Monthly State Let Construction Report For Tyler District As Of Sep 15, 2014 Page 1 Of 3

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyVAN ZANDT
Highway US 80 ETC
From 3.2 MI W OF FM 2965 (KAUFMAN C/L),E
To 0.7 MI E OF SH 64 IN WILLS POINT
CSJ 0095-06-064
Proj ID STP 2014(205)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
155.152 7401723.84 15163.29 7180177.31 97.0
Work Order 12-05-13
Work Began 06-02-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 75
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0095-06-064
FLAT LINE, INC.( 11.94%)
RED SIXTEEN CONSTRUCTION, INC. (0.96%)
Contract # 11133022
Totals 7401723.84 15163.29 7180177.31 97.0

CountyGREGG
Highway US 80
From 0.35 MI E OF SH 42 IN WHITE OAK, E
To 1.4 MI W OF SL 281(FISHER RD)IN LVW
CSJ 0096-04-065
Proj ID STP 2013(206)
Work Type GR, BS, HMAC SURF, STRM SWR, C & G, SIGNS
 
1.558 3482669.95 39009.97 3309291.14 95.0
Work Order 01-31-13
Work Began 02-18-13
Work Completed  
Time Computed 02-16-13
Contract Working Days 221
Addl Days Granted 13
Working Days Charged 222
Percent Time Used 94
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0096-04-065
RICE ENVIRONMENTAL SERVICES(0.75%)
COWBELL TRAFFIC SERVICES, INC. (0.38%)
DUSTROL, INC.(1.15%)
G & L FLOWERS TRUCKING (2.00%)
STRIPING TECHNOLOGY, L.P.(1.14%)
ROBINSON CONSTRUCTION(3.63%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.13%)
Contract # 12123218
Totals 3482669.95 39009.97 3309291.14 95.0

CountyHENDERSON
Highway SH 19
From 4.1 MI N OF FM 837 (CR 468N), N
To 3.5 MI S OF FM 1615 (COON CRK BRG)
CSJ 0108-05-014
Proj ID C 108-5-14
Work Type GR, STRS, HMA BS & SURF, OCST, LVL - UP
 
4.636 6385017.81 4729.91 6093248.97 95.8
Work Order 10-18-12
Work Began 11-19-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 265
Addl Days Granted 0
Working Days Charged 287
Percent Time Used 108
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0108-05-014
HIGHWAY TECHNOLOGIES, INC. (0.29%)
COX PAVING COMPANY, L.P. (4.37%)
D. I. J. CONSTRUCTION, INC.(1.01%)
FORTSON CONTRACTING, INC.(1.50%)
3LW MANAGEMENT, LLC(9.06%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.51%)
Contract # 08123224
Totals 6385017.81 4729.91 6093248.97 95.8

CountyANDERSON
Highway SH 19
From 3.6 MI N OF FM 837(HENDERSON C/L),S
To 0.4 MI N OF FM 321 AT MONTALBA
CSJ 0108-06-051
Proj ID STP 2013(637)
Work Type GR, STRS, HMA BS & SURF, OCST, LVL - UP
 
11.813 12487715.87 0.00 0.00 0.0
Work Order 07-10-14
Work Began 09-02-14
Work Completed  
Time Computed 07-26-14
Contract Working Days 453
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0108-06-051
COLD CREEK CONSTRUCTION, LTD (0.82%)
FORTSON CONTRACTING, INC.(0.45%)
HIGHWAY 19 CONSTRUCTION, LLC ( 10.97%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35%)
SAMMY G. SMALLWOOD (0.46%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.15%)
STRIPING TECHNOLOGY, L.P.(1.23%)
Contract # 05143205
Totals 12487715.87 0.00 0.00 0.0

CountyGREGG
Highway SH 31
From 0.5 MI S OF FM 2205 IN LONGVIEW, N
To 0.45 MI S OF US 80 (SOUTH ST)
CSJ 0138-01-095
Proj ID NH 2013(911)
Work Type IRRIGATION, PLANTING BED PREP, PLANTS
 
2.025 189035.00 2000.00 194498.50 99.9
Work Order 09-16-13
Work Began 10-21-13
Work Completed  
Time Computed 10-02-13
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 78
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0138-01-095
ALTUS TRAFFIC MANAGEMENT LLC (1.56%)
TX DOWN UNDER CONSTRUCTION LLC (6.10%)
Contract # 08133225
Totals 189035.00 2000.00 194498.50 99.9

CountyRUSK
Highway US 259
From AT FM 1798, NEAR MINDEN
To .
CSJ 0138-05-052
Proj ID STP 1102(218)SB
Work Type GR, STRS, FLX & ACP BS, SURF, SIGN, ILUMTN
 
0.766 5497236.41 0.00 5581096.03 99.9
Work Order 08-11-11
Work Began 06-04-12
Work Completed  
Time Computed 01-02-12
Contract Working Days 263
Addl Days Granted 60
Working Days Charged 291
Percent Time Used 90
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0138-05-052
AMERICAN REMEDIATION OPTIONS, INC. (2.09%)
STRIPING TECHNOLOGY, L.P.(2.83%)
COWBELL TRAFFIC SERVICES, INC. (0.09%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.05%)
SCOTT DERR PAINTING CO, LLC(0.10%)
PANOLA SIGN & BARRICADE, INC.(0.23%)
MAC TRANSPORTATION, LTD, L.L.P.(3.32%)
MESA ROD BUSTERS, INC. (0.07%)
R & R TELCO ENTERPRISES, INC.(0.12%)
DUSTROL, INC.(0.00%)
Contract # 06113241
Totals 5497236.41 0.00 5581096.03 99.9

CountyGREGG
Highway FM 2208
From AT SMELLEY/HOLLYBROOK INTERSECTION
To 0.14 MI N OF SL 281 N RAMP
CSJ 0138-15-010
Proj ID STP 2014(917)
Work Type SIGNAL
 
0.100 144010.50 0.00 0.00 0.0
CountyGREGG
Highway FM 2208
From 0.4 MI N OF SL 281 (HARRISON C/L),S
To SL 281 N RAMP IN LONGVIEW
CSJ 0138-15-011
Proj ID CC 138-15-11
Work Type GR, ACP, OCST, C & G
 
0.371 397810.77 0.00 0.00 0.0
Work Order 08-13-14
Work Began 00-00-00
Work Completed  
Time Computed 08-29-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0138-15-010
SOUTHWEST ENVIRONMENT SERVICES LLC (0.57%)
PANOLA SIGN & BARRICADE, INC.(0.74%)
MAC TRANSPORTATION, LTD, L.L.P.(3.85%)
STRIPING TECHNOLOGY, L.P.( 24.55%)
Contract # 07143022
Totals 541821.27 0.00 0.00 0.0

CountyGREGG
Highway US 259
From AT SYNERGY DR IN KILGORE
To 0.3 MI N OF FM 349
CSJ 0138-16-003
Proj ID NH 2013(912)
Work Type SBG WDN, HMAC BS & SURF, OCST, MBGF, SIGN
 
0.317 489748.16 454.50 432195.56 88.2
Work Order 09-09-13
Work Began 03-19-14
Work Completed  
Time Computed 03-17-14
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 96
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0138-16-003
ALTUS TRAFFIC MANAGEMENT LLC (0.69%)
STRIPING TECHNOLOGY, L.P.(3.69%)
DUSTIN ALLEN, INC. (2.12%)
TEX OP CONSTRUCTION, LP(1.19%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.71%)
GREGG WILLIAMS CONSTRUCTION(0.09%)
Contract # 08133040
Totals 489748.16 454.50 432195.56 88.2

CountyHENDERSON
Highway SH 31
From 0.34 MI W OF FM 773 (BEG C&G), E
To 1.1 MI W OF FM 1803(W) IN MURCHISON
CSJ 0164-01-068
Proj ID STP 2013(549)
Work Type PVMT RPR, PLNG, CAM, OCST, HARST, HMAC
 
7.862 4945961.90 35982.97 4653263.64 94.8
Work Order 06-26-13
Work Began 08-12-13
Work Completed  
Time Computed 07-12-13
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 176
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0164-01-068
DUSTROL, INC.(4.44%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.13%)
PENHALL COMPANY(0.14%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.21%)
STRIPING TECHNOLOGY, L.P.(2.94%)
VIKING CONSTRUCTION, INC.( 12.69%)
COX PAVING COMPANY, L.P. (4.71%)
Contract # 04133218
Totals 4945961.90 35982.97 4653263.64 94.8

CountySMITH
Highway US 69
From 0.2 MI S OF CUMBERLAND RD,S 0.57 MI
To 0.66 MI N OF TOLL 49
CSJ 0191-01-082
Proj ID CC 191-1-82
Work Type GR, STR, FLX BS, PVMT, SIGNS, SIGS, STRPG
 
0.567 2021972.96 675524.99 1285173.80 63.5
Work Order 03-13-14
Work Began 05-05-14
Work Completed  
Time Computed 03-29-14
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 91
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0191-01-082
TOTAL HIGHWAY MAINTENANCE, LLC (0.22%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.04%)
STRIPING TECHNOLOGY, L.P.(1.30%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.( 17.94%)
J & M CONTRACTING, COMPANY (2.02%)
TEX OP CONSTRUCTION, LP(4.56%)
Contract # 01143020
Totals 2021972.96 675524.99 1285173.80 63.5

CountyHENDERSON
Highway US 175
From 0.1 MI SE OF FM 804, SE
To CR 4712 (END OF C-S)
CSJ 0198-01-023
Proj ID NH 1402(195)
Work Type RECONSTR GR, STRS, BS, SURF & PAV M
 
6.695 39261003.89 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 605
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0198-01-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143055
Totals 39261003.89 0.00 0.00 0.0

CountyWOOD
Highway US 69
From 0.6 MI NW OF FM 779 IN GOLDEN, SE
To SL 564 IN MINEOLA
CSJ 0203-05-037
Proj ID C 203-5-37
Work Type GR, STRS, ACP BS & SURF, PVT MRK
 
4.207 2817127.02 608106.58 1954328.05 69.4
Work Order 08-09-13
Work Began 09-10-13
Work Completed  
Time Computed 08-25-13
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 102
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0203-05-037
BUYERS BARRICADES, INC.(0.66%)
AMERICAN REMEDIATION OPTIONS, INC. (1.95%)
WEST TEXAS RUMBLE STRIP(0.13%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.46%)
STRIPING TECHNOLOGY, L.P.(1.80%)
MAC TRANSPORTATION, LTD, L.L.P.(7.48%)
P.R. PARKER COMPANY, INC.(0.42%)
Contract # 06133223
Totals 2817127.02 608106.58 1954328.05 69.4

CountyANDERSON
Highway US 79
From 1.6 MI SW OF LP 256 IN PALESTINE, S
To 0.4 MI SW OF FM 645
CSJ 0205-07-043
Proj ID NH 2008(510)
Work Type GR, BS, ASPH PVT, SIGS, ILLUM, SIGNS
 
8.601 41986850.19 977627.68 16862160.08 40.1
Work Order 10-24-12
Work Began 11-12-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 880
Addl Days Granted 0
Working Days Charged 443
Percent Time Used 50
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-07-043
HIGHWAY TECHNOLOGIES, INC. (0.10%)
STRIPING TECHNOLOGY, L.P.(1.65%)
MAC TRANSPORTATION, LTD, L.L.P.(3.12%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.39%)
AMERICAN REMEDIATION OPTIONS, INC. (0.53%)
DANRIDGE CONSTRUCTION, LLC.(0.30%)
DUSTROL, INC.(0.20%)
WEST TEXAS RUMBLE STRIP(0.05%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.30%)
NORTH TEXAS REBAR, LLC (0.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.23%)
Contract # 09123003
Totals 41986850.19 977627.68 16862160.08 40.1

CountySMITH
Highway SH 64
From 0.1 MI W OF FM 2661, E
To 0.6 MI W OF FM 724 (NEAR CR 1184)
CSJ 0245-05-046
Proj ID STP 2013(225)
Work Type GR, SURF, BASE, ACP, PVT MRKG
 
1.191 2387571.56 2620.68 2295114.17 96.1
Work Order 07-08-13
Work Began 08-05-13
Work Completed  
Time Computed 07-24-13
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 93
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0245-05-046
HIGHWAY 19 CONSTRUCTION, LLC ( 25.78%)
STRIPING TECHNOLOGY, L.P.(1.24%)
MARCOM"S MOWING SERVICE, LLC (0.81%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.36%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.32%)
Contract # 05133033
Totals 2387571.56 2620.68 2295114.17 96.1

CountySMITH
Highway SH 64
From FM 3226 SE OF CHAPEL HILL, SE
To SH 135 NEAR ARP
CSJ 0245-06-076
Proj ID STP 2014(590)
Work Type GR, STRS, FLX BS, LVL - UP, OCST, HMAC SRF
 
8.294 3872443.98 15308.60 15308.60 0.3
Work Order 06-30-14
Work Began 08-21-14
Work Completed  
Time Computed 07-16-14
Contract Working Days 125
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 11
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0245-06-076
PANOLA SIGN & BARRICADE, INC.(0.60%)
DREWERY & WHEATON, LLC (2.51%)
J & M CONTRACTING, COMPANY ( 10.08%)
Contract # 04143017
Totals 3872443.98 15308.60 15308.60 0.3

CountyRUSK
Highway SH 64
From 0.17 MI W OF BS 64E IN HENDERSON,E
To 0.2 MI W OF US79/US259 (N MARSHALL)
CSJ 0245-08-040
Proj ID STP 2013(913)
Work Type GR, STRS, PLNG, HMA BS, C & G, SURF, PV MKG
 
0.338 2102152.24 0.00 763536.69 36.3
Work Order 08-08-13
Work Began 10-11-13
Work Completed  
Time Computed 08-24-13
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 75
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0245-08-040
STRIPING TECHNOLOGY, L.P.(6.47%)
ROBINSON CONSTRUCTION( 11.78%)
REYNOLDS & KAY, LTD. (8.20%)
TEX OP CONSTRUCTION, LP(0.66%)
Contract # 07133246
Totals 2102152.24 0.00 763536.69 36.3

CountyVAN ZANDT
Highway SH 64
From FM 858 NR BEN WHEELER, SE
To 0.1 MI SE OF FM 314
CSJ 0245-19-022
Proj ID STP 2012(765)
Work Type GR, FLX BS. LVL - UP, HMAC SURF, STRS
 
6.920 7358629.82 274067.51 4604008.36 62.5
Work Order 10-18-12
Work Began 12-03-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 172
Addl Days Granted 212
Working Days Charged 254
Percent Time Used 66
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0245-19-022
N-LINE TRAFFIC MAINTENANCE, L.P. (0.91%)
J. M. CONSTRUCTION (1.74%)
STRIPING TECHNOLOGY, L.P.(1.74%)
HIGHWAY 19 CONSTRUCTION, LLC (4.68%)
Contract # 08123040
Totals 7358629.82 274067.51 4604008.36 62.5

CountySMITH
Highway SH 110
From IN THE SW QUAD OF SH 110 & TOLL 49
To IN NORTHERN WHITEHOUSE
CSJ 0345-01-059
Proj ID STP 2014(633)
Work Type GRD, EMBANK, ILLUMINATN, WELCOME SIGN
 
0.110 120955.00 22650.00 39900.00 32.9
Work Order 06-13-14
Work Began 07-28-14
Work Completed  
Time Computed 06-29-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 26
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0345-01-059
SOUTH TEXAS ILLUMINATION, LLC( 19.53%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.81%)
Contract # 05143029
Totals 120955.00 22650.00 39900.00 32.9

CountyWOOD
Highway SH 154
From 1 MI N OF FM 288(LAKE FORK RES BR)S
To SH 37 (MAIN ST) IN QUITMAN
CSJ 0401-02-026
Proj ID STP 2013(118)
Work Type WDN GR, STRS, REPL BR, ACP BS & SURF, P
 
5.626 5801592.45 106266.48 5769782.70 99.9
Work Order 11-30-12
Work Began 03-04-13
Work Completed  
Time Computed 03-01-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 166
Percent Time Used 138
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 0401-02-026
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.80%)
BAHENA CONSTRUCTION CO.,INC. (7.81%)
STRIPING TECHNOLOGY, L.P.(1.03%)
BLACKTOPPER TECHNOLOGY, INC. (1.52%)
TEX OP CONSTRUCTION, LP(0.14%)
RK HALL, LLC ( 40.26%)
COWBELL TRAFFIC SERVICES, INC. (0.24%)
COX PAVING COMPANY, L.P. (2.53%)
DUSTIN ALLEN, INC. (0.31%)
FARR FOUNDATION, INC.(0.71%)
Contract # 10123007
Totals 5801592.45 106266.48 5769782.70 99.9

CountySMITH
Highway SH 31
From FM 850, E OF TYLER, E
To FM757
CSJ 0424-01-045
Proj ID STP 2013(914)
Work Type GRADING, OCST, STRUCTURES, PVMT MRKGS
 
6.631 3431987.29 1203888.11 2690356.71 78.6
Work Order 12-10-13
Work Began 01-13-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 85
Percent Time Used 111
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-045
DUSTROL, INC.(0.64%)
REYNOLDS & KAY, LTD. ( 13.96%)
PANOLA SIGN & BARRICADE, INC.(0.23%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.50%)
STRIPING TECHNOLOGY, L.P.(1.95%)
TJT CONSTRUCTION (2.50%)
Contract # 09133040
Totals 3431987.29 1203888.11 2690356.71 78.6

page 1 | page 2 | page 3