Monthly State Let Construction Report For Tyler District As Of Jan 11, 2017 Page 1 Of 3

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyANDERSON
HighwaySH 19
From3.6 MI N OF FM 837(HENDERSON C/L),S
To0.4 MI N OF FM 321 AT MONTALBA
CSJ0108-06-051
Proj IDSTP 2013(637)
Work TypeGR,STRS,HMA BS & SURF,OCST,LVL-UP
 
11.81312487715.876593908.4552.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-10-14
Work Began09-02-14
Work Completed
Time Computed07-26-14
Contract Working Days453
Addl Days Granted0
Working Days Charged296
Percent Time Used65
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0108-06-051
COLD CREEK CONSTRUCTION, LTD (0.82)
FORTSON CONTRACTING, INC. (0.45)
HIGHWAY 19 CONSTRUCTION, LLC (10.97)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35)
SAMMY G. SMALLWOOD (0.46)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.15)
STRIPING TECHNOLOGY, L.P. (1.23)
FARR FOUNDATION, INC. (0.64)
SAN-ANN-CO., INC. (0.04)
Contract #05143205
Totals12487715.870.006593908.4552.8

CountyVAN ZANDT ETC
HighwaySH 19 ETC
FromRAINS C/L, S
ToUS 80 IN FRUITVALE
CSJ0108-12-017
Proj IDSTP 2017(517)HES
Work TypeMILLED CENTERLINE
 
97.428716585.540.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0108-12-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173219
Totals716585.540.000.000.0

CountyANDERSON ETC
HighwayUS 287 ETC
FromFM 2706, E
ToFM 321
CSJ0122-04-037
Proj IDSTP 2016(290)
Work TypeSEAL COAT & PAVEMENT MARKINGS
 
170.36510343177.569110245.0388.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-15
Work Began08-01-16
Work Completed
Time Computed00-00-00
Contract Working Days95
Addl Days Granted3
Working Days Charged115
Percent Time Used117
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0122-04-037
STRIPE-A-ZONE, INC. (11.48)
BRYDL CONTRACTING, INC. (0.74)
FLASHER EQUIPMENT COMPANY (1.13)
Contract #11153216
Totals10343177.560.009110245.0388.2

CountyANDERSON ETC
HighwayUS 287 ETC
FromFREESTONE C/L SE
To1.7 MI SE OF FM 488 (FREESTONE CL),
CSJ0122-04-038
Proj IDSTP 2017(355)
Work TypeSEAL COAT & PAVEMENT MARKINGS
 
216.06311487064.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0122-04-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173005
Totals11487064.250.000.000.0

CountyRUSK
HighwayUS 259
FromSL 571 ,S
ToSH 64 (TRAFFIC STAR) IN HENDERSON
CSJ0138-03-142
Proj IDNH 1602(129)
Work TypeBASE REPAIR, OCST, PFC
 
2.3724277728.084063999.1795.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-20-16
Work Began08-18-16
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged77
Percent Time Used171
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0138-03-142
COWBELL TRAFFIC SERVICES, INC. (0.11)
O. TREVINO CONSTRUCTION, LLC (2.19)
PANOLA SIGN & BARRICADE, INC. (0.22)
L. S. EQUIPMENT CO., INC. (8.97)
STRIPING TECHNOLOGY, L.P. (1.21)
STRIPING SYSTEMS, INC. (0.03)
W.O.E. CONSTRUCTION (0.07)
TNT MASONRY, INC. (0.00)
Contract #05163210
Totals4277728.080.004063999.1795.7

CountyHENDERSON
HighwaySH 31
FromAT WB TRINITY RIVER, W OF TRINIDAD
ToSTR #101080016303040
CSJ0163-03-048
Proj IDBR 1502(473)
Work TypeGR,RIPRAP,BCKFIL,PNT,DECK RPR,MGBF
 
0.8572305309.452276746.6198.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-29-16
Work Began03-15-16
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged88
Percent Time Used97
Contractor(s)
OLYMPUS PAINTING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0163-03-048
ACCESS RIGGING LLC (16.04)
DALLAS LITE AND BARRICADE INC. (0.23)
STRIPING TECHNOLOGY, L.P. (1.53)
BATTERSON,LLP (0.72)
WASKEY SERVICES LLC (2.29)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.90)
TRAFFIC CALMING USA, LLC. (20.38)
Contract #12153015
Totals2305309.450.002276746.6198.7

CountySMITH
HighwayUS 271
FromFM 2015, N OF TYLER, S
To0.4 MI S OF SS 147 (OAKWOOD)
CSJ0165-01-101
Proj IDNH 2016(191)
Work TypePLNG,BR JNT RPR,ACP LVL UP,SURF TRT
 
4.5424372572.153591920.4382.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-26-16
Work Began07-14-16
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged84
Percent Time Used152
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0165-01-101
ACU CONSTRUCTION LLC (1.76)
HARRIS TRUCKING SERVICES (0.64)
STRIPING TECHNOLOGY, L.P. (3.77)
FLEX SUPPLY, LLC (0.26)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.60)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.15)
CHEROKEE SERVICES (0.87)
STRIPING SYSTEMS, INC. (0.03)
TEX OP CONSTRUCTION, LP (0.42)
Contract #03163208
Totals4372572.150.003591920.4382.7

CountyHENDERSON
HighwayUS 175
From0.1 MI SE OF FM 804, SE
ToCR 4712 (END OF C-S)
CSJ0198-01-023
Proj IDNH 1402(195)
Work TypeRECONSTR GR, STRS, BS, SURF & PAV M
 
6.69539261003.8927191518.9269.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-21-14
Work Began04-06-15
Work Completed
Time Computed00-00-00
Contract Working Days605
Addl Days Granted5
Working Days Charged297
Percent Time Used48
Contractor(s)
A. L. HELMCAMP, INC.
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0198-01-023
DUSTIN ALLEN, INC. (0.36)
MURRAY CONSTRUCTION (0.22)
STRIPING TECHNOLOGY, L.P. (0.31)
SAN-ANN-CO., INC. (0.21)
KLP COMMERCIAL, LLC (4.91)
KENSAR LLC DBA S & S TRUCKING (1.88)
BIG CREEK CONSTRUCTION, LTD. (0.00)
ENVIRODREDGE (0.20)
RIOS TRUCKING CO. (0.00)
Contract #08143055
Totals39261003.890.0027191518.9269.2

CountyHENDERSON
HighwayUS 175
From1.1 MI E OF LP 60E @ LARUE, SE
To0.85 MI E OF FM 315, IN POYNOR
CSJ0198-02-027
Proj IDNH 2015(423)
Work TypeRECONSTR GR, STRS, BS, SURF & PAV M
 
4.73137849155.3122613286.1259.7
Work Order06-30-15
Work Began10-06-15
Work Completed
Time Computed07-16-15
Contract Working Days654
Addl Days Granted0
Working Days Charged258
Percent Time Used39
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-02-027
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20)
WOLFE CONSTRUCTION GROUP, INC. (0.83)
K & S UTILITY CONTRACTORS, INC. (4.02)
OTTO TRUCKING, INC. (3.31)
APAC-TEXAS, INC. (19.01)
BREDA COMPANY, INC. (2.68)
ANTIGO CONSTRUCTION, INC. (0.02)
LAYFIELD CONSTRUCTION, INC (0.40)
A BROTHERS MILLING, LLC (0.18)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.18)
STRIPING TECHNOLOGY, L.P. (0.54)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.00)
MCL CONTRACTING, LLC (0.04)
Contract #04153201
Totals37849155.311250828.5222613286.1259.7

CountyHENDERSON
HighwayUS 175
From0.85 MI E OF FM 315, IN POYNOR
ToANDERSON C/L
CSJ0198-02-035
Proj IDC 198-2-35
Work TypeGR,SUB BS,BS,HMAC,DRAIN STRS,SIGNS
 
0.9237052578.981980085.9928.0
CountyANDERSON
HighwayUS 175
From1.9 MI S OF FM 315 (HENDERSON C/L)
To0.5 MI NW OF SH 155 AT FRANKSTON
CSJ0198-03-027
Proj IDNH 1502(561)
Work TypeGR,SUB BS,BS,HMAC,DRAIN STRS,SIGNS
 
3.80420312971.665244727.6725.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-17-16
Work Began05-04-16
Work Completed
Time Computed00-00-00
Contract Working Days571
Addl Days Granted0
Working Days Charged105
Percent Time Used18
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0198-02-035
STRIPING TECHNOLOGY, L.P. (0.36)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.16)
MARCOM"S MOWING SERVICE, LLC (0.21)
FORTSON CONTRACTING, INC. (0.04)
STRIPING SYSTEMS, INC. (0.00)
FARR FOUNDATION, INC. (0.32)
Contract #12153202
Totals27365550.640.007224813.6626.4

CountyCHEROKEE
HighwayUS 69
FromSL 456 IN JACKSONVILLE, S
To0.058 MI N OF SL 62 IN RUSK
CSJ0199-01-081
Proj IDNH 1502(130)
Work TypeSTRS,PLNG,HMAC,OCST,PFC,MBGF,BS RPR
 
10.72211063277.5910150129.0591.7
Work Order08-24-15
Work Began11-04-15
Work Completed
Time Computed09-24-15
Contract Working Days180
Addl Days Granted0
Working Days Charged169
Percent Time Used93
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0199-01-081
DUSTIN ALLEN, INC. (0.20)
BAHENA CONSTRUCTION CO.,INC. (1.17)
PANOLA SIGN & BARRICADE, INC. (0.18)
SOUTHWEST ENVIRONMENT SERVICES LLC (12.26)
STRIPING TECHNOLOGY, L.P. (1.77)
B & E CONSTRUCTION INC. (9.96)
PLAIN DEALING TRUCKING COMPANY, INC. (0.00)
Contract #06153013
Totals11063277.5929324.3210150129.0591.7

CountyCHEROKEE
HighwayUS 69
From0.028 MI S OF FM 343 IN RUSK, S
To0.08 MI N OF SH 21 IN ALTO
CSJ0199-02-057
Proj IDNH 1502(277)
Work TypeSTRS,PLNG,HMAC,OCST,PFC,MBGF,BS RPR
 
10.0279380454.057422081.8179.1
Work Order08-20-15
Work Began01-04-16
Work Completed
Time Computed09-20-15
Contract Working Days180
Addl Days Granted10
Working Days Charged193
Percent Time Used101
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0199-02-057
STRIPING TECHNOLOGY, L.P. (1.99)
BAHENA CONSTRUCTION CO.,INC. (1.69)
PANOLA SIGN & BARRICADE, INC. (0.21)
SOUTHWEST ENVIRONMENT SERVICES LLC (13.91)
DUSTIN ALLEN, INC. (0.39)
PLAIN DEALING TRUCKING COMPANY, INC. (0.00)
B & E CONSTRUCTION INC. (11.46)
Contract #06153014
Totals9380454.05900007.417422081.8179.1

CountyCHEROKEE
HighwayUS 69
From2.0 MI N OF FM 1247,NEAR WELLS,S
To0.9 MI S OF FM 1247 (ANGELINA C/L)
CSJ0199-03-028
Proj IDHP 2013(803)
Work TypeGRDG,STRS,BASE,OCST,SURF,PVT MRKG
 
2.89617687832.870.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-05-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days350
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0199-03-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06163005
Totals17687832.870.000.000.0

CountySMITH
HighwayFM 1253
FromCR 462(S), 1.3 MI N OF FM 857, S
ToFM 1805
CSJ0203-08-015
Proj IDSTP 1502(278)HES
Work TypeSUBGRADE WIDEN, LEVEL-UP, OCST
 
12.0097499499.386029140.5780.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-10-15
Work Began09-18-15
Work Completed
Time Computed00-00-00
Contract Working Days311
Addl Days Granted0
Working Days Charged268
Percent Time Used86
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0203-08-015
PANOLA SIGN & BARRICADE, INC. (0.62)
STRIPING TECHNOLOGY, L.P. (1.44)
AMERICAN REMEDIATION OPTIONS, INC. (6.84)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.47)
Contract #06153028
Totals7499499.380.006029140.5780.3

CountyANDERSON
HighwayUS 79
From1.6 MI SW OF LP 256 IN PALESTINE, S
To0.4 MI SW OF FM 645
CSJ0205-07-043
Proj IDNH 2008(510)
Work TypeGR,BS,ASPH PVT, SIGS, ILLUM,SIGNS
 
8.60141986850.1936605654.6087.1
Work Order10-24-12
Work Began11-12-12
Work Completed
Time Computed11-09-12
Contract Working Days880
Addl Days Granted0
Working Days Charged880
Percent Time Used100
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-07-043
HIGHWAY TECHNOLOGIES, INC. (0.10)
STRIPING TECHNOLOGY, L.P. (1.65)
MAC TRANSPORTATION, LTD, L.L.P. (3.12)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.39)
AMERICAN REMEDIATION OPTIONS, INC. (0.53)
DANRIDGE CONSTRUCTION, LLC. (0.30)
DUSTROL, INC. (0.20)
WEST TEXAS RUMBLE STRIP (0.05)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.68)
NORTH TEXAS REBAR, LLC (0.02)
TOTAL HIGHWAY MAINTENANCE, LLC (0.23)
P.R. PARKER COMPANY, INC. (0.00)
TEX OP CONSTRUCTION, LP (0.01)
DIRECTIONAL DRILLING (0.01)
DFW REBAR, INC. (0.01)
Contract #09123003
Totals41986850.19334782.4736605654.6087.1

CountyCHEROKEE
HighwayUS 79
From3 MI W OF SH 110, W
To0.3 MI E OF SH 204(DOGWOOD) J'VILLE
CSJ0206-04-039
Proj IDNH 2016(997)
Work TypePLN,CM TRT,BS&SURF,RF RL,MBGF,PV MK
 
3.2585778866.012784242.3348.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-19-16
Work Began07-06-16
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged98
Percent Time Used65
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0206-04-039
SOUTHWEST ENVIRONMENT SERVICES LLC (0.40)
ACU CONSTRUCTION LLC (2.11)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.49)
STRIPING TECHNOLOGY, L.P. (2.55)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.23)
ISAACS CONSTRUCTION SERVICES, LLC. (0.43)
Contract #04163211
Totals5778866.010.002784242.3348.1

CountyRUSK
HighwayUS 79
FromSL 571 IN HENDERSON, SW
ToFM 839
CSJ0206-07-058
Proj IDSTP 1502(281)HES
Work TypeSTRS, WDNG, OCST, ACP, PVT MRKGS
 
3.0506661253.883399886.3351.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-24-15
Work Began01-15-16
Work Completed
Time Computed00-00-00
Contract Working Days263
Addl Days Granted2
Working Days Charged96
Percent Time Used36
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0206-07-058
J & M CONTRACTING, COMPANY (5.38)
TEXOP CONSTRUCTION (0.67)
PANOLA SIGN & BARRICADE, INC. (0.39)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.50)
STRIPING TECHNOLOGY, L.P. (0.82)
STRIPING SYSTEMS, INC. (0.01)
DREWERY & WHEATON, LLC (1.65)
FREDONIA CONSTRUCTION SERVICES (1.42)
Contract #06153251
Totals6661253.880.003399886.3351.0

CountyRUSK
HighwaySH 43
From4 MI S OF FM 2658 (CR 2136), NE
To2.2 S OF FM 2658 (BEGIN C-S)
CSJ0207-02-027
Proj IDSTP 2016(364)
Work TypeSURF TREAT,ACP SURF,MBGF,PVMT MRKG
 
8.2854691110.394671285.5199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-15-16
Work Began07-18-16
Work Completed
Time Computed00-00-00
Contract Working Days57
Addl Days Granted0
Working Days Charged87
Percent Time Used152
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0207-02-027
COWBELL TRAFFIC SERVICES, INC. (0.20)
DUSTIN ALLEN, INC. (5.81)
EAST TEXAS BRIDGE, INC. (5.38)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (12.05)
PANOLA SIGN & BARRICADE, INC. (0.25)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.23)
STRIPING TECHNOLOGY, L.P. (2.56)
STRIPING SYSTEMS, INC. (0.03)
B & E CONSTRUCTION INC. (2.89)
Contract #02163232
Totals4691110.390.004671285.5199.9

CountySMITH
HighwaySH 31
FromFM 757, E
To2.5 MI W OF FM 2767(NR MULEY BRC),E
CSJ0424-01-048
Proj IDSTP 2013(640)
Work TypeGR,STRS,ACP BS & SURF,PVT MRK
 
10.7347802782.955022517.4664.3
Work Order10-29-14
Work Began11-18-14
Work Completed
Time Computed11-14-14
Contract Working Days328
Addl Days Granted0
Working Days Charged261
Percent Time Used79
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-048
SOUTHWEST ENVIRONMENT SERVICES LLC (4.79)
ALTUS TRAFFIC MANAGEMENT LLC (0.48)
STRIPING TECHNOLOGY, L.P. (2.44)
C.S. TREE SERVICE (0.48)
FORTSON CONTRACTING, INC. (0.09)
MURRAY CONSTRUCTION (0.22)
TEX OP CONSTRUCTION, LP (0.79)
J & I TRUCKING CO (1.05)
HOPE SERVICES, INC. (0.70)
HARRIS TRUCKING SERVICES (1.40)
ISAACS CONSTRUCTION SERVICES, LLC. (0.93)
Contract #08143053
Totals7802782.95171026.505022517.4664.3

CountySMITH
HighwaySH 31
FromSL 323, IN TYLER, E
ToFM 850 (E)
CSJ0424-01-053
Proj IDSTP 1602(359)
Work TypeOCST, 2" PFC
 
2.9461795043.6587505.964.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0424-01-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07163028
Totals1795043.650.0087505.964.8

page 1 | page 2 | page 3