
11.813 12487715.87 29915.00 1873331.38 15.0
Work Order 07-10-14
Work Began 09-02-14
Work Completed  
Time Computed 07-26-14
Contract Working Days 453
Addl Days Granted 0
Working Days Charged 127
Percent Time Used 28
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0108-06-051
COLD CREEK CONSTRUCTION, LTD (0.82%)
FORTSON CONTRACTING, INC.(0.45%)
HIGHWAY 19 CONSTRUCTION, LLC ( 10.97%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35%)
SAMMY G. SMALLWOOD (0.46%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.15%)
STRIPING TECHNOLOGY, L.P.(1.23%)
FARR FOUNDATION, INC.(0.64%)
Contract # 05143205
Totals 12487715.87 29915.00 1873331.38 15.0

CountyRUSK
Highway US 84
From 1.1 MI W OF FM 3055, E
To 0.2 MI W OF US 259 IN MT ENTERPRISE
CSJ 0123-05-014
Proj ID STP 2015(531)
Work Type ACP BS & SURF, PVT MRKG
 
1.800 1077700.00 347668.01 520975.33 48.3
Work Order 02-24-15
Work Began 04-28-15
Work Completed  
Time Computed 03-12-15
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 30
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0123-05-014
PANOLA SIGN & BARRICADE, INC.(0.55%)
DUSTROL, INC.(1.47%)
ODUM SERVICES, L.P.(2.29%)
STRIPING TECHNOLOGY, L.P.(2.09%)
Contract # 01153021
Totals 1077700.00 347668.01 520975.33 48.3

CountyRUSK
Highway US 259
From 0.4 MI S OF US 79 IN HENDERSON, S
To JARRELL CREEK (END C-S)
CSJ 0138-04-045
Proj ID NH 1502(121)
Work Type BS RPR, PLNG, HMAC BS, OCST, PFC OV
 
10.136 5667818.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0138-04-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153046
Totals 5667818.78 0.00 0.00 0.0

CountyGREGG
Highway SH 31
From 0.3 MI N OF FM 2205 (GRACE CRK), N
To 0.2 MI S OF US 80(COTTON) IN LONGVW
CSJ 0138-08-026
Proj ID STP 1402(088)
Work Type FENCE, WELCOME SIGN, PLANTINGS
 
0.278 281249.70 59598.60 182731.00 64.9
Work Order 01-23-15
Work Began 03-11-15
Work Completed  
Time Computed 02-08-15
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 34
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0138-08-026
FLEX SUPPLY, LLC (1.60%)
YORKS MASONRY & STONE WORKS(8.97%)
Contract # 12143232
Totals 281249.70 59598.60 182731.00 64.9

CountyGREGG
Highway FM 2208
From AT SMELLEY/HOLLYBROOK INTERSECTION
To 0.14 MI N OF SL 281 N RAMP
CSJ 0138-15-010
Proj ID STP 2014(917)
Work Type SIGNAL
 
0.100 144010.50 0.00 143303.65 99.5
CountyGREGG
Highway FM 2208
From 0.4 MI N OF SL 281 (HARRISON C/L),S
To SL 281 N RAMP IN LONGVIEW
CSJ 0138-15-011
Proj ID CC 138-15-11
Work Type GR, ACP, OCST, C & G
 
0.371 397810.77 0.00 371545.28 93.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-14
Work Began 09-15-14
Work Completed  
Time Computed 08-29-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 98
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0138-15-010
SOUTHWEST ENVIRONMENT SERVICES LLC (0.98%)
PANOLA SIGN & BARRICADE, INC.(0.74%)
MAC TRANSPORTATION, LTD, L.L.P.(3.85%)
STRIPING TECHNOLOGY, L.P.( 25.16%)
TEX OP CONSTRUCTION, LP(0.97%)
Contract # 07143022
Totals 541821.27 0.00 514848.93 95.0

CountyHENDERSON
Highway SH 31
From 0.34 MI W OF FM 773 (BEG C&G), E
To 1.1 MI W OF FM 1803(W) IN MURCHISON
CSJ 0164-01-068
Proj ID STP 2013(549)
Work Type PVMT RPR, PLNG, CAM, OCST, HARST, HMAC
 
7.862 4945961.90 0.00 4693895.13 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-26-13
Work Began 08-12-13
Work Completed 01-15-15
Time Computed 07-12-13
Contract Working Days 52
Addl Days Granted 11
Working Days Charged 92
Percent Time Used 146
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0164-01-068
DUSTROL, INC.(4.44%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.13%)
PENHALL COMPANY(0.14%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.21%)
STRIPING TECHNOLOGY, L.P.(2.94%)
VIKING CONSTRUCTION, INC.( 12.69%)
COX PAVING COMPANY, L.P. (4.71%)
Contract # 04133218
Totals 4945961.90 0.00 4693895.13 100.0

CountyHENDERSON
Highway SH 31
From .09 MI W OF FM 317(BGN DPRS MDN), E
To .3 MI W OF FM 773 (BGN C&G) MRCHSN
CSJ 0164-01-069
Proj ID STP 2015(621)
Work Type PFC, MBGF, CAM, OCST, BKFL, HMAC, PLNG
 
4.656 3640350.87 0.00 0.00 0.0
Work Order 03-13-15
Work Began 00-00-00
Work Completed  
Time Computed 03-29-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0164-01-069
ALTUS TRAFFIC MANAGEMENT LLC (0.18%)
FORTSON CONTRACTING, INC.(0.83%)
MURRAY CONSTRUCTION(0.58%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.52%)
STRIPING TECHNOLOGY, L.P.(2.12%)
COWBELL TRAFFIC SERVICE, INC.(0.47%)
Contract # 02153210
Totals 3640350.87 0.00 0.00 0.0

CountyWOOD
Highway SH 37
From 0.4 MI S OF FM 515 IN WINNSBORO, S
To FM 2088 IN QUITMAN
CSJ 0190-02-038
Proj ID STP 2015(534)
Work Type PVT RPR, PLNG, OCST, HMAC SURF, PVT MRK
 
13.893 7688421.61 663364.87 2871633.37 37.3
Work Order 02-10-15
Work Began 04-08-15
Work Completed  
Time Computed 02-26-15
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 15
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0190-02-038
PANOLA SIGN & BARRICADE, INC.(0.21%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.27%)
MAC TRANSPORTATION, LTD, L.L.P.(1.73%)
STRIPING TECHNOLOGY, L.P.(1.00%)
TEX OP CONSTRUCTION, LP(0.65%)
Contract # 01153202
Totals 7688421.61 663364.87 2871633.37 37.3

CountySMITH
Highway US 69
From 0.2 MI S OF CUMBERLAND RD,S 0.57 MI
To 0.66 MI N OF TOLL 49
CSJ 0191-01-082
Proj ID CC 191-1-82
Work Type GR, STR, FLX BS, PVMT, SIGNS, SIGS, STRPG
 
0.567 2021972.96 63900.85 2037269.80 100.0
Work Order 03-13-14
Work Began 05-05-14
Work Completed 02-06-15
Time Computed 03-29-14
Contract Working Days 107
Addl Days Granted 3
Working Days Charged 112
Percent Time Used 101
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0191-01-082
TOTAL HIGHWAY MAINTENANCE, LLC (0.22%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.04%)
STRIPING TECHNOLOGY, L.P.(1.30%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.( 17.94%)
J & M CONTRACTING, COMPANY (2.02%)
TEX OP CONSTRUCTION, LP(4.56%)
Contract # 01143020
Totals 2021972.96 63900.85 2037269.80 100.0

CountyHENDERSON
Highway US 175
From 0.1 MI SE OF FM 804, SE
To CR 4712 (END OF C-S)
CSJ 0198-01-023
Proj ID NH 1402(195)
Work Type RECONSTR GR, STRS, BS, SURF & PAV M
 
6.695 39261003.89 0.00 3467969.09 8.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-21-14
Work Began 04-06-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 605
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 3
Contractor(s)
A. L. HELMCAMP, INC.
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0198-01-023
DUSTIN ALLEN, INC. (0.36%)
MURRAY CONSTRUCTION(0.22%)
STRIPING TECHNOLOGY, L.P.(0.31%)
SAN-ANN-CO., INC.(0.21%)
KLP COMMERCIAL, LLC(4.91%)
KENSAR LLC DBA S & S TRUCKING(1.88%)
Contract # 08143055
Totals 39261003.89 0.00 3467969.09 8.8

CountyHENDERSON
Highway US 175
From 1.1 MI E OF LP 60E @ LARUE, SE
To 0.85 MI E OF FM 315, IN POYNOR
CSJ 0198-02-027
Proj ID NH 2015(423)
Work Type RECONSTR GR, STRS, BS, SURF & PAV M
 
4.731 37849155.31 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 654
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-02-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153201
Totals 37849155.31 0.00 0.00 0.0

CountyCHEROKEE
Highway US 69
From SL 456 IN JACKSONVILLE, S
To 0.058 MI N OF SL 62 IN RUSK
CSJ 0199-01-081
Proj ID NH 1502(130)
Work Type STRS, PLNG, HMAC, OCST, PFC, MBGF, BS RPR
 
10.722 11063277.59 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0199-01-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153013
Totals 11063277.59 0.00 0.00 0.0

CountyCHEROKEE
Highway US 69
From 0.028 MI S OF FM 343 IN RUSK, S
To 0.08 MI N OF SH 21 IN ALTO
CSJ 0199-02-057
Proj ID NH 1502(277)
Work Type STRS, PLNG, HMAC, OCST, PFC, MBGF, BS RPR
 
10.027 9380454.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0199-02-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153014
Totals 9380454.05 0.00 0.00 0.0

CountyWOOD
Highway US 69
From 0.6 MI NW OF FM 779 IN GOLDEN, SE
To SL 564 IN MINEOLA
CSJ 0203-05-037
Proj ID C 203-5-37
Work Type GR, STRS, ACP BS & SURF, PVT MRK
 
4.207 2817127.02 14599.55 2733883.13 100.0
Work Order 08-09-13
Work Began 09-10-13
Work Completed 05-19-15
Time Computed 08-25-13
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 120
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0203-05-037
BUYERS BARRICADES, INC.(0.66%)
AMERICAN REMEDIATION OPTIONS, INC. (2.07%)
WEST TEXAS RUMBLE STRIP(0.13%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.46%)
STRIPING TECHNOLOGY, L.P.(1.80%)
MAC TRANSPORTATION, LTD, L.L.P.(7.48%)
P.R. PARKER COMPANY, INC.(0.42%)
TEX OP CONSTRUCTION, LP(0.38%)
Contract # 06133223
Totals 2817127.02 14599.55 2733883.13 100.0

CountySMITH
Highway FM 1253
From CR 462(S), 1.3 MI N OF FM 857, S
To FM 1805
CSJ 0203-08-015
Proj ID STP 1502(278)HES
Work Type SUBGRADE WIDEN, LEVEL - UP, OCST
 
12.009 7499499.38 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 311
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0203-08-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153028
Totals 7499499.38 0.00 0.00 0.0

CountyANDERSON
Highway US 79
From 1.6 MI SW OF LP 256 IN PALESTINE, S
To 0.4 MI SW OF FM 645
CSJ 0205-07-043
Proj ID NH 2008(510)
Work Type GR, BS, ASPH PVT, SIGS, ILLUM, SIGNS
 
8.601 41986850.19 1385228.46 24142470.46 57.5
Work Order 10-24-12
Work Began 11-12-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 880
Addl Days Granted 0
Working Days Charged 631
Percent Time Used 71
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-07-043
HIGHWAY TECHNOLOGIES, INC. (0.10%)
STRIPING TECHNOLOGY, L.P.(1.65%)
MAC TRANSPORTATION, LTD, L.L.P.(3.12%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.39%)
AMERICAN REMEDIATION OPTIONS, INC. (0.53%)
DANRIDGE CONSTRUCTION, LLC.(0.30%)
DUSTROL, INC.(0.20%)
WEST TEXAS RUMBLE STRIP(0.05%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.30%)
NORTH TEXAS REBAR, LLC (0.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.23%)
P.R. PARKER COMPANY, INC.(0.02%)
TEX OP CONSTRUCTION, LP(0.01%)
Contract # 09123003
Totals 41986850.19 1385228.46 24142470.46 57.5

CountyANDERSON
Highway US 79
From SL 256 IN PALESTINE, SW
To 1.4 MI SW OF FM 1990(TILE FCTRY RD)
CSJ 0205-07-075
Proj ID NH 1502(049)
Work Type PLNG, SUPERAVE, OCST, PFC, PVT MRKG
 
1.663 2318824.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-19-15
Work Began 00-00-00
Work Completed  
Time Computed 06-19-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-07-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153251
Totals 2318824.87 0.00 0.00 0.0

CountyRUSK
Highway US 79
From SL 571, NE & N
To SH 64 AT TRAFFIC STAR IN HENDERSON
CSJ 0206-07-057
Proj ID NH 1502(132)
Work Type BS RPR, PLNG, SUPRPV, HMAC, OCST, PFC OV
 
4.440 5221369.21 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0206-07-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153043
Totals 5221369.21 0.00 0.00 0.0

CountyRUSK
Highway US 79
From SL 571 IN HENDERSON, SW
To FM 839
CSJ 0206-07-058
Proj ID STP 1502(281)HES
Work Type STRS, WDNG, OCST, ACP, PVT MRKGS
 
3.050 6661253.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0206-07-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153251
Totals 6661253.88 0.00 0.00 0.0

page 1 | page 2 | page 3